Site Accessibility Information Access Key 1 to Skip to Top Navigation Access Key 2 to Skip to the Three One One link Access Key 3 to Skip to City of Winnipeg Main Menu Access Key 4 to Skip to Left Navigation Menu Access Key 5 to Skip to Content area Access Key 6 to Skip to Right Sidebar content area Access Key 7 to Skip to Footer Links
City of Winnipeg
|  Link to the City of Winnipeg French websiteFrançais  |
Public Works

Road Construction List

The roadway construction list provides project information in alphabetical order by street name. Project information is available by location in both map and list format. Please see the regional street lane closures page for information on current lane closures on major streets.

How to use the construction list

Click on the + beside the project name. A dropdown box will appear with these project details:

  1. type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
  2. type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
  3. estimated to start,
  4. estimated to end,
  5. approximate percentage completed:
    • Pre-Construction – Construction phase has not started.
    • 0% – Construction contract is in place, but crews have not mobilized to the site.
    • 5% – Crews have mobilized to the site and construction has just begun.
    • 10% 90% – An approximation of progress; construction is well underway.
    • 95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
    • COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
  6. consultant information, and
  7. contractor information.

You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.

Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.

A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z


City of Winnipeg - Public Works Capital Projects
(Last updated on May 19, 2022 @ 5:30 PM)
 
