Road Construction List
The roadway construction list provides project information in alphabetical order by street name.
Project information is available by location in both map and list format . Please see the regional street lane closures page for information on current lane closures on major streets.
How to use the construction list
Click on the + beside the project name. A dropdown box will appear with these project details:
type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
estimated to start,
estimated to end,
approximate percentage completed:
Pre-Construction – Construction phase has not started.
0% – Construction contract is in place, but crews have not mobilized to the site.
5% – Crews have mobilized to the site and construction has just begun.
10% 90% – An approximation of progress; construction is well underway.
95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
consultant information, and
contractor information.
You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.
Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.
City of Winnipeg - Public Works Capital Projects
(Last updated on March 5, 2021 @ 5:30 PM)
+
Aikins St - Enniskillen Av / McAdam Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 27/2020
Estimated to end
Fall 2021
Approx. % completed
70
Consultant
AECOM Canada Ltd
Contractor
J.C. Paving Ltd.
+
Archibald St - Messier St / Doucet St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
To Be Determined
Additional information
Click here
+
Archibald St - Plinguet St / Messier St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
To Be Determined
Additional information
Click here
+
Archibald St - St Catherine St / Elizabeth Rd
View Map
Facility type
Pedestrian / Cycling
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
To Be Determined
Additional information
Click here
+
Archibald St - St Catherine St / Elizabeth Rd
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
To Be Determined
Additional information
Click here
+
Arden Av / St Michael Rd - St Marys Rd / Pulberry St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Ashwood Cv - Sweetwater By / End
View Map
Facility type
Street
Type of work
Asphalt Overlay
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Ashworth St S - Warde Av/Baisinger Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Mid May 2020
Estimated to end
Fall 2020
Approx. % completed
Planned
Consultant
City Of Winnipeg - Streets Maintenance Division
Contractor
City Of Winnipeg - Centralized Services
+
Barratt Av - Clifton St/Spruce St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Beecher Av - Ferrier St/Swailes Av
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Booth Dr - Bruce Av / Portage Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 22/2020
Estimated to end
Summer 2021
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
J.C. Paving Ltd.
+
Braeside Pl - Point West Dr / End
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Spring 2021
Estimated to end
Summer 2021
Approx. % completed
0
Consultant
KGS Group Limited
Contractor
Maple Leaf Construction Ltd.
+
Broadway - Osborne St / Main St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Bruce Av - Ainslie St/Moray St
View Map
Facility type
Sidewalk
Type of work
New - Sidewalk Construction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Bruce Av - Ainslie St/Moray St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Bruce Av - Rita St/Ainslie St
View Map
Facility type
Sidewalk
Type of work
New - Sidewalk Construction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Chalmers Av - Watt St/Brazier St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Mid May 2020
Estimated to end
Summer 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Streets Maintenance Division
Contractor
City Of Winnipeg - Centralized Services
+
Chudley St - Tyndall Av/Manitoba Av
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Colony St - Portage Av / St Mary Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Cormorant By - Edgewater Dr / Edgewater Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Corydon Av - Borebank St/Brock St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 19/2020
Estimated to end
Summer 2021
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Additional information
Click here
+
Corydon Av - Cambridge St / Thurso St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Contractor
Maple Leaf Construction Ltd.
Additional information
Click here
+
Corydon Av - Cordova St/Lanark St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 19/2020
Estimated to end
Summer 2021
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Additional information
Click here
+
Corydon Av - Thurso St / Stafford St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 11/2020
Estimated to end
Summer 2021
Approx. % completed
70
Consultant
Stantec Consulting Ltd
Contractor
Maple Leaf Construction Ltd.
Additional information
Click here
Document
+
Corydon Av/Fleet Av - Oak St/Ash St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Summer 2021
Approx. % completed
Deferred
Consultant
WSP Canada Inc.
Contractor
Wintec Building Services Inc.
Document
+
Dakota St - Beliveau Rd / St Marys Rd
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Dakota St - Bishop Grandin Bv / Beliveau Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Day St - Pandora St / Regent Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
+
Des Meurons St - Carriere Av / Morier Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 20/2020
Estimated to end
Summer 2021
Approx. % completed
50
Consultant
Dillon Consulting Limited
Contractor
Wintec Building Services Inc.
Document
+
Des Meurons St - Goulet St / Marion St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Donald - Broadway / Gertrude Av (not including Bridge)
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
Bituminex Paving Ltd
+
Donald - Broadway / Gertrude Av (not including Bridge)
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
Bituminex Paving Ltd
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Dufferin Av - Sinclair St/Arlington St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Spring 2021
Estimated to end
Summer 2021
Approx. % completed
0
Consultant
KGS Group Limited
Contractor
Wintec Building Services Inc.
