Site Accessibility Information Access Key 1 to Skip to Top Navigation Access Key 2 to Skip to the Three One One link Access Key 3 to Skip to City of Winnipeg Main Menu Access Key 4 to Skip to Left Navigation Menu Access Key 5 to Skip to Content area Access Key 6 to Skip to Right Sidebar content area Access Key 7 to Skip to Footer Links
City of Winnipeg
|  Link to the City of Winnipeg French websiteFrançais  |
The 2022 municipal election is on October 26. Get the latest election information. Les élections municipales de 2022 ont lieu le 26 octobre. Obtenez des renseignements à jour sur les élections.
Public Works

Road construction list

The roadway construction list provides project information in alphabetical order by street name. Project information is available by location in both map and list format.

More information: Lane closures

How to use the construction list

Click on the + beside the project name. A dropdown box will appear with these project details:

  1. type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
  2. type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
  3. estimated to start,
  4. estimated to end,
  5. approximate percentage completed:
    • Pre-Construction – Construction phase has not started.
    • 0% – Construction contract is in place, but crews have not mobilized to the site.
    • 5% – Crews have mobilized to the site and construction has just begun.
    • 10% 90% – An approximation of progress; construction is well underway.
    • 95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
    • COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
  6. consultant information, and
  7. contractor information.

You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.

Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.

A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z


City of Winnipeg - Public Works Capital Projects
(Last updated on October 4, 2022 @ 12:30 PM)
 
