Prioritization of Major Capital Projects Approved by Executive Policy Committee for Federal & Provincial Cost-sharing

Released: September 17, 2019 at 1:30 p.m.

Winnipeg, MB – Executive Policy Committee unanimously approved the prioritization of several major City of Winnipeg infrastructure projects for cost-sharing with federal and provincial governments Mayor Brian Bowman said today.

“The last time we collaborated as a Council to prioritize major infrastructure projects, and worked with our federal and provincial government partners, we got the Waverly underpass built,” said Mayor Brian Bowman. “Today, Executive Policy Committee is recommending for Council’s review the prioritization of four capital projects for federal-provincial cost sharing with a significant focus on wastewater upgrades.”

The administrative report unanimously adopted by Executive Policy Committee prioritizes and recommends the approval to submit four capital projects for federal and provincial funding under the Investing in Canada Infrastructure Program.

The Investing in Canada Infrastructure Program is the current ten year federal infrastructure funding program. This program is expected to make over $1 billion in federal contribution funding available over ten years for Manitoba infrastructure projects.

Under this program, Executive Policy Committee has adopted and is recommending to Council the prioritization and approval of the following four capital projects:

  • The North End Water Pollution Control Centre (NEWPCC) Upgrade: Headworks Facilities Project;
  • The North End Water Pollution Control Centre (NEWPCC) Upgrade: Biosolids Facilities Project;
  • The South Winnipeg Recreation Campus: Phase One – Recreation Centre Project; and
  • The St. James Civic Centre – Facility Expansion Project.

The combined cost of these four capital projects is estimated at $994 million.

The two highest prioritized capital projects recommended by the public service for cost-sharing under the Investing in Canada Infrastructure Program are wastewater treatment projects. The cost of these two projects is estimated to be $909 million representing 91% of the $994 million total cost of all four projects.

It is expected eligible costs for projects approved through the Investing in Canada Infrastructure Program would be cost-shared by each level of government with the federal government contributing 40%, the provincial government contributing 33.33%, and the city government contributing 26.67% of the total eligible costs.

If approved under the Investing in Canada Infrastructure Program, these capital projects would be eligible for federal and provincial partnership funding of up to $643.4 million which would significantly reduce the financial burden on Winnipeg residents.

When prioritizing and recommending the four projects, the public service followed asset management processes as well as criteria cited by Executive Policy Committee which required projects to have been previously identified in the city’s capital budgets or five-year forecast. It also required that projects fit within the financial constraints of the City of Winnipeg capital budget.

While the City of Winnipeg’s infrastructure deficit has been reduced over the last several years, its current infrastructure deficit is estimated at $6.9 billion. Within this infrastructure deficit are 22 major capital projects requiring $4.5 billion in funding.

The Mayor said if the prioritization and recommendations adopted by Executive Policy Committee today are ultimately approved by Council it would provide a significant amount of financial support to the City of Winnipeg’s efforts to meet provincial regulatory requirements for the treatment and removal of nutrients determined harmful to Lake Winnipeg.

The administrative report is publicly available on the City of Winnipeg’s Decision Making Information System (DMIS). It will be considered by Council at the September 26, 2019 meeting.

Was this information helpful?

How can we make this web page better?

Information collected will be used to improve our website. Do not use this form to submit a request for service or information because it will not be forwarded to departments for response. To submit a request for service or information, contact 311.

This form is not intended to collect personal information; however, any personal information you choose to include in your comments is collected by the City of Winnipeg under the authority of section 36(1)(b) of the Freedom of Information and Protection of Privacy Act for the purpose of improving our website and will not be used or disclosed for any other purposes, except as authorized by law. Contact the Corporate Access and Privacy Officer by mail (City Clerk’s Department, Susan A. Thompson Building, 510 Main Street, Winnipeg MB, R3B 1B9) or by telephone (311) if you have any questions about the collection of this information.