+
Dunkirk Dr - Fermor Av / Norberry Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Contractor
Bituminex Paving Ltd
Additional information
Click here
+
Dunkirk Dr - Fermor Av / St Marys Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Contractor
Bituminex Paving Ltd
Additional information
Click here
+
Dunkirk Dr - Norberry Dr / St Marys Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Contractor
Bituminex Paving Ltd
Additional information
Click here
+
Durward St - Templeton Av/Tully Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Spring 2021
Estimated to end
Summer 2021
Approx. % completed
0
Consultant
KGS Group Limited
Contractor
Wintec Building Services Inc.
+
Edmonton St - Ellice Av / Cumberland Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Ellice Av - Garry St / Donald St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Erin St - Notre Dame Ave / Sargent Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
Additional information
Click here
+
Erin St - Sargent Av / Wolever Ave
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
Additional information
Click here
+
Gallagher Av W - Keewatin St/Dee St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Spring 2021
Estimated to end
Summer 2021
Approx. % completed
0
Consultant
KGS Group Limited
Contractor
Wintec Building Services Inc.
+
Goulet St - Braemar Av / Youville St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Graham Av - Hargrave St / Carlton St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Contractor
J.C. Paving Ltd.
+
Grant Av - Montrose St / Lanark St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Grant Av - Montrose St / Queenston St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Grosvenor Av/Corydon Av - Oxford St/Waverley St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Summer 2021
Approx. % completed
Deferred
Consultant
WSP Canada Inc.
Contractor
Wintec Building Services Inc.
Document
+
Hargrave St - York Av / Broadway
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
Bituminex Paving Ltd
Additional information
Click here
+
Henderson Hw - McLeod Av / Leighton Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Higgins Av - Mordaunt St/Annabella St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Hobbs Cr - London St/Antrim Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Mid May 2020
Estimated to end
Summer 2021
Approx. % completed
70
Consultant
City Of Winnipeg - Streets Maintenance Division
Contractor
City Of Winnipeg - Centralized Services
+
Inkster Bv - McKenzie St / Arlington St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
John Forsyth Rd - Baisinger Dr/Dakota St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Spring 2021
Estimated to end
Summer 2021
Approx. % completed
0
Consultant
KGS Group Limited
Contractor
Maple Leaf Construction Ltd.
+
Johnson Av W - Levis St / Henderson Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Additional information
Click here
+
Jubilee Av - Osborne St / Pembina Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Additional information
Click here
+
Keewatin St - Adsum Dr / Inkster Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Keewatin St - Selkirk Av / Logan Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
WSP Canada Inc.
+
King Edward St - Hyde Av / Logan Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
WSP Canada Inc.
+
King Edward St - Hyde Av / Logan Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
WSP Canada Inc.
+
Kingston Rw - Edinburgh St / Rosewarne Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Kingston Rw - Rosewarne Av / St Marys Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Kirkfield St - Portage Av / McBey Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 1/2020
Estimated to end
Summer 2021
Approx. % completed
90
Consultant
WSP Canada Inc
Contractor
J.C. Paving Ltd.
Document
+
Lagimodiere Bv - Fermor Av / Cottonwood Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lagimodiere Bv - Regent Av W / Almey Av
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Mid May 2020
Estimated to end
Summer 2021
Approx. % completed
30
+
Lagimodiere Bv - Springfield Rd / 200m S of Headmaster Rw
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
WSP Canada Inc.
+
Lagimodiere Bv - Springfield Rd / 200m S of Headmaster Rw
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
WSP Canada Inc.
+
Lagimodiere Bv SB - Reenders Dr / Regent Av W
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Contractor
Borland Construction
+
Lakeglen Dr - Lake Lindero Rd/Lake Lindero Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Mid May 2020
Estimated to end
Summer 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Streets Maintenance Division
Contractor
City Of Winnipeg - Centralized Services
+
Laurel By - Diplomat Dr/Hillhouse Rd
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Laurel By - Hillhouse Rd / Diplomat Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Spring 2021
Estimated to end
Summer 2021
Approx. % completed
0
Consultant
KGS Group Limited
Contractor
Wintec Building Services Inc.