 
View All on Map


820 Cloutier Drive Slope Stabilization   View Map
Facility type Bridge
Type of work Slope Stabilization
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Adamar Rd - Pembina Hw/End   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Agnes St - Sargent Av / Ellice Av   View Map
Facility type Street
Type of work TBO
Estimated to start Aug 8, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Document
2022_Construction Notice_Agnes St.pdf
Albina Wy/Raber Rd - Kairistine Ln/Hume St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Darco Enterprises
Document
2022 Preconstruction Notice_Hume Street_Kairistine Lane Alley.pdf
Alexander Av - Keewatin St/Dee St   View Map
Facility type Street
Type of work TBO
Estimated to start June 1, 2022
Estimated to end Late June 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Document
2022 Construction Notice_Alexander Ave.pdf
Alexander Av - Main St / Princess St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start October 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Streets Maintenance Division
Allegheny Dr - Dalhousie Dr / Ulster St   View Map
Facility type Street
Type of work TBO
Estimated to start May 16, 2022
Estimated to end June 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Wintec Building Services Inc.
Document
2022 Construction Notice_Allegheny Dr.pdf
Andrews St - College Av / Redwood Av   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Andrews St - Redwood Av / Aberdeen Av   View Map
Facility type Street
Type of work TBO
Estimated to start August 22, 2022
Estimated to end Mid September 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Annabella St - Rover Av / Sutherland Av   View Map
Facility type Street
Type of work TBO
Estimated to start September 12, 2022
Estimated to end Late September 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Document
2022_Construction Notice_Annabella St.pdf
Archibald St - Messier St / Doucet St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor To Be Determined
Additional information Click here
Archibald St - Plinguet St / Messier St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor To Be Determined
Additional information Click here
Ascot By - Laxdal Rd / Laxdal Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Aug 5, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Document
2022_Construction Notice_Ascot Bay .pdf
Assiniboine Gr - Bedson St / End   View Map
Facility type Street
Type of work TBO
Estimated to start July 18, 2022
Estimated to end Early August 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Document
2022_Preconstruction Notice_Assiniboine Grove.pdf
Assiniboine Park - Conservatory Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 21, 2022
Estimated to end Mid September 2022
Approx. % completed 90
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Document
2022 Construction Notice_Assiniboine Park.pdf
Assiniboine Park - Corydon Sidewalk Improvements   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 23, 2022
Estimated to end Late July 2022
Approx. % completed 90
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Document
2022 Construction Notice_Park Blvd.pdf
Assiniboine Park - Locomotive Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 21, 2022
Estimated to end Mid September 2022
Approx. % completed 90
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Document
2022 Construction Notice_Assiniboine Park.pdf
Assiniboine Park - Pavilion Cres   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 21, 2022
Estimated to end Mid September 2022
Approx. % completed 90
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Document
2022 Construction Notice_Assiniboine Park.pdf
Baytree Ct - Forestgate Av / End   View Map
Facility type Street
Type of work TBO
Estimated to start August 29, 2022
Estimated to end Late September 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Document
2022_Construction Notice_Baytree Crt.pdf
Beecher Av - Ferrier St / End   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Global Homes
Beechtree Cr - Beliveau Rd / Beliveau Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Beliveau Rd E - Marlene St / St Annes Rd   View Map
Facility type Street
Type of work TBO
Estimated to start Late September 2022
Estimated to end Fall 2022
Approx. % completed 5
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Berry St - 1800 Berry Street   View Map
Facility type Sidewalk
Type of work Rehabilitation
Estimated to start June 13, 2022
Estimated to end Fall 2022
Approx. % completed 60
Consultant AECOM Canada Ltd
Contractor Darco Enterprises
Document
2022 Construction Notice_Berry Street_Airport Hotel.pdf
Berry St - Ellice Av / St Matthews Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 11, 2022
Estimated to end Mid September 2022
Approx. % completed 60
Consultant AECOM Canada Ltd
Contractor Darco Enterprises
Document
2022_Construction Notice_St Mathews-Ellice.pdf
Berry St - Ness Av / Portage Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 24, 2022
Estimated to end Late June 2022
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Darco Enterprises
Document
2022 Construction Notice_Berry St_Ness to Portage.pdf
Berry St - Silver Av / Ness Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 13, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Darco Enterprises
Document
2022 Construction Notice_Berry St_Silver to Ness.pdf
Berry St - St Matthews Av / Silver Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 4, 2022
Estimated to end Mid August 2022
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor Darco Enterprises
Document
2022 Construction Notice_Berry Street-Silver-St Mathews.pdf
Birchdale Av/Lawndale Av - Conniston St/Lyndale Dr   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Biscayne By - McGillivray Pl / McGillivray Pl   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start October 5, 2022
Estimated to end Fall 2022
Approx. % completed 5
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Document
2022_Construction Notice_Biscayne Bay.pdf
Blackwood By - Marrington Rd / Marrington Rd   View Map
Facility type Street
Type of work TBO
Estimated to start September 2,2022
Estimated to end Late September 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Document
2022_Construction Notice_Blackwood By.pdf
Bluewater Cr - Cherwell Rd / Cherwell Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Brewer Cr - Panet Rd / Molson St   View Map
Facility type Street
Type of work TBO
Estimated to start August 29, 2022
Estimated to end Late September 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Document
2022_Construction Notice_Brewer Cr.pdf
Briar Cliff By - Killarney Av / Killarney Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Aug 15, 2022
Estimated to end Late September 2022
Approx. % completed 40
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2022_Construction Notice_Briarcliff_Killarney to Killarney.pdf
Broadway - Osborne St / Main St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Additional information Click here
Brock St - Corydon Av / Grosvenor Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 11, 2022
Estimated to end Mid August 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Document
2022 Preconstruction Notice_Brock St_Corydon to Grosvenor.pdf
Brotman By - John Forsyth Rd / John Forsyth Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Buller St - Gilbert Av / Manitoba Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start September 6, 2022
Estimated to end Early October 2022
Approx. % completed 30
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Document
2022_Constrution Notice_Buller.pdf
Byng Pl/Windermere Av - Riverside Dr/Pembina Hw   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start September 6, 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant AECOM Canada Ltd
Document
2022_Construction Notice_Backlane_Pembina to Riverside.pdf
Caldwell Cr - Scurfield Bv / Scurfield Bv   View Map
Facility type Street
Type of work TBO
Estimated to start August 29, 2022
Estimated to end Late September 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Document
2022_Construction Notice_Caldwell Cr.pdf
Campbell St - Mathers Av / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 20, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Document
2022 Preconstruction Notice_Campbell St2.pdf
Canora St - Preston Av / Westminster Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed 70
Consultant WSP Canada Inc.
Contractor Darco Enterprises
Document
2022 Preconstruction Notice_Canora St.pdf
Carpathia Rd - 469 Carpathia Rd / Kenaston Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start September 12, 2022
Estimated to end Fall 2022
Approx. % completed 10
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Document
2022_Construction Notice_Carpathia Rd.pdf
Carpathia Rd - Corydon Av / 469 Carpathia Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 11, 2022
Estimated to end Fall 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Document
2022 Preconstruction Notice_Carpathia Rd_Kenaston to Corydon.pdf
Chancellor Dr - Augusta Dr / Quincy By   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Aug 29, 2022
Estimated to end Fall 2022
Approx. % completed 30
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2022_Construction Notice_Chancellor_Augusta to Quincy2.pdf
Chief Peguis Tl - Main St/Henderson Hw   View Map
Facility type Street
Type of work Preservation
Estimated to start Late August 2022
Estimated to end Fall 2022
Approx. % completed Complete
Document
2022_Construction Notice_EB Chief Peguis Trail.pdf
Church Av - Sinclair St / Arlington St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 30, 2022
Estimated to end Mid July 2022
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2022 Construction Notice_Church Ave.pdf