 
View All on Map


820 Cloutier Drive Slope Stabilization   View Map
Facility type Bridge
Type of work Slope Stabilization
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Agnes St - Sargent Av / Ellice Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Albina Wy/Raber Rd - Kairistine Ln/Hume St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2022 Preconstruction Notice_Hume Street_Kairistine Lane Alley.pdf
Alexander Av - Keewatin St/Dee St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Allegheny Dr - Dalhousie Dr / Ulster St   View Map
Facility type Street
Type of work TBO
Estimated to start May 16, 2022
Estimated to end June 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Wintec Building Services Inc.
Document
2022 Construction Notice_Allegheny Dr.pdf
Andrews St - College Av / Redwood Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Andrews St - Redwood Av / Aberdeen Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Annabella St - Rover Av / Sutherland Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Archibald St - Messier St / Doucet St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor To Be Determined
Additional information Click here
Archibald St - Plinguet St / Messier St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor To Be Determined
Additional information Click here
Ascot By - Laxdal Rd / Laxdal Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant KGS Group Limited
Document
2022 Preconstruction Notice_Ascot By.pdf
Assiniboine Gr - Bedson St / End   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Assiniboine Park - Conservatory Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Assiniboine Park - Corydon Sidewalk Improvements   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Assiniboine Park - Locomotive Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Assiniboine Park - Pavilion Cres   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Baytree Ct - Forestgate Av / End   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Beecher Av - Ferrier St / End   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Global Homes
Beechtree Cr - Beliveau Rd / Beliveau Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Beliveau Rd E - Marlene St / St Annes Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Berry St - 1800 Berry Street   View Map
Facility type Sidewalk
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant AECOM Canada Ltd
Document
2022 Construction Notice_Berry Street_Airport Hotel.pdf
Berry St - Ellice Av / St Matthews Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 24, 2022
Estimated to end Late June 2022
Approx. % completed Planned
Consultant AECOM Canada Ltd
Document
2022 Construction Notice_Berry Street_Portage to Ellice.pdf
Berry St - Ness Av / Portage Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 24, 2022
Estimated to end Late June 2022
Approx. % completed Planned
Consultant AECOM Canada Ltd
Document
2022 Construction Notice_Berry Street_Portage to Ellice.pdf
Berry St - Silver Av / Ness Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 13, 2022
Estimated to end Late August
Approx. % completed Planned
Consultant AECOM Canada Ltd
Document
2022 Construction Notice_Berry St_Silver to Ness.pdf
Berry St - St Matthews Av / Silver Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 24, 2022
Estimated to end Late June 2022
Approx. % completed Planned
Consultant AECOM Canada Ltd
Document
2022 Construction Notice_Berry Street_Portage to Ellice.pdf
Birchdale Av/Lawndale Av - Conniston St/Lyndale Dr   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Biscayne By - McGillivray Pl / McGillivray Pl   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant KGS Group Limited
Document
2022 Preconstruction Notice_Biscayne By.pdf
Blackwood By - Marrington Rd / Marrington Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Bluewater Cr - Cherwell Rd / Cherwell Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Brewer Cr - Panet Rd / Molson St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Briar Cliff By - Killarney Av / Killarney Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Broadway - Osborne St / Main St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Additional information Click here
Brock St - Corydon Av / Grosvenor Av   View Map
Facility type Street
Type of work Resurfacing
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant KGS Group Limited
Document
2022 Preconstruction Notice_Brock St.pdf
Brotman By - John Forsyth Rd / John Forsyth Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Buller St - Gilbert Av / Manitoba Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Caldwell Cr - Scurfield Bv / Scurfield Bv   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Campbell St - Mathers Av / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant KGS Group Limited
Document
2022 Preconstruction Notice_Campbell St.pdf
Canora St - Preston Av / Westminster Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2022 Preconstruction Notice_Canora St.pdf
Carpathia Rd - 469 Carpathia Rd / Kenaston Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant KGS Group Limited
Document
2022 Preconstruction Notice_Carpathia Rd.pdf
Carpathia Rd - Corydon Av / 469 Carpathia Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant KGS Group Limited
Document
2022 Preconstruction Notice_Carpathia Rd.pdf
Chancellor Dr - Augusta Dr / Quincy By   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Chief Peguis Tl - Main St/Henderson Hw   View Map
Facility type Street
Type of work Preservation
Estimated to start May 2022
Estimated to end Fall 2022
Approx. % completed Planned
Church Av - Sinclair St / Arlington St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2022
Estimated to end August 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022 Preconstruction Notice_Church.pdf
Citadel Cr - Adsum Dr / Desharnais St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Colony St - Portage Av / St Mary Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Corydon Av - Borebank St/Brock St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2022
Estimated to end Summer 2022
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Additional information Click here
Corydon Av - Cordova St/Lanark St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2022
Estimated to end Summer 2022
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Additional information Click here
Countryside Wy - Norris Rd / End   View Map
Facility type Street
Type of work Resurfacing
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022 Preconstruction Notice_Countryside Way.pdf
Cranlea Pa - McIvor Av / Gilmore Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Cunnington Av - Killarney St / Silverthorne Pl   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Cunnington Av - St Marys Rd / Alley   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Dakota St - Beliveau Rd / St Marys Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Dakota St - Bishop Grandin Bv / Beliveau Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