+
Leila Av - McPhillips St / McGregor St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Leila Ave - McPhillips St / McGregor St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Leila Ave - McPhillips St / McGregor St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lindenwood Dr W - Brentcliffe Dr/Forestgate Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
50
+
Lindenwood Dr W - Forestgate Av/Lindmere Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
September 7/2020
Estimated to end
Summer 2021
Approx. % completed
50
Consultant
KGS Group Limited
Contractor
Maple Leaf Construction Ltd.
Document
+
Logan Av - Disraeli Fwy / Main St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lyndale Dr - Claremont Av/Birchdale Av
View Map
Facility type
Street
Type of work
River Bank Restoration
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
TREK Geotechnical Inc.
+
Marwood Cr - Edgemont Dr / Edgemont Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
McGregor St - Church Av / Mountain Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
McGregor St - Seven Oaks Av / McAdam Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
McPhillips St - Machray Av / Mountain Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Meredith By - Templeton Av / Templeton Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Spring 2021
Estimated to end
Summer 2021
Approx. % completed
0
Consultant
KGS Group Limited
Contractor
Wintec Building Services Inc.
+
Michelle Jean Park - Lisgar Av / Hallet St
View Map
Facility type
Pedestrian / Cycling
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Mountain Ave - Arlington St / McPhillips St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Munroe Av - Raleigh St / Watt St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Additional information
Click here
+
Munroe Av - Watt St / Henderson Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Additional information
Click here
+
Myles Robinson Wy - Desjardins Dr/Island Lakes Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Spring 2021
Estimated to end
Summer 2021
Approx. % completed
0
Consultant
KGS Group Limited
Contractor
Maple Leaf Construction Ltd.
+
Nairn Av - Stadacona St / Watt St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Northwest Hydro Corridor Pathway - Leila Av / Church Av
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Oakhurst Cr - Monty Hall Dr/Monty Hall Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Spring 2021
Estimated to end
Summer 2021
Approx. % completed
0
Consultant
KGS Group Limited
Contractor
Wintec Building Services Inc.
+
Oakleaf Dr - Avalon Rd/Riel Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Spring 2021
Estimated to end
Summer 2021
Approx. % completed
0
Consultant
KGS Group Limited
Contractor
Maple Leaf Construction Ltd.
+
Osborne St - Hethrington Av/Rathgar Av
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Pandora Ave E - Day St / Wayoata St
View Map
Facility type
Pedestrian / Cycling
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
+
Pandora Ave E - Day St / Wayoata St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
+
Park Lane Av - Hekla Av / Park Lane Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Pembina Hw - De Leglise Av / Ducharme Av
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Additional information
Click here
+
Pembina Hw - Ducharme Av / De Leglise Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Additional information
Click here
+
Pembina Hw - McGillivray Bv / Chevrier Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Additional information
Click here
+
Pembina Hw - McGillivray Bv / Chevrier Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Additional information
Click here
+
Pincarrow Pt - Scurfield Bv/Eglinton Cr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Spring 2021
Estimated to end
Summer 2021
Approx. % completed
0
Consultant
KGS Group Limited
Contractor
Maple Leaf Construction Ltd.
+
Pioneer Av - Westbrook St / Main St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Portage Av - David St / Knox St
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
WSP Canada Inc.
+
Portage Av - Main St / Memorial Bv
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Spring 2021
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Portage Av - Main St / Memorial Bv
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Spring 2021
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Portage Av - St Charles St / David St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
WSP Canada Inc.
+
Portage Av - Woodlawn St / Century St
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Portage Av -St James St / Moorgate St
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Portage Ave WB - Knox St / St Charles St
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Summer 2021
Estimated to end
Summer 2021
Approx. % completed
Planned
Consultant
WSP Canada Inc.
+
Redwood Av - Salter St / Main St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Regent Av W - Plessis Rd / Rougeau Av
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Contractor
Borland Construction
+
Regent Av W - Plessis Rd / Rougeau Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Contractor
Borland Construction
+
Regis Dr - Charing Cross Cr / Paddington Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
River Av - Osborne St / Wellington Cr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Roblin Blvd - Berkley St / Dieppe Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Additional information
Click here
+
Roblin Blvd - Berkley St / Dieppe Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Additional information
Click here
+
Roblin Blvd - Dieppe St / PTH101
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 8/2020
Estimated to end
Fall 2021
Approx. % completed
80
Consultant
Stantec Consulting Ltd
Contractor
Bituminex Paving Ltd
Additional information
Click here
Document
+
Roblin Blvd - Dieppe St / PTH101
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 8/2020
Estimated to end
Summer 2021
Approx. % completed
80
Consultant
Stantec Consulting Ltd
Contractor
Bituminex Paving Ltd
Additional information
Click here
Document
+
Roblin Blvd - Dieppe St / PTH101
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 8/2020
Estimated to end
Fall 2021
Approx. % completed
80
Consultant
Stantec Consulting Ltd
Contractor
Bituminex Paving Ltd
Additional information
Click here
Document
+
Ross Av - Paulin St / Ellen St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Spring 2021
Estimated to end
Summer 2021
Approx. % completed
0
Consultant
KGS Group Limited
Contractor
Wintec Building Services Inc.