Citadel Cr - Adsum Dr / Desharnais St   View Map
Facility type Street
Type of work TBO
Estimated to start August 15, 2022
Estimated to end Early September 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Document
2022_Construction Notice_Citadel Cr.pdf
Colony St - Portage Av / St Mary Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed 20
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Corydon Av - Borebank St/Brock St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2022
Estimated to end Summer 2022
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Additional information Click here
Corydon Av - Cordova St/Lanark St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2022
Estimated to end Summer 2022
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Additional information Click here
Countryside Wy - Norris Rd / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start September 12, 2022
Estimated to end Early October 2022
Approx. % completed 10
Consultant City Of Winnipeg - Engineering Division
Contractor JC Paving
Document
2022_Construction Notice_Countryside Wy.pdf
Cranlea Pa - McIvor Av / Gilmore Av   View Map
Facility type Street
Type of work TBO
Estimated to start September 26, 2022
Estimated to end Mid October 2022
Approx. % completed 10
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Document
2022_Construction Notice_Cranlea Path.pdf
Cunnington Av - Killarney St / Silverthorne Pl   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Aug 3, 2022
Estimated to end Late August 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Construction Notice_Cunnington Avenue.pdf
Cunnington Av - St Marys Rd / Killarney St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Aug 3, 2022
Estimated to end Late August 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Construction Notice_Cunnington Avenue.pdf
Dakota St - Beliveau Rd / St Marys Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Dakota St - Bishop Grandin Bv / Beliveau Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Day St - New AT Asphalt Path   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start August 17, 2022
Estimated to end Late September 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Document
2022_Construction Notice_Day Street_Transcona Trail to McMeans Av E_AT Path.pdf
De Leglise Av - Campeau St / Pembina Hw   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor JC Paving
Dee St - Logan Av / Alexander Av   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Des Meurons St - Goulet St / Marion St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Downing St - Ellice Av / Armoury Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed 5
Consultant WSP Canada Inc.
Contractor Darco Enterprises
Document
2022 Preconstruction Notice_Downing St.pdf
Dubuc St - Enfield Cr / Des Meurons St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 11, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Dubuc St.pdf
Dundas St - Sargent Av / Yukon Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 24, 2022
Estimated to end Late June 2022
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Dundas_Sargent to Yukon.pdf
Dunkirk Dr - Dunkirk Dr / Kingston Rw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start October 2022
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Dunkirk Dr - St Vital Bridge / Norberry Dr   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Dunkirk Dr - Kingston Rw / Dunkirk Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start October 2022
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Dunkirk Dr - Kingston Rw / Dunkirk Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start October 2022
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Dunkirk Dr - Kingston Rw / Dunkirk Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start October 2022
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Dunkirk Dr - St Vital Rd / St Vital Bridge   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Edderton Av - Derek St / Beaumont St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Edelweiss Cr - Donwood Dr/ Donwood Dr   View Map
Facility type Street
Type of work TBO
Estimated to start September 26, 2022
Estimated to end Mid October 2022
Approx. % completed 10
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Document
2022_Construction Notice_Edelweiss Cr.pdf
Edmonton St - Ellice Av / Cumberland Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Ellice Av - Carlton St / Kennedy St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Erin St - Notre Dame Ave / Sargent Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Erin St - Sargent Av / Wolever Ave   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 24,2022
Estimated to end Fall 2022
Approx. % completed 30
Consultant Morrison Hershfield Limited
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Document
2022 Construction Notice_Erin.pdf
Eugenie St - Tache Av / St Marys Rd   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Fifth Av/Guay Av - Des Meurons St/St Marys Rd   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Flett Av - Reay Cr / Antrim Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 20, 2022
Estimated to end Late July 2022
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor JC Paving
Document
2022 Construction Notice_Flett.pdf
Forest Park Dr - Sinclair St / Airlies St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 30, 2022
Estimated to end Mid July 2022
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2022 Construction Notice_Forest Park Drive.pdf
Forestgate Av - Lindenwood Dr W / Deer Run Dr   View Map
Facility type Street
Type of work TBO
Estimated to start August 29, 2022
Estimated to end Late September 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Document
2022_Construction Notice_Forestgate Ave.pdf
Gateway Rd - Johnson Av E/Riverton Av   View Map
Facility type Street
Type of work TBO
Estimated to start Aug 8, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Document
2022_Construction Notice_Gateway Rd.pdf
Gerard St - River Av / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 6,2022
Estimated to end Late July 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Gerard St.pdf
Gertrude Av Speed Bump Installation   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 22, 2022
Estimated to end Mid September 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Construction Notice_Gertrude Ave.pdf
Glenacres Cr - Millstream Wy/Millstream Wy   View Map
Facility type Street
Type of work TBO
Estimated to start May 18,2022
Estimated to end June 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Wintec Building Services Inc.
Document
2022 Construction Notice_Glenacres Crescent .pdf
Glenthorne Cr - Greendell Av / Darwin St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Glenthorne Cr - Woodlawn Av / Greendell Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Goulet St - Braemar Av / Youville St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Grandcrest St - Forest Park Dr / Hartford Av   View Map
Facility type Street
Type of work TBO
Estimated to start June 8/2022
Estimated to end Early July 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Document
2022 Construction Notice_Grandcrest St.pdf
Grant Av - 150m East of Kenaston / Borebank St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Document
2022 Construction Notice_Grant Ave.pdf
Grant Av - Borebank St / Montrose St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 25, 2022
Estimated to end Fall 2023
Approx. % completed 70
Consultant Morrison Hershfield Limited
Contractor J.C. Paving Ltd.
Document
2022 Construction Notice_Grant Ave.pdf
Grant Avenue Pathway - Chalfont Rd/Assiniboine Forest Path   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start September 1, 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Grant Ave Pathway Construction Notice.pdf
Greencrest Av - Ulster St / Pembina Hw   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Grundy Av - Ingersoll St / Garfield St N   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 18, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Darco Enterprises
Document
2022_Construction Notice_Grundy Ave.pdf
Gull Lake Rd - East Lake Dr / Markham Rd   View Map
Facility type Street
Type of work TBO
Estimated to start September 2,2022
Estimated to end Late September 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Document
2022_Construction Notice_Gull Lake Rd.pdf
Harvard Av E - Roanoke St / Leola St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 9/2022
Estimated to end Late July 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Harvard Ave.pdf
Harwood Cr - Dale Bv / Rannock Av   View Map
Facility type Street
Type of work TBO
Estimated to start Aug 8, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Document
2022_Construction Notice_Harwood Cres.pdf
Harwood Cr - Rannock Av / Cullen Dr   View Map
Facility type Street
Type of work TBO
Estimated to start Aug 8, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Document
2022_Construction Notice_Harwood Cres.pdf
Hawkesbury Cr - Tweedsmuir Rd / Tweedsmuir Rd   View Map
Facility type Street
Type of work TBO
Estimated to start August 8, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Document
2022_Preconstruction Notice_Hawkesbury Cr.pdf
Henderson Hw - City Limit / North of Gilmore Av   View Map
Facility type Street
Type of work Study
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Hillberry By - Columbia Dr / Columbia Dr   View Map
Facility type Street
Type of work TBO
Estimated to start September 2,2022
Estimated to end Late September 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Document
2022_Construction Notice_Hillberry By.pdf
Honeybourne Cr - Westgrove Wy / Dale Bv   View Map
Facility type Street
Type of work TBO
