Roadworks on Fermor Avenue concluding

La présente page n’a pas été traduite. Veuillez consulter la version anglaise ci-dessous.

Winnipeg, MB – Today, Mayor Brian Bowman joined Councillor Matt Allard, Chairperson of the Standing Policy Committee on Infrastructure Renewal and Public Works, and Councillor Brian Mayes, St. Vital, to announce the conclusion of roadwork on Fermor Avenue, from St. Anne’s Road to Archibald Street.

The extensive, multi-faceted project was constructed in phases over the last two years to minimize traffic disruptions. The project includes the reconstruction of Fermor Avenue between St. Anne’s Road to Archibald Street and the rehabilitation of the bridge over the Seine River, among other improvements.

On Sunday, November 3, traffic on Fermor Avenue, between St. Anne’s Road and Archibald Street will begin operating on two through-lanes in the westbound direction of travel. The two through-lanes in the eastbound direction will fully reopen to traffic in November. Once completed, the new smoother roadway will provide improved safety and travel times for motorists.

“It is fantastic to see this stretch of construction complete so Fermor Avenue can get back to moving people efficiently along one of the City’s major regional arteries,” said Mayor Brian Bowman. “Winnipeggers have been patient in all areas of the City as we continue historic investments into fixing our roads and the results can be clearly seen here in St. Vital.”

“Since I was elected, I heard from many area residents that the condition of Fermor Avenue was a major concern to them,” said Councillor Matt Allard, Chairperson of the Standing Policy Committee on Infrastructure Renewal and Public Works. “I appreciate everyone’s patience as we undertook these much needed infrastructure improvements which will improve safety and travel times for those commuting in the area.”

“I am pleased that this project is finally coming to completion,” said Councillor Brian Mayes, St. Vital. “I wish to thank former Chair of Finance Marty Morantz for his support and leadership of this project. This project modernizes the road and much improves safety in the area.”

Funded from the Regional Streets Renewal Program and the Waterways Crossings and Grade Separations Program, the project cost $29.6 million.

For more information, please see: City of Winnipeg – Fermor Avenue Bridge over Seine River Rehabilitation and Roadworks

Ces renseignements sont-ils utiles?

Comment pourrait-on améliorer cette page Web?

Les renseignements recueillis serviront à l’amélioration de notre site Web. Prière de ne pas se servir de ce formulaire pour soumettre une demande de service ou de renseignements, car la demande ne sera pas transmise au service en question. Pour soumettre une demande de service ou de renseignements, veuillez communiquer avec le 311.

Le présent formulaire ne vise pas à recueillir des renseignements personnels. Cependant, les renseignements personnels que vous choisissez d’inclure dans vos commentaires sont recueillis par la Ville de Winnipeg en conformité avec l’alinéa 36(1)b) de la Loi sur l’accès à l’information et la protection de la vie privée dans le but d’améliorer son site Web et ne seront ni utilisés ni divulgués pour d’autres raisons, sauf dans les cas où cela est autorisé par la loi. Communiquez avec l’agent de l’accès à l’information et de la protection de la vie privée de la Ville par courrier au Bureau du greffier, immeuble Susan-A.-Thompson, 510, rue Main, Winnipeg (Manitoba) R3B 1B9, ou par téléphone au 311 si vous avez des questions sur la collecte de ces renseignements.