+
Sage Creek Path - De La Seigneurie Bv / Lagimodiere Bv
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Salter St - Cathedral Av / Slaw Rebchuk Bridge
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Contractor
Darco Enterprises
Additional information
Click here
+
Salter St - Jefferson Av / Inkster Bv
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Sargent Av - Edmonton St / Furby St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Sargent Av/Ellice Av - Ingersoll St/Sherburn St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
September 28/2020
Estimated to end
Summer 2021
Approx. % completed
5
Consultant
KGS Group Limited
Contractor
Asphaltec Paving
Document
+
Sargent Ave - Empress St / St James St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
Facility type
Pedestrian / Cycling
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Selkirk Av - Main St / Salter St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Selkirk Ave - Arlington St / McPhillips St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Additional information
Click here
Document
+
Sherburn St - Ellice Av/St Matthews Av
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Smith St - Notre Dame / Graham Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Southwalk By - Charing Cross Cr / Charing Cross Cr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
St Annes Rd - St Marys Rd / Fermor Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
St Mary Av - Hargrave St / Carlton St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
St Mary Av - Memorial Bv / Portage Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
St Mary Av - Memorial Bv / Portage Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
St Marys Av - Garry St / Smith St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
St Marys Av - Main St / Garry St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
St Marys Av - Smith St / Hargrave St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Stafford St - Corydon Ave/Pembina Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Additional information
Click here
+
Stradbrook Ave - Wellington Cr / Osborne St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Sturgeon Creek Path - Saskatchewan Av / Silver Av
View Map
Facility type
Pedestrian / Cycling
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Sturgeon Rd - Ness Av / Hallonquist Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Sturgeon Rd - Ness Av / Hallonquist Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Sweetwater By - Edgewater Dr / Edgewater Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Taylor Ave - Harrow St/Pembina Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Additional information
Click here
+
Taylor Ave - Wilton St / Harrow St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Additional information
Click here
+
Taylor Ave - Wilton St / Pembina Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Additional information
Click here
+
Taylor Ave - Wilton St / Pembina Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2020
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
+
Taylor Ave - Wilton St / Pembina Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Additional information
Click here
+
Thornhill By - Rochester Av/Rochester Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Spring 2021
Estimated to end
Summer 2021
Approx. % completed
5
Consultant
KGS Group Limited
Contractor
Wintec Building Services Inc.
Document
+
Transcona Bv - In close proximity to retention pond
View Map
Facility type
Sidewalk
Type of work
Slope Restoration
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
+
Trowbridge By - Malmsbury Av/Knotsberry By
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
0
Consultant
KGS Group Limited
Contractor
Maple Leaf Construction Ltd.
Document
+
Ulster St - Dalhousie Dr/Mapleridge Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Spring 2021
Estimated to end
Summer 2021
Approx. % completed
0
Consultant
KGS Group Limited
Contractor
Wintec Building Services Inc.
+
University Cr - Chancellor Matheson Rd / Pembina Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
+
University Cr - Pembina Hw / Sifton Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
+
University Cr - Sifton Rd / Chancellor Matheson Rd
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
+
Wall St - St Matthews Av / Wellington Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
Contractor
J.C. Paving Ltd.
Additional information
Click here
+
Wall St - Wellington Av / Notre Dame Ave
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
Contractor
J.C. Paving Ltd.
Additional information
Click here
+
Watercress Rd - Cormorant By / Edgewater Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Wellington Cr - River Av / Stradbrook Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Wellington Crescent Riverbank, Path and Roadway Project
View Map
Facility type
Street
Type of work
River Bank Restoration
Estimated to start
Spring 2021
Estimated to end
Fall 2021
Consultant
KGS Group
+
William Av - Arlington St / McPhillips St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Additional information
Click here
+
William Stephenson Wy - Main St / Westbrook St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Wynyard By - Southwell Rd/Manthorne Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Spring 2021
Estimated to end
Summer 2021
Approx. % completed
0
Consultant
KGS Group Limited
Contractor
Wintec Building Services Inc.
Disclaimer and Indemnity:
The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.
The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.
By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.