Road Construction List
The roadway construction list provides project information in alphabetical order by street name.
Project information is available by location in both map and list format . Please see the regional street lane closures page for information on current lane closures on major streets.
How to use the construction list
Click on the + beside the project name. A dropdown box will appear with these project details:
type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
estimated to start,
estimated to end,
approximate percentage completed:
Pre-Construction – Construction phase has not started.
0% – Construction contract is in place, but crews have not mobilized to the site.
5% – Crews have mobilized to the site and construction has just begun.
10% 90% – An approximation of progress; construction is well underway.
95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
consultant information, and
contractor information.
You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.
Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.
City of Winnipeg - Public Works Capital Projects
(Last updated on May 19, 2022 @ 5:30 PM)
+
820 Cloutier Drive Slope Stabilization
View Map
Facility type
Bridge
Type of work
Slope Stabilization
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Agnes St - Sargent Av / Ellice Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Albina Wy/Raber Rd - Kairistine Ln/Hume St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
Alexander Av - Keewatin St/Dee St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Contractor
Asphaltec Paving
+
Allegheny Dr - Dalhousie Dr / Ulster St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
May 16, 2022
Estimated to end
June 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Contractor
Wintec Building Services Inc.
Document
+
Andrews St - College Av / Redwood Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Andrews St - Redwood Av / Aberdeen Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Annabella St - Rover Av / Sutherland Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Archibald St - Messier St / Doucet St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
To Be Determined
Additional information
Click here
+
Archibald St - Plinguet St / Messier St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
To Be Determined
Additional information
Click here
+
Ascot By - Laxdal Rd / Laxdal Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Late Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
KGS Group Limited
Document
+
Assiniboine Gr - Bedson St / End
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Assiniboine Park - Conservatory Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Assiniboine Park - Corydon Sidewalk Improvements
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Assiniboine Park - Locomotive Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Assiniboine Park - Pavilion Cres
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Baytree Ct - Forestgate Av / End
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Beecher Av - Ferrier St / End
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Global Homes
+
Beechtree Cr - Beliveau Rd / Beliveau Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Beliveau Rd E - Marlene St / St Annes Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Facility type
Sidewalk
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Document
+
Berry St - Ellice Av / St Matthews Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 24, 2022
Estimated to end
Late June 2022
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Document
+
Berry St - Ness Av / Portage Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 24, 2022
Estimated to end
Late June 2022
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Document
+
Berry St - Silver Av / Ness Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 13, 2022
Estimated to end
Late August
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Document
+
Berry St - St Matthews Av / Silver Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 24, 2022
Estimated to end
Late June 2022
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Document
+
Birchdale Av/Lawndale Av - Conniston St/Lyndale Dr
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
+
Biscayne By - McGillivray Pl / McGillivray Pl
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
KGS Group Limited
Document
+
Blackwood By - Marrington Rd / Marrington Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Bluewater Cr - Cherwell Rd / Cherwell Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Brewer Cr - Panet Rd / Molson St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Briar Cliff By - Killarney Av / Killarney Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Broadway - Osborne St / Main St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Additional information
Click here
+
Brock St - Corydon Av / Grosvenor Av
View Map
Facility type
Street
Type of work
Resurfacing
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
KGS Group Limited
Document
+
Brotman By - John Forsyth Rd / John Forsyth Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Buller St - Gilbert Av / Manitoba Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Caldwell Cr - Scurfield Bv / Scurfield Bv
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Campbell St - Mathers Av / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
KGS Group Limited
Document
+
Canora St - Preston Av / Westminster Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
Carpathia Rd - 469 Carpathia Rd / Kenaston Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
KGS Group Limited
Document
+
Carpathia Rd - Corydon Av / 469 Carpathia Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
KGS Group Limited
Document
+
Chancellor Dr - Augusta Dr / Quincy By
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Chief Peguis Tl - Main St/Henderson Hw
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
May 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
+
Church Av - Sinclair St / Arlington St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2022
Estimated to end
August 2022
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Citadel Cr - Adsum Dr / Desharnais St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Colony St - Portage Av / St Mary Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
+
Corydon Av - Borebank St/Brock St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2022
Estimated to end
Summer 2022
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Additional information
Click here
+
Corydon Av - Cordova St/Lanark St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2022
Estimated to end
Summer 2022
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Additional information
Click here
+
Countryside Wy - Norris Rd / End
View Map
Facility type
Street
Type of work
Resurfacing
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Cranlea Pa - McIvor Av / Gilmore Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Cunnington Av - Killarney St / Silverthorne Pl
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Cunnington Av - St Marys Rd / Alley
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Dakota St - Beliveau Rd / St Marys Rd
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Dakota St - Bishop Grandin Bv / Beliveau Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
De Leglise Av - Campeau St / Pembina Hw
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Dee St - Logan Av / Alexander Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Des Meurons St - Goulet St / Marion St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Downing St - Ellice Av / Armoury Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
Dubuc St - Enfield Cr / Des Meurons St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
+
Dundas St - Sargent Av / Yukon Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Edderton Av - Derek St / Beaumont St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Edelweiss Cr - Donwood Dr/ Donwood Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Edmonton St - Ellice Av / Cumberland Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Ellice Av - Carlton St / Kennedy St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Erin St - Notre Dame Ave / Sargent Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
Contractor
Maple Leaf Construction Ltd.
