Site Accessibility Information Access Key 1 to Skip to Top Navigation Access Key 2 to Skip to the Three One One link Access Key 3 to Skip to City of Winnipeg Main Menu Access Key 4 to Skip to Left Navigation Menu Access Key 5 to Skip to Content area Access Key 6 to Skip to Right Sidebar content area Access Key 7 to Skip to Footer Links
City of Winnipeg
|  Link to the City of Winnipeg French websiteFrançais  |
DOWNLOAD
THE APP!
What’s Your Residential Street Snow Zone?
Public Works

Road Construction List

The roadway construction list provides project information in alphabetical order by street name. Project information is available by location in both map and list format. Please see the regional street lane closures page for information on current lane closures on major streets.

How to use the construction list

Click on the + beside the project name. A dropdown box will appear with these project details:

  1. type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
  2. type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
  3. estimated to start,
  4. estimated to end,
  5. approximate percentage completed:
    • Pre-Construction – Construction phase has not started.
    • 0% – Construction contract is in place, but crews have not mobilized to the site.
    • 5% – Crews have mobilized to the site and construction has just begun.
    • 10% 90% – An approximation of progress; construction is well underway.
    • 95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
    • COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
  6. consultant information, and
  7. contractor information.

You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.

Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.

A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z


City of Winnipeg - Public Works Capital Projects
(Last updated on March 19, 2019 @ 8:00 PM)
 