Estimated to start July 27, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Document
2022 Preconstruction Notice_Honeybourne Cr.pdf
Horace St - Des Meurons St / Enfield Cr   View Map
Facility type Street
Type of work TBO
Estimated to start Late September 2022
Estimated to end Fall 2022
Approx. % completed 5
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Horace St - Youville St / Des Meurons St   View Map
Facility type Street
Type of work TBO
Estimated to start Late September 2022
Estimated to end Fall 2022
Approx. % completed 5
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Inkster Bv - McKenzie St / Arlington St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Jewett By - Sinnott St / Sinnott St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start September 26, 2022
Estimated to end Fall 2022
Approx. % completed 5
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Document
2022_Construction Notice_Jewett Bay.pdf
John Forsyth Rd - Thornewood Av / Warde Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start July 27, 2022
Estimated to end Mid August 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Construction Notice_John Forsyth.pdf
Johnson Av W - Levis St / Henderson Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Additional information Click here
Jolliett Cr - Rouge Rd / Sansome Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 16, 2022
Estimated to end Mid June 2022
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Darco Group Ltd.
Document
2022 Construction Notice_Jolliett Cr.pdf
Jubilee Av - Cockburn St S / Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Dillon Consulting Limited
Additional information Click here
Jubilee Av - Osborne St / Cockburn St S   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 8, 2022
Estimated to end Fall 2022
Approx. % completed 40
Consultant Dillon Consulting Limited
Contractor Bayview Construction Ltd
Additional information Click here
Document
2022 Construction Notice_Jubilee.pdf
Kavanagh St/Giroux St - Dufresne Av/West Concrete Lane Limit   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Keenleyside St - Beach Av / Talbot Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 22, 2022
Estimated to end Fall 2022
Approx. % completed 50
Consultant City Of Winnipeg - Engineering Division
Contractor JC Paving
Document
2022_Construction Notice_Keenleyside Rehabilitation.pdf
Keenleyside St - Talbot Av / Nairn Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start August 22, 2022
Estimated to end Fall 2022
Approx. % completed 50
Consultant City Of Winnipeg - Engineering Division
Contractor JC Paving
Document
2022_Construction Notice_Keenleyside Reconstruction.pdf
Keewatin St - Adsum Dr / Inkster Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 16, 2022
Estimated to end Summer 2022
Approx. % completed Complete
Consultant KGS Group
Contractor J.C. Paving Ltd.
Document
2022 Construction Notice_Keewatin.pdf
Keewatin St - Manitoba Av / Selkirk Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start August 23, 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Streets Maintenance Division
Kenaston Bv - McGillivray Bv/Railway Line   View Map
Facility type Street
Type of work Preservation
Estimated to start Early July 2022
Estimated to end Mid September 2022
Approx. % completed Complete
Document
2022_Construction Notice_NB Kenaston Blvd.pdf
Kenaston Bv - McGillivray Bv/Scurfield Bv   View Map
Facility type Street
Type of work Preservation
Estimated to start Early July 2022
Estimated to end Late August 2022
Approx. % completed Complete
Document
2022_Construction Notice_SB Kenaston Blvd.pdf
Kildonan Dr - Donwood Dr / Rossmere Cr   View Map
Facility type Street
Type of work TBO
Estimated to start September 23, 2022
Estimated to end Mid October 2022
Approx. % completed 30
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Document
2022_Construction Notice_Kildonan Dr.pdf
Kingsbury Av - Sinclair St / West of Airlies St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 30, 2022
Estimated to end Early July 2022
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2022 Construction Notice_Kingsbury Ave.pdf
Kingston Rw - Dunkirk Dr / Dunkirk Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start October 2022
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Knox St -Hamilton Av / Ness Av   View Map
Facility type Street
Type of work TBO
Estimated to start July 27, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Document
2022 Preconstruction Notice_Knox St.pdf
La Grave St - Lemay Av / Lord Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor JC Paving
Lagimodiere Bv - Fermor Av / Cottonwood Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lakeshore Rd - Chancellor Dr / Chancellor Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor JC Paving
Lakeshore Rd - Chancellor Dr / Chancellor Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor JC Paving
Lakewood Pathway - Lake Park Dr/Clearwater Rd/Edgewater Dr   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start September 20, 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Construction Notice_Van Belleghem Park.pdf
Lansdowne Av - Main St / Salter St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 27, 2022
Estimated to end Late September 2022
Approx. % completed 50
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2022 Construction Notice_Lansdowne Ave.pdf
Laval Dr - Pasadena Av/Silverstone Av   View Map
Facility type Street
Type of work TBO
Estimated to start June 1, 2022
Estimated to end Mid June 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Wintec Building Services Inc.
Document
2022 Construction Notice_Laval Dr.pdf
Lawndale Av - Lyndale Dr / Highfield St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Aug 8, 2022
Estimated to end Fall 2022
Approx. % completed 70
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Document
2022_Construction Notice_Lawndale Ave.pdf
Legion Av - King Edward St / Oddy St   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Leila Ave - McPhillips St / McGregor St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Leila Ave - McPhillips St / McGregor St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Leila Ave - McPhillips St / McGregor St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Logan Av - Blake St/Vine St   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Logan Av - Disraeli Fwy / Main St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Logan Av - Gwendoline St / Sherbrook St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Lydia St - McDermot Av / Notre Dame Av   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Macalester By - Silverstone Av / Silverstone Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Main St - Sutherland Av / Higgins Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Makinak By - Crestview Park Dr / Crestview Park Dr   View Map
Facility type Street
Type of work TBO
Estimated to start July 18, 2022
Estimated to end Early August 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Document
2022_Preconstruction Notice_Makinak By.pdf
Manchester Bv N - Point Rd / End   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Mandalay Dr - Olford Cr / Jefferson Av   View Map
Facility type Street
Type of work TBO
Estimated to start August 22, 2022
Estimated to end Mid September 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Document
2022_Construction Notice_Mandalay Dr.pdf
Manitoba Av - Chudley St / Keewatin St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 11, 2022
Estimated to end Mid September 2022
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Document
2022 Construction Notice_Manitoba.pdf
Mattinee By - Donwood Dr / Donwood Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 11, 2022
Estimated to end Mid August 2022
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor JC Paving
Document
2022 Construction Notice_Mattinee.pdf
Maynard Cs - Jefferson Av / Maberley Rd   View Map
Facility type Street
Type of work TBO
Estimated to start August 8, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Document
2022_Preconstruction Notice_Maynard Cl.pdf
McCalman Av - Kent Rd / Chester St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 2, 2022
Estimated to end Early September 2022
Approx. % completed 70
Consultant City Of Winnipeg - Engineering Division
Contractor JC Paving
Document
2022_Construction Notice_McCalman.pdf
McGill Av - McMasters Rd/Silverstone Av   View Map
Facility type Street
Type of work TBO
Estimated to start May 17,2022
Estimated to end June 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Wintec Building Services Inc.
Document
2022 Construction Notice_McGill Ave.pdf
McGregor St - Church Av / Mountain Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
McGregor St - Selkirk Av / Dufferin Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
McGregor St - Seven Oaks Av / McAdam Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
McMeans Av E - Wayoata St / Wabasha St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
McMillan Av/Corydon Av/Donald St   View Map
Facility type Street
Type of work Preservation
Estimated to start Early September 2022
Estimated to end Fall 2022
Approx. % completed 50
Document
2022_Construction Notice_Donald Street.pdf
McPhillips St - Jefferson Av/Inkster Bv   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
McPhillips St - Machray Av / Mountain Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Menno By - Antrim Rd / Antrim Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 27, 2022
Estimated to end Early August 2022
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor JC Paving
Document
2022 Construction Notice_Menno.pdf