Additional information
Click here
Document
+
Erin St - Sargent Av / Wolever Ave
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 24,2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
Contractor
Maple Leaf Construction Ltd.
Additional information
Click here
Document
+
Eugenie St - Tache Av / St Marys Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Fifth Av/Guay Av - Des Meurons St/St Marys Rd
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
+
Flett Av - Reay Cr / Antrim Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Forest Park Dr - Sinclair St / Airlies St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 2022
Estimated to end
August 2022
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Forestgate Av - Lindenwood Dr W / Deer Run Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Gateway Rd - Johnson Av E/Riverton Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
May 2022
Estimated to end
Summer 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Contractor
Asphaltec Paving
Document
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
Gertrude Av Speed Bump Installation
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Glenacres Cr - Millstream Wy/Millstream Wy
View Map
Facility type
Street
Type of work
TBO
Estimated to start
May 18,2022
Estimated to end
June 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Contractor
Wintec Building Services Inc.
Document
+
Glenthorne Cr - Greendell Av / Darwin St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Glenthorne Cr - Woodlawn Av / Greendell Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Goulet St - Braemar Av / Youville St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Grandcrest St - Forest Park Dr / Hartford Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Contractor
Asphaltec Paving
+
Grant Av - 150m East of Kenaston / Borebank St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
Document
+
Grant Av - Borebank St / Montrose St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
Document
+
Grant Avenue Pathway - Chalfont Rd/Assiniboine Forest Path
View Map
Facility type
Pedestrian / Cycling
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Greencrest Av - Ulster St / Pembina Hw
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Grundy Av - Ingersoll St / Garfield St N
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
Gull Lake Rd - East Lake Dr / Markham Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Harvard Av E - Roanoke St / Leola St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
Harwood Cr - Dale Bv / Rannock Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Harwood Cr - Rannock Av / Cullen Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Hawkesbury Cr - Tweedsmuir Rd / Tweedsmuir Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Henderson Hw - City Limit / North of Gilmore Av
View Map
Facility type
Street
Type of work
Study
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Hillberry By - Columbia Dr / Columbia Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Honeybourne Cr - Westgrove Wy / Dale Bv
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Horace St - Des Meurons St / Enfield Cr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Horace St - Youville St / Des Meurons St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Inkster Bv - McKenzie St / Arlington St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Jewett By - Sinnott St / Sinnott St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
KGS Group Limited
Document
+
John Forsyth Rd - Thornewood Av / Warde Av
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Johnson Av W - Levis St / Henderson Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Additional information
Click here
+
Jubilee Av - Cockburn St S / Pembina Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
Jubilee Av - Osborne St / Cockburn St S
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 8, 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
Kavanagh St/Giroux St - Dufresne Av/West Concrete Lane Limit
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
+
Keenleyside St - Beach Av / Talbot Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Keenleyside St - Talbot Av / Nairn Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Keewatin St - Adsum Dr / Inkster Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 16, 2022
Estimated to end
Summer 2022
Approx. % completed
Planned
Consultant
KGS Group
Contractor
J.C. Paving Ltd.