De Leglise Av - Campeau St / Pembina Hw   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Dee St - Logan Av / Alexander Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Des Meurons St - Goulet St / Marion St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Downing St - Ellice Av / Armoury Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2022 Preconstruction Notice_Downing St.pdf
Dubuc St - Enfield Cr / Des Meurons St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Dundas St - Sargent Av / Yukon Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Edderton Av - Derek St / Beaumont St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Edelweiss Cr - Donwood Dr/ Donwood Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Edmonton St - Ellice Av / Cumberland Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Ellice Av - Carlton St / Kennedy St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Erin St - Notre Dame Ave / Sargent Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Document
2022 Construction Notice_Erin.pdf
Erin St - Sargent Av / Wolever Ave   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 24,2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Document
2022 Construction Notice_Erin.pdf
Eugenie St - Tache Av / St Marys Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Fifth Av/Guay Av - Des Meurons St/St Marys Rd   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Flett Av - Reay Cr / Antrim Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022 Preconstruction Notice_Flett Ave.pdf
Forest Park Dr - Sinclair St / Airlies St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 2022
Estimated to end August 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022 Preconstruction Notice_Forest Park.pdf
Forestgate Av - Lindenwood Dr W / Deer Run Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Gateway Rd - Johnson Av E/Riverton Av   View Map
Facility type Street
Type of work TBO
Estimated to start May 2022
Estimated to end Summer 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Document
2021 Construction Deferral Notice_Gateway Road.pdf
Gerard St - River Av / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2022 Preconstruction Notice_Gerard St.pdf
Gertrude Av Speed Bump Installation   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Glenacres Cr - Millstream Wy/Millstream Wy   View Map
Facility type Street
Type of work TBO
Estimated to start May 18,2022
Estimated to end June 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Wintec Building Services Inc.
Document
2022 Construction Notice_Glenacres Crescent .pdf
Glenthorne Cr - Greendell Av / Darwin St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Glenthorne Cr - Woodlawn Av / Greendell Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Goulet St - Braemar Av / Youville St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Grandcrest St - Forest Park Dr / Hartford Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Grant Av - 150m East of Kenaston / Borebank St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Document
2022 Preconstruction Notice_Grant Avenue.pdf
Grant Av - Borebank St / Montrose St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Document
2022 Preconstruction Notice_Grant Avenue.pdf
Grant Avenue Pathway - Chalfont Rd/Assiniboine Forest Path   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Greencrest Av - Ulster St / Pembina Hw   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Grundy Av - Ingersoll St / Garfield St N   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2022 Preconstruction Notice_Grundy Ave.pdf
Gull Lake Rd - East Lake Dr / Markham Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Harvard Av E - Roanoke St / Leola St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2022 Preconstruction Notice_Harvard Ave.pdf
Harwood Cr - Dale Bv / Rannock Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Harwood Cr - Rannock Av / Cullen Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Hawkesbury Cr - Tweedsmuir Rd / Tweedsmuir Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Henderson Hw - City Limit / North of Gilmore Av   View Map
Facility type Street
Type of work Study
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Hillberry By - Columbia Dr / Columbia Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Honeybourne Cr - Westgrove Wy / Dale Bv   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Horace St - Des Meurons St / Enfield Cr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Horace St - Youville St / Des Meurons St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Inkster Bv - McKenzie St / Arlington St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Jewett By - Sinnott St / Sinnott St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant KGS Group Limited
Document
2022 Preconstruction Notice_Jewett Bay.pdf
John Forsyth Rd - Thornewood Av / Warde Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Johnson Av W - Levis St / Henderson Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Additional information Click here
Jubilee Av - Cockburn St S / Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant Dillon Consulting Limited
Contractor Bayview Construction Ltd
Additional information Click here
Document
2022 Construction Notice_Jubilee.pdf
Jubilee Av - Osborne St / Cockburn St S   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 8, 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant Dillon Consulting Limited
Contractor Bayview Construction Ltd
Additional information Click here
Document
2022 Construction Notice_Jubilee.pdf
Kavanagh St/Giroux St - Dufresne Av/West Concrete Lane Limit   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Keenleyside St - Beach Av / Talbot Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022 Preconstruction Notice_Keenleyside St - Talbot to Beach.pdf
Keenleyside St - Talbot Av / Nairn Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022 Preconstruction Notice_Keenleyside - Nairn to Talbot.pdf
Keewatin St - Adsum Dr / Inkster Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 16, 2022
Estimated to end Summer 2022
Approx. % completed Planned
Consultant KGS Group
Contractor J.C. Paving Ltd.
Document
2022 Construction Notice_Keewatin.pdf
Kenaston Bv - McGillivray Bv/Railway Line   View Map
Facility type Street
Type of work Preservation
Estimated to start May 2022
Estimated to end Fall 2022
Approx. % completed Planned
Kenaston Bv - McGillivray Bv/Scurfield Bv   View Map
Facility type Street
Type of work Preservation
Estimated to start May 2022
Estimated to end Fall 2022
Approx. % completed Planned
Kildonan Dr - Donwood Dr / Rossmere Cr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Kingsbury Av - Sinclair St / West of Airlies St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 2022
Estimated to end August 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022 Preconstruction Notice_Kingsbury.pdf
Knox St -Hamilton Av / Ness Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
La Grave St - Lemay Av / Lord Av   View Map
Facility type Street
Type of work Resurfacing