Midland St - Notre Dame Av / Saskatchewan Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Midwinter Av - Stadacona St / 193 Midwinter Ave   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start September 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Streets Maintenance Division
Milt Stegall Dr - Sargent Av / Yukon Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 11, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Document
2022_Preconstruction Notice_Milt Stegall_Sargent to Yukon.pdf
Minnetonka St - Avalon Rd / River Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start August 22, 2022
Estimated to end Mid September 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022 Construction Notice_Minnetonka St.pdf
Mitchelson Wy - Bonner Av/Ragsdill Rd   View Map
Facility type Street
Type of work TBO
Estimated to start May 16,2022
Estimated to end June 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Document
2022 Construction Notice_Mitchelson Way.pdf
Montcalm Cr - Hartford Av/Vanier Dr   View Map
Facility type Street
Type of work TBO
Estimated to start June 8,2022
Estimated to end Early July 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Document
2022 Construction Notice_Montcalm Cr.pdf
Moore Av - Dunkirk Dr / St Marys Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Aug 9, 2022
Estimated to end Mid September 2022
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2022_Construction Notice_Moore_River to St Marys.pdf
Moore Av - Flynn St / Pulberry St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Aug 9, 2022
Estimated to end Mid September 2022
Approx. % completed 70
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2022_Construction Notice_Moore_River to St Marys.pdf
Moore Av - Pulberry St / Dunkirk Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Aug 9, 2022
Estimated to end Mid September 2022
Approx. % completed 70
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2022_Construction Notice_Moore_River to St Marys.pdf
Moore Av - River Rd / Flynn St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Aug 9, 2022
Estimated to end Mid September 2022
Approx. % completed 70
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2022_Construction Notice_Moore_River to St Marys.pdf
Moray St - Charleswood Bridge/Portage Av   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Complete
Document
2022_Construction Notice_Portage Ave Moray Street_Preservation.pdf
Morton By - Stack St / Stack St   View Map
Facility type Street
Type of work TBO
Estimated to start July 27, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Document
2022 Preconstruction Notice_Morton By.pdf
Mountain Ave - Arlington St / McPhillips St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 2022
Estimated to end Fall 2022
Approx. % completed 40
Consultant Morrison Hershfield Limited
Contractor J.C. Paving Ltd.
Document
2022 Construction Notice_Mountain Ave2.pdf
Munroe Av - Raleigh St / Watt St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 24, 2022
Estimated to end Fall 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Additional information Click here
Document
2022 Construction Notice_Munroe.pdf
Munroe Av - Watt St / Henderson Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 24, 2022
Estimated to end Fall 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Additional information Click here
Document
2022 Construction Notice_Munroe.pdf
Murray Park Rd - Saulteaux Cr / Saulteaux Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 22, 2022
Estimated to end Early September 2022
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Murray_Cree to Moray Southside.pdf
Murray Park Rd - Saulteaux Cr / Saulteaux Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 22, 2022
Estimated to end Early September 2022
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Murray_Cree to Moray Southside.pdf
Murray Park Rd - Saulteaux Cr / Sturgeon Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 22, 2022
Estimated to end Early September 2022
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Murray_Cree to Moray Southside.pdf
Nairn Av - Stadacona St / Watt St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2022
Estimated to end Fall 2022
Approx. % completed 80
Consultant Dillon Consulting Limited
Contractor J.C. Paving Ltd.
Document
2022 Construction Notice_Nairn Ave.pdf
Niakwa Trail Pathway - Lagimodiere Bv/Westmount Dr   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start September 19, 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Construction Notice_Niakwa Pathway.pdf
Northwest Hydro Corridor Pathway - Church Av to McPhillips Street Casino   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Northwest Hydro Corridor Pathway - Leila Av / Church Av   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start September 14, 2022
Estimated to end Fall 2022
Approx. % completed 60
Consultant City Of Winnipeg - Engineering Division
Document
2022_Construction Notice_Northwest Hydro New Multi-Use Pathway.pdf
Norwood & Main Street Bridge Rehabilitation   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Notre Dame Av - Arlington St / McPhillips St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start September 5, 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Construction Notice_Notre Dame Ave.pdf
Notre Dame Av - Dublin Av / Wall St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Aug 20, 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Streets Maintenance Division
Notre Dame St - Langevin St / St Joseph St   View Map
Facility type Street
Type of work TBO
Estimated to start Late September 2022
Estimated to end Fall 2022
Approx. % completed 5
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Oakenwald Av - Wicklow St / Point Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Document
2022 Preconstruction Notice_Oakenwald St.pdf
Oakland Av - Rothesay St / Roch St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start August 15, 2022
Estimated to end Mid September 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Construction Notice_Oakland Ave.pdf
Osborne St - Baltimore Rd / Rosedale Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start October 2022
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Osborne St - Don Av / Glasgow Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start October 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Streets Maintenance Division
Osborne St - Rosedale Av / St Vital Bridge   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start October 2022
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Osborne St - Stradbrook Av / Wardlaw Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Pacific Av - Sherbrook St / Tecumseh St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 18, 2022
Estimated to end Fall 2022
Approx. % completed 40
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Document
2022_Construction Notice 2 - Pacific - Treatment Change.pdf
Palmerston Av - Arlington St / Ethelbert St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed 50
Consultant WSP Canada Inc.
Contractor Darco Enterprises
Document
2022 Preconstruction Notice_Palmerston Ave_920 to Wolseley.pdf
Palmerston Av - Lenore St / Arlington St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 18, 2022
Estimated to end Fall 2022
Approx. % completed 70
Consultant WSP Canada Inc.
Contractor Darco Enterprises
Document
2022_Construction Notice_Palmerston Ave_Lenore St to 921 Palmerston Ave.pdf
Pandora Ave E - Redonda St / Wayoata St   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start July 4, 2022
Estimated to end Fall 2022
Approx. % completed 0
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Additional information Click here
Document
2022 Construction Notice_Pandora Ave_Wayoata St to Redonda St_AT Path.pdf
Parkview St - Portage Av / Assiniboine Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 24, 2022
Estimated to end Late June 2022
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Darco Enterprises
Document
2022 Construction Notice_Parkview_Portage to Assiniboine.pdf
Pembina Hw - McGillivray Bv / Chevrier Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 9, 2022
Estimated to end Fall 2022
Approx. % completed 40
Consultant Dillon Consulting Limited
Contractor Bayview Construction Ltd
Additional information Click here
Document
2022 Construction Notice_Pembina.pdf
Pembina Hw - McGillivray Bv / Chevrier Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant Dillon Consulting Limited
Additional information Click here
Pentland St - McIvor Av/Gilmore Av   View Map
Facility type Street
Type of work TBO
Estimated to start May 18,2022
Estimated to end June 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Document
2022 Construction Notice_Pentland St.pdf
Perth Av - Jones St / Scotia St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 11, 2022
Estimated to end Fall 2022
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2022 Construction Notice_Perth Ave.pdf
Perth Av - Main St / Jones St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 11, 2022
Estimated to end Fall 2022
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2022 Construction Notice_Perth Ave.pdf
Pioneer Av - Westbrook St / Main St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed 80
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Plessis Rd - St Boniface Rd/City Limit   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 26, 2022
Estimated to end Early August 2022
Approx. % completed 0
Consultant AECOM
Document
2022 Construction Notice_Plessis Widening.pdf
Portage Av - Lake St/50m West of Rita St   View Map
Facility type Street
Type of work Preservation
Estimated to start Mid July 2022
Estimated to end Fall 2022
Approx. % completed Complete
Document
2022_Construction Notice_Portage Avenue Moray St.pdf
Price Dr - Brewer Cr / Brewer Cr   View Map
Facility type Street
Type of work TBO
Estimated to start August 29, 2022