Document
+
Kenaston Bv - McGillivray Bv/Railway Line
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
May 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
+
Kenaston Bv - McGillivray Bv/Scurfield Bv
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
May 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
+
Kildonan Dr - Donwood Dr / Rossmere Cr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Kingsbury Av - Sinclair St / West of Airlies St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 2022
Estimated to end
August 2022
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Knox St -Hamilton Av / Ness Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
La Grave St - Lemay Av / Lord Av
View Map
Facility type
Street
Type of work
Resurfacing
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Lagimodiere Bv - Fermor Av / Cottonwood Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lakeshore Rd - Chancellor Dr / Chancellor Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Lakeshore Rd - Chancellor Dr / Chancellor Dr
View Map
Facility type
Street
Type of work
Resurfacing
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Lakewood Pathway - Lake Park Dr/Clearwater Rd/Edgewater Dr
View Map
Facility type
Pedestrian / Cycling
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Lansdowne Av - Main St / Salter St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2022
Estimated to end
August 2022
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Laval Dr - Pasadena Av/Silverstone Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
May 2022
Estimated to end
Summer 2022
Approx. % completed
50
Consultant
WSP Canada Inc.
Contractor
Wintec Building Services Inc.
Document
+
Lawndale Av - Lyndale Dr / Highfield St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
Legion Av - King Edward St / Oddy St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Leila Ave - McPhillips St / McGregor St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Leila Ave - McPhillips St / McGregor St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Leila Ave - McPhillips St / McGregor St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Facility type
Street
Type of work
Preservation
Estimated to start
May 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
+
Logan Av - Disraeli Fwy / Main St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lydia St - McDermot Av / Notre Dame Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Macalester By - Silverstone Av / Silverstone Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Makinak By - Crestview Park Dr / Crestview Park Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Manchester Bv N - Point Rd / End
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Mandalay Dr - Olford Cr / Jefferson Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Manitoba Av - Chudley St / Keewatin St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Mattinee By - Donwood Dr / Donwood Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Maynard Cs - Jefferson Av / Maberley Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
McCalman Av - Kent Rd / Chester St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
McGill Av - McMasters Rd/Silverstone Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
May 17,2022
Estimated to end
June 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Contractor
Wintec Building Services Inc.
Document
+
McGregor St - Church Av / Mountain Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
McGregor St - Selkirk Av / Dufferin Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
McGregor St - Seven Oaks Av / McAdam Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
McMeans Av E - Wayoata St / Wabasha St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
McMillan Av/Corydon Av/Donald St
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
May 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
+
McPhillips St - Machray Av / Mountain Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Menno By - Antrim Rd / Antrim Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Midland St - Notre Dame Av / Saskatchewan Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
MIlt Stegall Dr - Sargent Av / Yukon Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Minnetonka St - Avalon Rd / River Rd
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Mitchelson Wy - Bonner Av/Ragsdill Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
May 16,2022
Estimated to end
June 2022
Approx. % completed
50
Consultant
WSP Canada Inc.
Contractor
Asphaltec Paving
Document
+
Montcalm Cr - Hartford Av/Vanier Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Contractor
Asphaltec Paving
+
Moore Av - Dunkirk Dr / St Marys Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Moore Av - Flynn St / Pulberry St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Moore Av - Pulberry St / Dunkirk Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Moore Av - River Rd / Flynn St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Moray St - Charleswood Bridge/Portage Av
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
May 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
+
Morton By - Stack St / Stack St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Mountain Ave - Arlington St / McPhillips St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
Document
+
Munroe Av - Raleigh St / Watt St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 24, 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Additional information
Click here
Document
+
Munroe Av - Watt St / Henderson Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 24, 2022
Estimated to end
Fall 2022
Approx. % completed
50
Consultant
WSP Canada Inc.