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Lagimodiere Bv - Fermor Av / Cottonwood Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lakeshore Rd - Chancellor Dr / Chancellor Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Lakeshore Rd - Chancellor Dr / Chancellor Dr   View Map
Facility type Street
Type of work Resurfacing
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Lakewood Pathway - Lake Park Dr/Clearwater Rd/Edgewater Dr   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Lansdowne Av - Main St / Salter St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2022
Estimated to end August 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Preconstruction Notice_Lansdowne.pdf
Laval Dr - Pasadena Av/Silverstone Av   View Map
Facility type Street
Type of work TBO
Estimated to start May 2022
Estimated to end Summer 2022
Approx. % completed 50
Consultant WSP Canada Inc.
Contractor Wintec Building Services Inc.
Document
2021 Construction Notice_Laval Dr.pdf
Lawndale Av - Lyndale Dr / Highfield St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2022 Preconstruction Notice_Lawndale Avenue E.pdf
Legion Av - King Edward St / Oddy St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Leila Ave - McPhillips St / McGregor St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Leila Ave - McPhillips St / McGregor St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Leila Ave - McPhillips St / McGregor St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Logan Av - Blake St/Vine St   View Map
Facility type Street
Type of work Preservation
Estimated to start May 2022
Estimated to end Fall 2022
Approx. % completed Planned
Logan Av - Disraeli Fwy / Main St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lydia St - McDermot Av / Notre Dame Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Macalester By - Silverstone Av / Silverstone Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Makinak By - Crestview Park Dr / Crestview Park Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Manchester Bv N - Point Rd / End   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Mandalay Dr - Olford Cr / Jefferson Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Manitoba Av - Chudley St / Keewatin St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Mattinee By - Donwood Dr / Donwood Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022 Preconstruction Notice_Mattinee Bay.pdf
Maynard Cs - Jefferson Av / Maberley Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
McCalman Av - Kent Rd / Chester St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022 Preconstruction Notice_McCalman Ave.pdf
McGill Av - McMasters Rd/Silverstone Av   View Map
Facility type Street
Type of work TBO
Estimated to start May 17,2022
Estimated to end June 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Wintec Building Services Inc.
Document
2022 Construction Notice_McGill Ave.pdf
McGregor St - Church Av / Mountain Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
McGregor St - Selkirk Av / Dufferin Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
McGregor St - Seven Oaks Av / McAdam Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
McMeans Av E - Wayoata St / Wabasha St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
McMillan Av/Corydon Av/Donald St   View Map
Facility type Street
Type of work Preservation
Estimated to start May 2022
Estimated to end Fall 2022
Approx. % completed Planned
McPhillips St - Machray Av / Mountain Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Menno By - Antrim Rd / Antrim Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022 Preconstruction Notice_Menno Bay.pdf
Midland St - Notre Dame Av / Saskatchewan Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
MIlt Stegall Dr - Sargent Av / Yukon Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Minnetonka St - Avalon Rd / River Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Mitchelson Wy - Bonner Av/Ragsdill Rd   View Map
Facility type Street
Type of work TBO
Estimated to start May 16,2022
Estimated to end June 2022
Approx. % completed 50
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Document
2022 Construction Notice_Mitchelson Way.pdf
Montcalm Cr - Hartford Av/Vanier Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Moore Av - Dunkirk Dr / St Marys Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Moore Av - Flynn St / Pulberry St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Moore Av - Pulberry St / Dunkirk Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Moore Av - River Rd / Flynn St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Moray St - Charleswood Bridge/Portage Av   View Map
Facility type Street
Type of work Preservation
Estimated to start May 2022
Estimated to end Fall 2022
Approx. % completed Planned
Morton By - Stack St / Stack St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Mountain Ave - Arlington St / McPhillips St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Document
2022 Construction Notice_Mountain Ave.pdf
Munroe Av - Raleigh St / Watt St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 24, 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Additional information Click here
Document
2022 Construction Notice_Munroe.pdf
Munroe Av - Watt St / Henderson Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 24, 2022
Estimated to end Fall 2022
Approx. % completed 50
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Additional information Click here
Document
2022 Construction Notice_Munroe.pdf
Murray Park Rd - Saulteaux Cr / Saulteaux Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Murray Park Rd - Saulteaux Cr / Saulteaux Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Murray Park Rd - Saulteaux Cr / Sturgeon Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Nairn Av - Stadacona St / Watt St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant Dillon Consulting Limited
Document
2022 Construction Notice_Nairn Ave.pdf
Niakwa Trail Pathway - Lagimodiere Bv/Westmount Dr   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Northwest Hydro Corridor Pathway - Leila Av / Church Av   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Norwood & Main Street Bridge Rehabilitation   View Map
Facility type Bridge
Type of work Rehabilitation
Notre Dame Av - Arlington St / McPhillips St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Notre Dame St - Langevin St / St Joseph St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Oakenwald Av - Wicklow St / Point Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2022 Preconstruction Notice_Oakenwald St.pdf
Oakland Av - Rothesay St / Roch St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Osborne St - Stradbrook Av / Wardlaw Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Pacific Av - Sherbrook St / Tecumseh St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Palmerston Av - Arlington St / Ethelbert St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2022 Preconstruction Notice_Palmerston Ave_920 to Wolseley.pdf
Palmerston Av - Lenore St / Arlington St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2022 Preconstruction Notice_Palmerston Ave_Lenore St to 921 Palmerston Ave.pdf