Estimated to end Fall 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Document
2022_Construction Notice_Price Dr.pdf
Provencher Bv - Tache Av / Langevin St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start August 29, 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Construction Notice_Provencher Boulevard.pdf
Provencher Pedestrian Bridge Lighting Upgrades   View Map
Facility type Bridge
Type of work Lighting Upgrades
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Ravenhurst St - Pandora Av E / John Duncan Dr   View Map
Facility type Street
Type of work TBO
Estimated to start August 22, 2022
Estimated to end Mid September 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Document
2022_Construction Notice_Ravenhurst St.pdf
Ravine Dr - River Pointe Dr / Settlers Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Redwood Av - Salter St / Main St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start August 2022
Estimated to end Fall 2022
Approx. % completed Planned
Document
2022 Preconstruction Notice_Redwood Ave.pdf
Reenders Pathway - Stapon Rd/Panet Rd   View Map
Facility type Pedestrian / Cycling
Type of work New Facility
Estimated to start September 26, 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Construction Notice_Reenders Dr.pdf
Renfrew St - Grant Av / Taylor Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 29, 2022
Estimated to end Fall 2022
Approx. % completed 30
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Document
2022_Construction Notice_Renfrew St.pdf
RHG Bonney Castle Pathway - Chancellor Dr/Syracuse Cr   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start August 18, 2022
Estimated to end Late September 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022 RHG Bonnycastle School Pathway Notice.pdf
River Av - Osborne St / Wellington Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
River Rd - Woodlawn Av / St Marys Rd   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start August 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Streets Maintenance Division
Roblin Bv - Chalfont Rd / William R Clement Pw   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start August 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Streets Maintenance Division
Roslyn Rd - Osborne St / Roslyn Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 25, 2022
Estimated to end Late June 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Roslyn Rd.pdf
Ross Av - Isabel St / Sherbrook St   View Map
Facility type Street
Type of work TBO
Estimated to start September 12, 2022
Estimated to end Late September 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Document
2022_Construction Notice _Ross Ave.pdf
Rossmere Cr - Dunvegan St / Kildonan Dr   View Map
Facility type Street
Type of work TBO
Estimated to start September 23, 2022
Estimated to end Mid October 2022
Approx. % completed 30
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Document
2022_Construction Notice_Rossmere Cr.pdf
Rouge Rd - Erlandson Dr / Assiniboine Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 16, 2022
Estimated to end Mid June 2022
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Darco Group Ltd.
Document
2022 Construction Notice_Rouge Rd.pdf
Route 90 Culvert at Omand's Creek   View Map
Facility type Bridge
Type of work Reconstruction
Estimated to start June 15, 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Rupertsland Bv - Jones St / Main St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 26, 2022
Estimated to end Fall 2022
Approx. % completed 20
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2022_Construction Notice - Rupertsland Blvd.pdf
Rupertsland Bv - Main St / Jones St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 26, 2022
Estimated to end Fall 2022
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2022_Construction Notice - Rupertsland Blvd.pdf
Salter St - Jefferson Av / Inkster Bv   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Sandcliffe Ct - Hawkesbury Cr / Hawkesbury Cr   View Map
Facility type Street
Type of work TBO
Estimated to start August 8, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Document
2022_Preconstruction Notice_Sandcliffe Crt.pdf
Sargent Av - Edmonton St / Furby St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Sargent Av/Ellice Av - Clifton St/Spruce St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Darco Enterprises
Document
2022 Preconstruction Notice_Sargent Avenue_Spruce Street Alley.pdf
Saskatchewan Av - King Edward St / King Edward St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 18, 2022
Estimated to end Fall 2022
Approx. % completed 80
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Saskatchewan Ave_Sherwin to St James.pdf
Saskatchewan Av - King Edward St / Sherwin Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 18, 2022
Estimated to end Fall 2022
Approx. % completed 80
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Saskatchewan Ave_Sherwin to St James.pdf
Saskatchewan Av - Midland St / Empress St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Saskatchewan Av - St James St / Century St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 18, 2022
Estimated to end Fall 2022
Approx. % completed 80
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Saskatchewan Ave_Sherwin to St James.pdf
Sedgeley Ct - Hawkesbury Cr / Hawkesbury Cr   View Map
Facility type Street
Type of work TBO
Estimated to start August 8, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Document
2022_Preconstruction Notice_Sedgeley Crt.pdf
Selkirk Av - Main St / Salter St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Selkirk Ave - Arlington St / McPhillips St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2022
Estimated to end Summer 2022
Approx. % completed 80
Consultant Stantec Consulting Ltd
Contractor Bayview Construction Ltd
Additional information Click here
Document
2022 Preconstruction Notice_Selkirk and William.pdf
Semple Av - Main St / Salter St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 21, 2022
Estimated to end Mid September 2022
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2022 Construction Notice_Semple Ave.pdf
Sherwin Rd - Notre Dame Av / Saskatchewan Av   View Map
Facility type Bridge
Type of work Reconstruction
Estimated to start June 2022
Estimated to end September 2022
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Bayview
Shillingstone Rd - Columbia Dr / Columbia Dr   View Map
Facility type Street
Type of work TBO
Estimated to start September 2,2022
Estimated to end Late September 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Document
2022_Construction Notice_Shillingstone Rd.pdf
Silver Av - Sturgeon Rd / Hamilton Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start October 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Streets Maintenance Division
Simpson Av - Moncton Av / Louelda St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 20, 2022
Estimated to end Late July 2022
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor JC Paving
Document
2022 Construction Notice_Simpson.pdf
Skowron Cr - Jacques Av / Grassie Bv   View Map
Facility type Street
Type of work TBO
Estimated to start August 29, 2022
Estimated to end Late September 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Document
2022_Construction Notice_Skowron Cr.pdf
Smith - Graham Av/Midtown Bridge   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 2022
Estimated to end Fall 2022
Approx. % completed 80
Consultant AECOM Canada Ltd
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Document
2022 Preconstruction Notice_Smith St.pdf
Smith St - Ellice Av / Portage Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 2022
Estimated to end Fall 2022
Approx. % completed 80
Consultant AECOM Canada Ltd
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Document
2022 Preconstruction Notice_Smith St.pdf
Smith St - Notre Dame / Ellice Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Smith St - Portage Av / Graham Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2022
Estimated to end Fall 2022
Approx. % completed 80
Consultant AECOM Canada Ltd
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Document
2022 Preconstruction Notice_Smith St.pdf
St Annes Rd - 50m South of Novavista Dr/220m North of Meadowood Dr   View Map
Facility type Street
Type of work Preservation
Estimated to start Mid August 2022
Estimated to end Fall 2022
Approx. % completed Complete
Document
2022_Construction Notice_St. Anne's Rd.pdf
St Annes Rd - Hindley Av/Worthington Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2023
Approx. % completed Planned
Document
2022 Preconstruction Notice_St Annes Rd 475.pdf
St Annes Rd - St Marys Rd / Fermor Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
St George Rd - Sadler Av / Hindley Av   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
St Mary Av - Memorial Bv / Portage Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed 80
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
St Mary Av - Memorial Bv / Portage Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed 80
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
St Vital Bridge   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start October 2022
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
St. James Bridges Minor Rehabilitation   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start August 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant Tetra Tech
Stafford St - Corydon Ave/Scotland Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 9, 2022
Estimated to end Fall 2022
Approx. % completed 40
Consultant Stantec Consulting Ltd
Contractor Nelson River Construction
Additional information Click here
Document
2022 Construction Notice_Stafford St.pdf
Stafford St - Scotland Av/Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant Stantec Consulting Ltd