 
View All on Map


Agnes Arnold Pl - Leila Av/Roberts Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Aikins St - North End/Templeton Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2019
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Darco Enterprises Ltd.
Bannerman Av - Airlies St/McPhillips St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Bayne Cr- London St/Tu Pelo Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Darco Enterprises Ltd.
Beresford Av - Osborne St/Daly St S   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Bishop Grandin Bv - Rapid Transit Corridor Overpass   View Map
Facility type Bridge
Type of work New - Rapid Transit Overpass Installation
Estimated to start February 2017
Estimated to end Spring 2020
Approx. % completed 30
Consultant Plenary Roads
Contractor PCL
Additional information Click here
Bishop Grandin Bv/Kenaston Bv   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Brighton Ct/Kildare Av E-Southampton Pl/Wayoata St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Broadway - Sherbrook St/Portage Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant Stantec Consulting Ltd.
Contractor Bituminex Paving Ltd
Broadway/Garry St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Cail By - Jefferson Av/Jefferson Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Chambers St - Logan Av/Alexander Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Chevrier Bv - Pembina Hw/Trottier By   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Chevrier Bv - Trottier By/Waverley St   View Map
Facility type Street
Type of work Mill and Fill - Pavement Widening
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Chief Peguis Greenway Extension   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling Construction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 90
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Additional information Click here
Churchill Dr - Eccles St/Casey St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Colony St - Ellice Av/Portage Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Coniston St/Lyndale Dr - Claremont Av/Ferndale Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Coniston St/Lyndale Dr - Monck Av/Claremont Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Darwin St- Riel Av/Riverbend Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
De Vries Av - McIvor Av/Springfield Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Darco Enterprises Ltd.
Des Meurons St - Vivian Av/Regal Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Donald St - Portage Av/Notre Dame Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor Borland Construction Inc.
Additional information Click here
Drake Bv - Elizabeth Rd/Autumnwood Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Dundurn Pl/Wolseley Av-Maryland St/Walnut St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Empress St E - Portage Av/Westway   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant Morrison Hershfield Limited
Contractor Borland Construction Inc.
Additional information Click here
Fawn Pl- Woodstock Ln/Whitetail Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor Darco Enterprises Ltd.
Fermor Av - Archibald St/St Annes Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2017
Estimated to end Summer 2019
Approx. % completed 95
Consultant Dillon
Fermor Av - St Annes Rd/Archibald St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2018
Estimated to end Fall 2019
Approx. % completed 20
Consultant Dillon Consulting Limited
Contractor MD Steele
Fermor Av at Seine River Crossing   View Map
Facility type Bridge
Type of work Bridge - Culvert Installation
Estimated to start Summer 2018
Estimated to end Summer 2019
Approx. % completed 45
Consultant Dillon Consulting Limited
Contractor MD Steele
Additional information Click here
Fife St - College Av/Burrows Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Fife St - Inkster Bv/College Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Fife St - Inkster Bv/College Av   View Map
Facility type Sidewalk
Type of work New - Sidewalk Construction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Fort St/York Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Gagnon St- Oxbow Bend Rd/Augier Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor Darco Enterprises Ltd.
Garden Grove Dr - Fairgrove By/Burrows Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Garry St - Broadway/Assiniboine   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Garry St - Notre Dame Av/Portage Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Garry St - Portage Av/Broadway   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Greene Av/Linden Av - Woodvale St/Kildonan Dr   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Haig Av- Egerton Rd/Des Meurons St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Fall 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Haresford Cr- Hawkins Cr/Novavista Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Fall 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Harkness St/Stradbrook Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Henderson Hw/Larsen Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Henderson Hw/McLeod Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Henlow By - Dovercourt Dr/Fultz Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Henlow By - Scurfield Bv/Dovercourt Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Higgins Av - Henry Av/Princess St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Highfield St/Coniston St - Chandos Av/Crawford Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Hutchings St - Inkster Bv/Sheppard St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Summer 2019
Approx. % completed 75
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Inkster Bv/McGregor St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Jefferson Av - 65m West of Watson St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Jefferson Av/McPhillips St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Keewatin St - Inkster Bv/Burrows Av   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling Construction
Estimated to start Summer 2019
Estimated to end Spring 2019
Approx. % completed 95
Consultant Stantec
Contractor Darco Enterprises Ltd.
Additional information Click here
King St/Alexander Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Knightsbridge Dr- Ashworth St/Meadowood Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Lagimodiere Bv - Dugald Rd/Regent Av W   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant Stantec
Contractor Bituminex Paving Ltd
Lagimodiere Bv and Sage Creek Bv Intersection   View Map
Facility type Street
Type of work Intersection Improvement
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant Stantec Consulting Ltd.
Contractor Bituminex Paving Ltd
Larsen Av - Brazier St/Henderson Hw   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Darco Enterprises Ltd.
Loudoun Rd - Wilkes Av/Wyper Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Hugh Munro Construction
Main St/Alexander Av/Disraeli Fwy   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Main St/Selkirk Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor Black & McDonald Limited / Harris Holdings Ltd.
McGillivray Bv - Rapid Transit Corridor Overpass   View Map
Facility type Bridge
Type of work New - Rapid Transit Overpass Installation
Estimated to start Spring 2017
Estimated to end Spring 2020
Approx. % completed 30
Consultant Plenary Roads
Contractor PCL
Additional information Click here
McGillivray Bv/90m West of Pembina Hw   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor Black & McDonald Limited / Harris Holdings Ltd.