Parkview St - Portage Av / Assiniboine Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 24, 2022
Estimated to end Late June 2022
Approx. % completed Planned
Consultant AECOM Canada Ltd
Document
2022 Construction Notice_Parkview_Portage to Assiniboine.pdf
Pembina Hw - McGillivray Bv / Chevrier Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 9, 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant Dillon Consulting Limited
Contractor Bayview Construction Ltd
Additional information Click here
Document
2022 Construction Notice_Pembina.pdf
Pembina Hw - McGillivray Bv / Chevrier Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant Dillon Consulting Limited
Contractor Bayview Construction Ltd
Additional information Click here
Document
2022 Construction Notice_Pembina.pdf
Pentland St - McIvor Av/Gilmore Av   View Map
Facility type Street
Type of work TBO
Estimated to start May 18,2022
Estimated to end June 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Document
2022 Construction Notice_Pentland St.pdf
Perth Av - Jones St / Scotia St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 2022
Estimated to end August 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Preconstruction Notice_Perth.pdf
Perth Av - Main St / Jones St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 2022
Estimated to end August 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Preconstruction Notice_Perth.pdf
Pioneer Av - Westbrook St / Main St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Plessis Rd - St Boniface Rd/City Limit   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant AECOM
Portage Av - Lake St/50m West of Rita St   View Map
Facility type Street
Type of work Preservation
Estimated to start May 2022
Estimated to end Fall 2022
Approx. % completed Planned
Price Dr - Brewer Cr / Brewer Cr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Provencher Bv - Tache Av / Langevin St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start June 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022 Pre Construction_Provencher Blvd Sidewalk Renewal.pdf
Provencher Pedestrian Bridge Lighting Upgrades   View Map
Facility type Bridge
Type of work Lighting Upgrades
Ravenhurst St - Pandora Av E / John Duncan Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Ravine Dr - River Pointe Dr / Settlers Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Redwood Av - Salter St / Main St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Reenders Pathway - Stapon Rd/Panet Rd   View Map
Facility type Pedestrian / Cycling
Type of work New Facility
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Renfrew St - Grant Av / Taylor Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant KGS Group Limited
Document
2022 Preconstruction Notice_Renfrew St.pdf
RHG Bonney Castle Pathway - Chancellor Dr/Syracuse Cr   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
River Av - Osborne St / Wellington Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Roslyn Rd - Osborne St / Roslyn Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2022 Preconstruction Notice_Roslyn Rd.pdf
Ross Av - Isabel St / Sherbrook St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Rossmere Cr - Dunvegan St / Kildonan Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Rouge Rd - Erlandson Dr / Assiniboine Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 16, 2022
Estimated to end Mid June 2022
Approx. % completed 80
Consultant WSP Canada Inc
Contractor Darco Group Ltd.
Document
2022 Construction Notice_Rouge Rd.pdf
Route 90 Culvert at Omand's Creek   View Map
Facility type Bridge
Type of work Reconstruction
Estimated to start June 15, 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Rupertsland Bv - Jones St / Main St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 2022
Estimated to end August 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Preconstruction Notice_Rupertsland.pdf
Rupertsland Bv - Main St / Jones St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 2022
Estimated to end August 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Preconstruction Notice_Rupertsland.pdf
Salter St - Jefferson Av / Inkster Bv   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Sandcliffe Ct - Hawkesbury Cr / Hawkesbury Cr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Sargent Av - Edmonton St / Furby St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Sargent Av/Ellice Av - Clifton St/Spruce St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2022 Preconstruction Notice_Sargent Avenue_Spruce Street Alley.pdf
Saskatchewan Av - King Edward St / King Edward St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Saskatchewan Av - King Edward St / Sherwin Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Saskatchewan Av - Midland St / Empress St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Saskatchewan Av - St James St / Century St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Sedgeley Ct - Hawkesbury Cr / Hawkesbury Cr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Selkirk Av - Main St / Salter St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Selkirk Ave - Arlington St / McPhillips St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2022
Estimated to end Summer 2022
Approx. % completed 20
Consultant Stantec Consulting Ltd
Contractor Bayview Construction Ltd
Additional information Click here
Document
2022 Preconstruction Notice_Selkirk and William.pdf
Semple Av - Main St / Salter St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 2022
Estimated to end August 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Preconstruction Notice_Semple.pdf
Sherwin Rd - Notre Dame Av / Saskatchewan Av   View Map
Facility type Bridge
Type of work Reconstruction
Estimated to start June 2022
Estimated to end September 2022
Approx. % completed 90
Consultant Morrison Hershfield Limited
Contractor Bayview
Shillingstone Rd - Columbia Dr / Columbia Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Simpson Av - Moncton Av / Louelda St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022 Preconstruction Notice_Simpson Ave.pdf
Skowron Cr - Jacques Av / Grassie Bv   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Smith - Graham Av/Midtown Bridge   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Document
2022 Preconstruction Notice_Smith St.pdf
Smith St - Ellice Av / Portage Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Document
2022 Preconstruction Notice_Smith St.pdf
Smith St - Notre Dame / Ellice Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Document
2022 Preconstruction Notice_Smith St.pdf
Smith St - Portage Av / Graham Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Document
2022 Preconstruction Notice_Smith St.pdf
St Annes Rd - 50m South of Novavista Dr/220m North of Meadowood Dr   View Map
Facility type Street
Type of work Preservation
Estimated to start May 2022
Estimated to end Fall 2022
Approx. % completed Planned
St Annes Rd - Hindley Av/Worthington Av Lane Reconstruction   View Map
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2023
Document
2022 Preconstruction Notice_St Annes Rd 475.pdf