Contractor Nelson River Construction
Additional information Click here
Stradbrook Av - Queen Elizabeth Wy/Harkness St   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Stradbrook Ave - Wellington Cr / Osborne St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Strauss Dr - 80 Strauss Dr / Thompson Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 16, 2022
Estimated to end Mid June 2022
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Darco Group Ltd.
Document
2022 Construction Notice_Strauss Dr.pdf
Strauss Dr - Strauss Dr / 80 Strauss Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 16, 2022
Estimated to end Mid June 2022
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Darco Group Ltd.
Document
2022 Construction Notice_Strauss Dr.pdf
Sturgeon Rd - Ness Av / Hallonquist Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Aug 8, 2022
Estimated to end Fall 2022
Approx. % completed 60
Consultant Morrison Hershfield Limited
Contractor J.C. Paving Ltd.
Document
2022_Construction Notice_Sturgeon Rd.pdf
Sturgeon Rd - Ness Av / Hallonquist Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Aug 8, 2022
Estimated to end Fall 2022
Approx. % completed 60
Consultant Morrison Hershfield Limited
Contractor J.C. Paving Ltd.
Document
2022_Construction Notice_Sturgeon Rd.pdf
Talbot Av - 267 Talbot Av / 168 Talbot Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start September 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Streets Maintenance Division
Taylor Ave - Harrow St / Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2022
Estimated to end Fall 2022
Approx. % completed 0
Consultant Stantec Consulting Ltd
Contractor Nelson River Construction
Additional information Click here
Document
2022 Preconstruction Notice_Taylor Ave.pdf
Tecumseh St - Alexander Av / Pacific Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed 50
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Telfer St N - St Matthews Av / Ellice Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start September 14, 2022
Estimated to end Fall 2022
Approx. % completed 10
Consultant WSP Canada Inc.
Contractor Darco Enterprises
Document
2022_Construction Notice_Telfer St .pdf
Thompson Dr - Strauss Dr / Ness Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 16, 2022
Estimated to end Mid June 2022
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Darco Group Ltd.
Document
2022 Construction Notice_Thompson Dr.pdf
Trudell By - Gardner Cv / Rougeau Av   View Map
Facility type Street
Type of work TBO
Estimated to start Aug 8, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Document
2022_Construction Notice_Trudell By.pdf
Trudell By - Rougeau Av / Gardner Cv   View Map
Facility type Street
Type of work TBO
Estimated to start Aug 8, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Document
2022_Construction Notice_Trudell By.pdf
Tu Pelo Av - London St / West of Jeffrey Cr   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Aug 8, 2022
Estimated to end Early September 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Construction Notice_Tu-pelo Ave.pdf
Tu Pelo Av - London St / West of Jeffrey Cr   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Aug 8, 2022
Estimated to end Early September 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Construction Notice_Tu-pelo Ave.pdf
Tulane By - Pasadena Av / Pasadena Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Asphaltec Paving
University Cr - Pembina Hw / Thatcher Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 18, 2022
Estimated to end October 2022
Approx. % completed 40
Consultant AECOM Canada Ltd
Contractor Bituminex Paving Ltd
Document
2022 Construction Notice_University Cr-Thatcher to Pembina.pdf
University Cr - Thatcher Dr / Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 18, 2022
Estimated to end October 2022
Approx. % completed 40
Consultant AECOM Canada Ltd
Contractor Bituminex Paving Ltd
Document
2022 Construction Notice_University Cr-Thatcher to Pembina.pdf
Vialoux Dr/Roblin Bv - Swann Dr/Wexford St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start August 15, 2022
Estimated to end Early September 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Document
2022_Preconstruction Notice_Linton Ln.pdf
Victoria Av E - Roanoke St / Leola St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start September 1, 2022
Estimated to end Fall 2022
Approx. % completed 50
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Document
2022_Construction Notice_Victoria Avenue E.pdf
Wall St - St Matthews Av / Wellington Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 16,2022
Estimated to end Fall 2022
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor J.C. Paving Ltd.
Additional information Click here
Document
2022 Construction Notice_Wall Street.pdf
Wall St - Wellington Av / Notre Dame Ave   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 16,2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor J.C. Paving Ltd.
Additional information Click here
Document
2022 Construction Notice_Wall Street.pdf
Waller Av/Clarence Av - Hudson St/Marshall Cr   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed 5
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Document
2022 Preconstruction Notice_Hudson St.pdf
Wardlaw Av - Scott St / Donald St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 25, 2022
Estimated to end Mid July 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Wardlaw Avenue - Scott St to Donald St.pdf
Wardlaw Av - Scott St / Osborne St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 25, 2022
Estimated to end Mid July 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Wardlaw Avenue - Scott St to Osborne St.pdf
Waterford Av - Pembina Hw / Lyon St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 15, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Waterford Ave.pdf
Wellington Cr - River Av / Stradbrook Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Wendilene St - Trudell By / Rougeau Av   View Map
Facility type Street
Type of work TBO
Estimated to start Aug 8, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Document
2022_Construction Notice_Wendilene St.pdf
Wentworth St - Fleet Av / End   View Map
Facility type Street
Type of work TBO
Estimated to start August 22, 2022
Estimated to end Mid September 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Document
2022_Construction Notice_Wentworth St.pdf
Weston St - Alexander Av / Pacific Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start August 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Streets Maintenance Division
Whellams Ln - Claus By / Appleton St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start August 5, 2022
Estimated to end Late August 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Construction Notice_Whellams Ln.pdf
Widlake St - Kildare Av E / Victoria Av E   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 8/2022
Estimated to end Late July 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Widlake Ave.pdf
William Av - Arlington St / McPhillips St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 2022
Estimated to end Fall 2022
Approx. % completed 40
Consultant Stantec Consulting Ltd
Contractor Bayview Construction Ltd
Additional information Click here
Document
2022 Preconstruction Notice_Selkirk and William.pdf
William Stephenson Wy - Main St / Westbrook St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2022
Approx. % completed 80
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Winona St - Kildare Av W / Regent Av W   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 15, 2022
Estimated to end Late July 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Winona St.pdf
Woodside Cr - Kildonan Meadow Dr/Kildonan Meadow Dr   View Map
Facility type Street
Type of work TBO
Estimated to start May 24, 2022
Estimated to end Mid June 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Document
2022 Construction Notice_Woodside Cres.pdf
Wordsworth Wy - Jolliett Cr / Browning Bv   View Map
Facility type Street
Type of work TBO
Estimated to start July 18, 2022
Estimated to end Early August 2022
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Document
2022_Preconstruction Notice_Wordsworth Wy.pdf
York Av - Main St / Carlton St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start September 19, 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Construction Notice_York Ave_Sidewalk.pdf
York Av - Main St / Carlton St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start September 19, 2022
Estimated to end Fall 2022
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2022_Construction Notice_York Ave_Sidewalk.pdf
Youville St - Guay Av/Haig Av   View Map
Facility type Street
Type of work TBO
Estimated to start May 25, 2022
Estimated to end Mid June 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Document
2022 Construction Notice_ Youville St.pdf
Youville St - Marion St / Eugenie St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 11, 2022
Estimated to end Late August 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Youville St.pdf
Yukon Av - Empress St / Milt Stegall Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 24, 2022
Estimated to end Late June 2022
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Yukon_St James to Empress.pdf
Yukon Av - Milt Stegall Dr / St James St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 24, 2022
Estimated to end Late June 2022
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Yukon_St James to Empress.pdf
Zawaly By - Kildare Av E/Kildare Av E   View Map
Facility type Street
Type of work TBO
Estimated to start May 16, 2022
Estimated to end Late June 2022
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Document
2022 Construction Notice_Zawaly By.pdf