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
Murray Park Rd - Saulteaux Cr / Saulteaux Cr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Murray Park Rd - Saulteaux Cr / Saulteaux Cr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Murray Park Rd - Saulteaux Cr / Sturgeon Rd
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Nairn Av - Stadacona St / Watt St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Document
+
Niakwa Trail Pathway - Lagimodiere Bv/Westmount Dr
View Map
Facility type
Pedestrian / Cycling
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Northwest Hydro Corridor Pathway - Leila Av / Church Av
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Norwood & Main Street Bridge Rehabilitation
View Map
Facility type
Bridge
Type of work
Rehabilitation
+
Notre Dame Av - Arlington St / McPhillips St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Notre Dame St - Langevin St / St Joseph St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Oakenwald Av - Wicklow St / Point Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
Oakland Av - Rothesay St / Roch St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Osborne St - Stradbrook Av / Wardlaw Av
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Pacific Av - Sherbrook St / Tecumseh St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Palmerston Av - Arlington St / Ethelbert St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
Palmerston Av - Lenore St / Arlington St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
Parkview St - Portage Av / Assiniboine Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 24, 2022
Estimated to end
Late June 2022
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Document
+
Pembina Hw - McGillivray Bv / Chevrier Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 9, 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
Pembina Hw - McGillivray Bv / Chevrier Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
Pentland St - McIvor Av/Gilmore Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
May 18,2022
Estimated to end
June 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Contractor
Asphaltec Paving
Document
+
Perth Av - Jones St / Scotia St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 2022
Estimated to end
August 2022
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Perth Av - Main St / Jones St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 2022
Estimated to end
August 2022
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Pioneer Av - Westbrook St / Main St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
+
Plessis Rd - St Boniface Rd/City Limit
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
AECOM
+
Portage Av - Lake St/50m West of Rita St
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
May 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
+
Price Dr - Brewer Cr / Brewer Cr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Provencher Bv - Tache Av / Langevin St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
June 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Provencher Pedestrian Bridge Lighting Upgrades
View Map
Facility type
Bridge
Type of work
Lighting Upgrades
+
Ravenhurst St - Pandora Av E / John Duncan Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Ravine Dr - River Pointe Dr / Settlers Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Redwood Av - Salter St / Main St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Reenders Pathway - Stapon Rd/Panet Rd
View Map
Facility type
Pedestrian / Cycling
Type of work
New Facility
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Renfrew St - Grant Av / Taylor Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
KGS Group Limited
Document
+
RHG Bonney Castle Pathway - Chancellor Dr/Syracuse Cr
View Map
Facility type
Pedestrian / Cycling
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
River Av - Osborne St / Wellington Cr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Roslyn Rd - Osborne St / Roslyn Cr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
Ross Av - Isabel St / Sherbrook St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Rossmere Cr - Dunvegan St / Kildonan Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Rouge Rd - Erlandson Dr / Assiniboine Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 16, 2022
Estimated to end
Mid June 2022
Approx. % completed
80
Consultant
WSP Canada Inc
Contractor
Darco Group Ltd.
Document
+
Route 90 Culvert at Omand's Creek
View Map
Facility type
Bridge
Type of work
Reconstruction
Estimated to start
June 15, 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Rupertsland Bv - Jones St / Main St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 2022
Estimated to end
August 2022
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Rupertsland Bv - Main St / Jones St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 2022
Estimated to end
August 2022
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Salter St - Jefferson Av / Inkster Bv
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Sandcliffe Ct - Hawkesbury Cr / Hawkesbury Cr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Sargent Av - Edmonton St / Furby St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Sargent Av/Ellice Av - Clifton St/Spruce St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
Saskatchewan Av - King Edward St / King Edward St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Saskatchewan Av - King Edward St / Sherwin Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Saskatchewan Av - Midland St / Empress St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Saskatchewan Av - St James St / Century St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Sedgeley Ct - Hawkesbury Cr / Hawkesbury Cr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Selkirk Av - Main St / Salter St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Selkirk Ave - Arlington St / McPhillips St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2022
Estimated to end
Summer 2022
Approx. % completed
20
Consultant
Stantec Consulting Ltd
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
Semple Av - Main St / Salter St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 2022
Estimated to end
August 2022
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Sherwin Rd - Notre Dame Av / Saskatchewan Av
View Map
Facility type
Bridge
Type of work
Reconstruction
Estimated to start
June 2022
Estimated to end
September 2022
Approx. % completed
90
Consultant
Morrison Hershfield Limited
Contractor
Bayview
+
Shillingstone Rd - Columbia Dr / Columbia Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Simpson Av - Moncton Av / Louelda St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Skowron Cr - Jacques Av / Grassie Bv
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Smith - Graham Av/Midtown Bridge
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
Maple Leaf Construction Ltd.
Additional information
Click here
Document
+
Smith St - Ellice Av / Portage Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
Maple Leaf Construction Ltd.
Additional information
Click here
Document
+
Smith St - Notre Dame / Ellice Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
Maple Leaf Construction Ltd.
Additional information
Click here
Document
+
Smith St - Portage Av / Graham Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
Maple Leaf Construction Ltd.