St Annes Rd - St Marys Rd / Fermor Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
St George Rd - Sadler Av / Hindley Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
St Mary Av - Memorial Bv / Portage Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
St Mary Av - Memorial Bv / Portage Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
St. James Bridges Minor Rehabilitation   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start August 2022
Estimated to end Fall 2022
Consultant Tetra Tech
Stafford St - Corydon Ave/Scotland Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 9, 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant Stantec Consulting Ltd
Contractor Nelson River Construction
Additional information Click here
Document
2022 Construction Notice_Stafford St.pdf
Stafford St - Scotland Av/Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant Stantec Consulting Ltd
Contractor Nelson River Construction
Additional information Click here
Document
2022 Preconstruction Notice_Stafford St.pdf
Stradbrook Av - Queen Elizabeth Wy/Harkness St   View Map
Facility type Street
Type of work Preservation
Estimated to start May 2022
Estimated to end Fall 2022
Approx. % completed Planned
Stradbrook Ave - Wellington Cr / Osborne St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Strauss Dr - 80 Strauss Dr / Thompson Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 16, 2022
Estimated to end Mid June 2022
Approx. % completed 60
Consultant WSP Canada Inc
Contractor Darco Group Ltd.
Document
2022 Construction Notice_Strauss Dr.pdf
Strauss Dr - Strauss Dr / 80 Strauss Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 16, 2022
Estimated to end Mid June 2022
Approx. % completed 70
Consultant WSP Canada Inc
Contractor Darco Group Ltd.
Document
2022 Construction Notice_Strauss Dr.pdf
Sturgeon Rd - Ness Av / Hallonquist Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor J.C. Paving Ltd.
Sturgeon Rd - Ness Av / Hallonquist Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor J.C. Paving Ltd.
Taylor Ave - Harrow St / Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant Stantec Consulting Ltd
Additional information Click here
Document
2022 Preconstruction Notice_Taylor Ave.pdf
Tecumseh St - Alexander Av / Pacific Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Telfer St N - St Matthews Av / Ellice Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 2022
Estimated to end Summer 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2022 Preconstruction Notice_Telfer St.pdf
Thompson Dr - Strauss Dr / Ness Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 16, 2022
Estimated to end Mid June 2022
Approx. % completed 50
Consultant WSP Canada Inc
Contractor Darco Group Ltd.
Document
2022 Construction Notice_Thompson Dr.pdf
Trudell By - Gardner Cv / Rougeau Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Trudell By - Rougeau Av / Gardner Cv   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Tu Pelo Av - London St / West of Jeffrey Cr   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Tu Pelo Av - London St / West of Jeffrey Cr   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Tulane By - Pasadena Av / Pasadena Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
University Cr - Pembina Hw / Thatcher Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 2022
Estimated to end Summer 2022
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Document
2021_Construction Notice_University Cres.pdf
University Cr - Thatcher Dr / Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2022
Estimated to end Summer 2022
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Document
2021_Construction Notice_University Cres.pdf
Vialoux Dr/Roblin Bv - Swann Dr/Wexford St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant KGS Group Limited
Document
2022 Preconstruction Notice_Linton Lane.pdf
Victoria Av E - Roanoke St / Leola St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2022 Preconstruction Notice_Victoria Ave.pdf
Wall St - St Matthews Av / Wellington Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 16,2022
Estimated to end Fall 2022
Approx. % completed 70
Consultant Morrison Hershfield Limited
Contractor J.C. Paving Ltd.
Additional information Click here
Document
2022 Construction Notice_Wall Street.pdf
Wall St - Wellington Av / Notre Dame Ave   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 16,2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor J.C. Paving Ltd.
Additional information Click here
Document
2022 Construction Notice_Wall Street.pdf
Waller Av/Clarence Av - Hudson St/Marshall Cr   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant KGS Group Limited
Document
2022 Preconstruction Notice_Hudson St.pdf
Wardlaw Av - Scott St / Donald St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2022 Preconstruction Notice_Wardlaw Avenue - Scott St to Donald St.pdf
Wardlaw Av - Scott St / Osborne St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2022 Preconstruction Notice_Wardlaw Avenue - Scott St to Osborne St.pdf
Waterford Av - Pembina Hw / Lyon St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2022 Preconstruction Notice_Waterford Ave.pdf
Wellington Cr - River Av / Stradbrook Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Wendilene St - Trudell By / Rougeau Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Wentworth St - Fleet Av / End   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Whellams Ln - Claus By / Appleton St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Widlake St - Kildare Av E / Victoria Av E   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2022 Preconstruction Notice_Widlake Ave.pdf
William Av - Arlington St / McPhillips St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant Stantec Consulting Ltd
Contractor Bayview Construction Ltd
Additional information Click here
Document
2022 Preconstruction Notice_Selkirk and William.pdf
William Stephenson Wy - Main St / Westbrook St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Winona St - Kildare Av W / Regent Av W   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2022 Preconstruction Notice_Winona St.pdf
Woodside Cr - Kildonan Meadow Dr/Kildonan Meadow Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Wordsworth Wy - Jolliett Cr / Browning Bv   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
York Av - Main St / Carlton St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
York Av - Main St / Carlton St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Youville St - Guay Av/Haig Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Youville St - Marion St / Eugenie St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Yukon Av - Empress St / Milt Stegall Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Yukon Av - Milt Stegall Dr / St James St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Zawaly By - Kildare Av E/Kildare Av E   View Map
Facility type Street
Type of work TBO
Estimated to start May 16, 2022
Estimated to end Late June 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Document
2022 Construction Notice_Zawaly By.pdf