McGregor St - Selkirk Av/Mountain Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant KGS Group
Contractor Bayview Construction Ltd
McPhillips St - Jarvis Av/Logan Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 80
Consultant Dillon Consulting Limited
Contractor Borland Construction Inc.
McPhillips St - Logan Av/Jarvis Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 80
Consultant Dillon Consulting Limited
Contractor Borland Construction Inc.
McPhillips St/Burrows Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor Black & McDonald Limited / Harris Holdings Ltd.
McPhillips St/Leila Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Melrose Av W/Pandora Av W-Bond St/Winona St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Memorial Bv - Portage Av/St Mary Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Memorial Bv - Portage Av/St Mary Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Memorial Bv - York Av/Broadway   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling Construction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Memorial Bv - York Av/St Mary Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Molson St - Nottingham Av/Union Av E   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Darco Enterprises Ltd.
Moray St - Saulteaux Cr/Moray St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Morpeth Bv - North End/Taylor Av   View Map
Facility type Sidewalk
Type of work New - Sidewalk Construction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Mutchmor Cs- Tu Pelo Av/Tu Pelo Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Darco Enterprises Ltd.
Notre Dame Av - Portage Av/Princess St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Additional information Click here
Notre Dame Av/Weston St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Partridge Av/Royal Av-Powers St/Andrews St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Pembina Hw - Grant Av/Osborne St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Additional information Click here
Pembina Hw - Grant Av/Osborne St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Additional information Click here
Pembina Hw - Rapid Transit Corridor Underpass   View Map
Facility type Bridge
Type of work New - Rapid Transit Underpass Installation
Estimated to start Spring 2017
Estimated to end Spring 2020
Approx. % completed 30
Consultant Plenary Roads
Contractor PCL
Additional information Click here
Pembina Hw/Southpark Dr   View Map
Facility type Signal
Type of work New - Rapid Transit Signal Installation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Peony Av - Verbena St/Viola St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Portage Av/Carlton St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Preston Av/Westminster Av-Ethelbert St/Home St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Princess St - Willaim Av/Donald St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Princess St - William Av/Notre Dame Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Additional information Click here
Provencher Bv - Des Meurons St/Archibald St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant Stantec Consulting Ltd.
Contractor Bituminex Paving Ltd
Rapid Transit Corridor - Phase 2   View Map
Facility type Rapid Transit Corridor
Type of work New - Rapid Transit Corridor
Estimated to start Summer 2016
Estimated to end Spring 2020
Approx. % completed 30
Consultant Plenary Roads
Contractor PCL
Additional information Click here
Roberts Cr - Agnes Arnold Pl/Jefferson Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Sara Av/Westminster Av-Langside St/Furby St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Sargent/Ellice Av-Arlington St/Alverstone St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Saskatchewan Av - 2450 Saskatchewan Av/Moray St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Saskatchewan Av - Moray St/Sturgeon Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Semple Av/Kilbride Av-Main St/Aikins St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Sherbrook St - McDermot Av/Cumberland Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant Stantec Consulting Ltd.
Contractor Darco Enterprises Ltd.
Speers Rd - Cottonwood Rd/Crestwood Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
St James St - 190m North of Ellice Av/Sargent Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Ltd
St Mary Av - Vaughan St/Memorial Bv   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Spring 2018
Estimated to end Summer 2019
Approx. % completed 0
Consultant City Of Winnipeg - Engineering Division
St Matthews Av/Valour Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Swindon Wy - Portsmouth Bv/Park Bv E   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 80
Consultant AECOM Canada Ltd
Contractor Darco Enterprises Ltd.
Transcona Trail - Regent Ave W/Panet Rd   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling Construction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant Stantec Consulting Ltd.
Contractor Darco Enterprises Ltd.
Troy Av - McPhillips St/Fife St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Walmer St/Kirkdale St - Lawndale Av/Birchdale Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Waverley St/Taylor Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Waverley Underpass Project - Taylor Av / Waverley St / Wilkes Av / Grant Av   View Map
Facility type Street
Type of work Bridge - Roadway Reconstruction
Estimated to start Spring 2017
Estimated to end Fall 2019
Approx. % completed 10
Consultant Dillon Consulting Limited
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Waverley Underpass Project - Taylor Av / Waverley St / Wilkes Av / Grant Av   View Map
Facility type Bridge
Type of work New - Bridges Underpass Installation
Estimated to start Spring 2017
Estimated to end Fall 2019
Approx. % completed 10
Consultant Dillon Consulting Limited
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Wellington Av/Sargent Av-Banning St/Lipton St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Wellington Av/Sargent Av-Toronto St/Beverley St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
West Alexander Pedestrian and Cycling Corridor   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling Construction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant Stantec Consulting Ltd.
Contractor Darco Enterprises Ltd.
Additional information Click here
West Alexander Pedestrian and Cycling Corridor   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling Construction
Estimated to start Summer 2017
Estimated to end Spring 2019
Approx. % completed 95
Consultant Stantec Consulting Ltd.
Contractor Darco Enterprises Ltd.
Additional information Click here
Westminster Av/Wolseley Av-Evanson St/Wolseley Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Whitetail Dr- Chalfont Rd/Eldridge Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 80
Consultant AECOM Canada Ltd
Contractor Darco Enterprises Ltd.
Whitley Dr- Ashworth St/Hawkins Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Woodstock Ln- North End/Eldridge Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 80
Consultant AECOM Canada Ltd
Contractor Darco Enterprises Ltd.
Yarwood Av/Wellington Av-Ingersoll St/Sherburn St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
York Av - Memorial Bv/Osborne St N   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.

Disclaimer and Indemnity:

The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.

The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.

By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.