Additional information
Click here
Document
+
St Annes Rd - 50m South of Novavista Dr/220m North of Meadowood Dr
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
May 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
+
St Annes Rd - Hindley Av/Worthington Av Lane Reconstruction
View Map
Type of work
Reconstruction
Estimated to start
Summer 2022
Estimated to end
Fall 2023
Document
+
St Annes Rd - St Marys Rd / Fermor Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
St George Rd - Sadler Av / Hindley Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
St Mary Av - Memorial Bv / Portage Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
+
St Mary Av - Memorial Bv / Portage Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
+
St. James Bridges Minor Rehabilitation
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
August 2022
Estimated to end
Fall 2022
Consultant
Tetra Tech
+
Stafford St - Corydon Ave/Scotland Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 9, 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Contractor
Nelson River Construction
Additional information
Click here
Document
+
Stafford St - Scotland Av/Pembina Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Contractor
Nelson River Construction
Additional information
Click here
Document
+
Stradbrook Av - Queen Elizabeth Wy/Harkness St
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
May 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
+
Stradbrook Ave - Wellington Cr / Osborne St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Strauss Dr - 80 Strauss Dr / Thompson Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 16, 2022
Estimated to end
Mid June 2022
Approx. % completed
60
Consultant
WSP Canada Inc
Contractor
Darco Group Ltd.
Document
+
Strauss Dr - Strauss Dr / 80 Strauss Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 16, 2022
Estimated to end
Mid June 2022
Approx. % completed
70
Consultant
WSP Canada Inc
Contractor
Darco Group Ltd.
Document
+
Sturgeon Rd - Ness Av / Hallonquist Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Contractor
J.C. Paving Ltd.
+
Sturgeon Rd - Ness Av / Hallonquist Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Contractor
J.C. Paving Ltd.
+
Taylor Ave - Harrow St / Pembina Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Additional information
Click here
Document
+
Tecumseh St - Alexander Av / Pacific Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Telfer St N - St Matthews Av / Ellice Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 2022
Estimated to end
Summer 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
Thompson Dr - Strauss Dr / Ness Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 16, 2022
Estimated to end
Mid June 2022
Approx. % completed
50
Consultant
WSP Canada Inc
Contractor
Darco Group Ltd.
Document
+
Trudell By - Gardner Cv / Rougeau Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Trudell By - Rougeau Av / Gardner Cv
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Tu Pelo Av - London St / West of Jeffrey Cr
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Tu Pelo Av - London St / West of Jeffrey Cr
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Tulane By - Pasadena Av / Pasadena Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
University Cr - Pembina Hw / Thatcher Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 2022
Estimated to end
Summer 2022
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Document
+
University Cr - Thatcher Dr / Pembina Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2022
Estimated to end
Summer 2022
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Document
+
Vialoux Dr/Roblin Bv - Swann Dr/Wexford St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
KGS Group Limited
Document
+
Victoria Av E - Roanoke St / Leola St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
Wall St - St Matthews Av / Wellington Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 16,2022
Estimated to end
Fall 2022
Approx. % completed
70
Consultant
Morrison Hershfield Limited
Contractor
J.C. Paving Ltd.
Additional information
Click here
Document
+
Wall St - Wellington Av / Notre Dame Ave
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 16,2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
Contractor
J.C. Paving Ltd.
Additional information
Click here
Document
+
Waller Av/Clarence Av - Hudson St/Marshall Cr
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
KGS Group Limited
Document
+
Wardlaw Av - Scott St / Donald St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
Wardlaw Av - Scott St / Osborne St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
Waterford Av - Pembina Hw / Lyon St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
Wellington Cr - River Av / Stradbrook Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Wendilene St - Trudell By / Rougeau Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Wentworth St - Fleet Av / End
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Whellams Ln - Claus By / Appleton St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Widlake St - Kildare Av E / Victoria Av E
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
William Av - Arlington St / McPhillips St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
William Stephenson Wy - Main St / Westbrook St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
+
Winona St - Kildare Av W / Regent Av W
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
Woodside Cr - Kildonan Meadow Dr/Kildonan Meadow Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Contractor
Asphaltec Paving
+
Wordsworth Wy - Jolliett Cr / Browning Bv
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
York Av - Main St / Carlton St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
York Av - Main St / Carlton St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Youville St - Guay Av/Haig Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Contractor
Asphaltec Paving
+
Youville St - Marion St / Eugenie St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
+
Yukon Av - Empress St / Milt Stegall Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Yukon Av - Milt Stegall Dr / St James St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Zawaly By - Kildare Av E/Kildare Av E
View Map
Facility type
Street
Type of work
TBO
Estimated to start
May 16, 2022
Estimated to end
Late June 2022
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Contractor
Asphaltec Paving
Document
Disclaimer and Indemnity:
The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.
The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.
By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.