In addition to the main tank closure, the splash pad and kiddie pool are closed due to unexpected heating issues. While we work to replace the heat exchanger unit, the entire facility is closed and swimming lessons are cancelled. We expect to reopen the splash pad and kiddie pool in mid-May. Check back for updates.
The main tank at the Seven Oaks Pool is scheduled to close for major capital work, including:
- Concrete/structural repair
- Waterproofing
- Tile replacement:
- Main tank
- Part of the pool deck
Minor splash pad repairs will also be completed (6-week closure, timing to be determined).
Timeline
- Start date: December 14, 2025
- Estimated timeline: 12-14 months
Impact to public
The facility will be operational, with the exception of the following:
- Main tank: closed beginning December 14, 2025 for 12-14 months
- Splash pad: remains operational, except for a 6-week period, timing to be determined
- Kiddie pool: remains operational, except for a 6-week period, timing to be determined
- Swimming lessons: lessons requiring the main tank will not be scheduled
- Rentals: efforts will be made to temporarily relocate groups who rent pool space
Background
Funding
- $3.5 million allocated
- Part of the Recreation and Library Investment Strategy, funded by the Government of Manitoba
Construction
- Tender closed: August 26, 2025
- Contract award: Anticipated October 2025
Recent renewal projects at Seven Oaks Pool:
- Roof replacement – Completed July 2024
- Pool redevelopment – Completed March 2019
- New family change rooms
- Universally accessible washrooms
- Enhanced public lobby
- New meeting space
- Small teach pool
- New indoor spray pad
- Concrete restoration
- Air handling unit replacement