Disclaimer and Indemnity:

The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.

The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.

By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.


Was this information helpful?

How can we make this web page better?

Information collected will be used to improve our website. Do not use this form to submit a request for service or information because it will not be forwarded to departments for response. To submit a request for service or information, contact 311.

This form is not intended to collect personal information; however, any personal information you choose to include in your comments is collected by the City of Winnipeg under the authority of section 36(1)(b) of the Freedom of Information and Protection of Privacy Act for the purpose of improving our website and will not be used or disclosed for any other purposes, except as authorized by law. Contact the Corporate Access and Privacy Officer by mail (City Clerk’s Department, Susan A. Thompson Building, 510 Main Street, Winnipeg MB, R3B 1B9) or by telephone (311) if you have any questions about the collection of this information.

Ces renseignements sont-ils utiles?

Comment pourrait-on améliorer cette page Web?

Les renseignements recueillis serviront à l’amélioration de notre site Web. Prière de ne pas se servir de ce formulaire pour soumettre une demande de service ou de renseignements, car la demande ne sera pas transmise au service en question. Pour soumettre une demande de service ou de renseignements, veuillez communiquer avec le 311.

Le présent formulaire ne vise pas à recueillir des renseignements personnels. Cependant, les renseignements personnels que vous choisissez d’inclure dans vos commentaires sont recueillis par la Ville de Winnipeg en conformité avec l’alinéa 36(1)b) de la Loi sur l’accès à l’information et la protection de la vie privée dans le but d’améliorer son site Web et ne seront ni utilisés ni divulgués pour d’autres raisons, sauf dans les cas où cela est autorisé par la loi. Communiquez avec l’agent de l’accès à l’information et de la protection de la vie privée de la Ville par courrier au Bureau du greffier, immeuble Susan-A.-Thompson, 510, rue Main, Winnipeg (Manitoba) R3B 1B9, ou par téléphone au 311 si vous avez des questions sur la collecte de ces renseignements.