Disclaimer and Indemnity:

The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.

The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.

By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.


Was this information helpful?

How can we make this web page better?

Information collected will be used to improve our website. Do not use this form to submit a request for service or information because it will not be forwarded to departments for response. To submit a request for service or information, contact 311.

This form is not intended to collect personal information; however, any personal information you choose to include in your comments is collected by the City of Winnipeg under the authority of section 36(1)(b) of the Freedom of Information and Protection of Privacy Act for the purpose of improving our website and will not be used or disclosed for any other purposes, except as authorized by law. Contact the Corporate Access and Privacy Officer by mail (City Clerk’s Department, Susan A. Thompson Building, 510 Main Street, Winnipeg MB, R3B 1B9) or by telephone (311) if you have any questions about the collection of this information.

Ces renseignements sont-ils utiles?

Comment pourrait-on améliorer cette page Web?

Les renseignements recueillis serviront à l’amélioration de notre site Web. Prière de ne pas se servir de ce formulaire pour soumettre une demande de service ou de renseignements, car la demande ne sera pas transmise au service en question. Pour soumettre une demande de service ou de renseignements, veuillez communiquer avec le 311.

Le présent formulaire ne vise pas à recueillir des renseignements personnels. Cependant, les renseignements personnels que vous choisissez d’inclure dans vos commentaires sont recueillis par la Ville de Winnipeg en conformité avec l’alinéa 36(1)b) de la Loi sur l’accès à l’information et la protection de la vie privée dans le but d’améliorer son site Web et ne seront ni utilisés ni divulgués pour d’autres raisons, sauf dans les cas où cela est autorisé par la loi. Communiquez avec l’agent de l’accès à l’information et de la protection de la vie privée de la Ville par courrier au Bureau du greffier, immeuble Susan-A.-Thompson, 510, rue Main, Winnipeg (Manitoba) R3B 1B9, ou par téléphone au 311 si vous avez des questions sur la collecte de ces renseignements.