Site Accessibility Information Access Key 1 to Skip to Top Navigation Access Key 2 to Skip to the Three One One link Access Key 3 to Skip to City of Winnipeg Main Menu Access Key 4 to Skip to Left Navigation Menu Access Key 5 to Skip to Content area Access Key 6 to Skip to Right Sidebar content area Access Key 7 to Skip to Footer Links
City of Winnipeg
|  Link to the City of Winnipeg French websiteFrançais  |
Public Works

Road Construction List

The roadway construction list provides project information in alphabetical order by street name. Project information is available by location in both map and list format. Please see the regional street lane closures page for information on current lane closures on major streets.

How to use the construction list

Click on the + beside the project name. A dropdown box will appear with these project details:

  1. type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
  2. type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
  3. estimated to start,
  4. estimated to end,
  5. approximate percentage completed:
    • Pre-Construction – Construction phase has not started.
    • 0% – Construction contract is in place, but crews have not mobilized to the site.
    • 5% – Crews have mobilized to the site and construction has just begun.
    • 10% 90% – An approximation of progress; construction is well underway.
    • 95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
    • COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
  6. consultant information, and
  7. contractor information.

You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.

Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.

A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z


City of Winnipeg - Public Works Capital Projects
(Last updated on December 12, 2019 @ 8:00 PM)
 
 
View All on Map


800m East of Lagimodiere Bv/Fermor Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
932 Archibald St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Academy Rd / Queenston St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Agnes Arnold Pl - Leila Av/Roberts Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Aikins St - North End/Templeton Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Darco Enterprises Ltd.
Ainslie St - Bruce Av/Lodge Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed 75
Consultant WSP Canada Inc
Contractor Darco Enterprises Ltd.
Albert St - Bannatyne Av/McDermot Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant AECOM Canada Ltd
Alexander Av - Stanley St/Ellen St   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2019
Estimated to end Mid August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Alexander Ave / Disraeli Fwy / Main St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Andrews St - Leila Av/Hartford Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late July 2019
Estimated to end Mid September 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Arnold Av - Hay St/Osborne St   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2019
Estimated to end Late August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Arthur St - Bannatyne Av/McDermot Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant AECOM Canada Ltd
Assiniboine Park Dr - Commissary Rd/Zoo Dr   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Mid May 2019
Estimated to end Late June 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Assiniboine Park Dr - Commissary Rd/Zoo Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2019
Estimated to end Late June 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Bannerman Av - Airlies St/McPhillips St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Bayne Cr- London St/Tu Pelo Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Darco Enterprises Ltd.
Beresford Av - Osborne St/Daly St S   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Binscarth St - Corliss Cr/Binscarth St   View Map
Facility type Street
Type of work TBO
Estimated to start Late July 2019
Estimated to end Mid August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Bishop Grandin Bv - Rapid Transit Corridor Overpass   View Map
Facility type Bridge
Type of work New - Rapid Transit Corridor
Estimated to start February 2017
Estimated to end Summer 2020
Approx. % completed 75
Consultant Plenary Roads
Contractor PCL
Additional information Click here
Bishop Grandin Bv / Kenaston Bv   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Bishop Grandin Bv / St Marys Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Brighton Ct/Kildare Av E-Southampton Pl/Wayoata St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Broadway - Sherbrook St/Portage Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant Stantec Consulting Ltd.
Contractor Bituminex Paving Ltd
Broadway/Garry St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Bronx Av - Grey St/Gateway Rd   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Mid June 2019
Estimated to end Early July 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Burrows Av / Keewatin St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Cail By - Jefferson Av/Jefferson Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Caledon Rd - Mapleridge Av/Killarney Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2020
Estimated to end To Be Determined
Approx. % completed 0
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Cavalier Dr / Portage Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Century St/St Matthews Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Century St/Wellington Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Chambers St - Logan Av/Alexander Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Chevrier Bv - Pembina Hw/Trottier By   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Early June 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Chevrier Bv - Trottier By/Waverley St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2018
Estimated to end Early June 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Chief Peguis Greenway Extension   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start Summer 2018
Estimated to end Summer 2020
Approx. % completed 90
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Additional information Click here
Chief Peguis Tl/Gateway Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Chief Peguis Tl/Henderson Hw   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Churchill Dr - Eccles St/Casey St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Coleridge Park Dr   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start To be determined
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Colony St - Ellice Av / Portage Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late May 2019
Estimated to end Mid October 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Coniston St/Lyndale Dr - Claremont Av/Ferndale Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early May 2019
Estimated to end Late June 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Coniston St/Lyndale Dr - Ferndale Av/Lawndale Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early May 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Coniston St/Lyndale Dr - Monck Av/Claremont Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early May 2019
Estimated to end Late June 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Cordova St - Wellington Cr/Academy Rd   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2019
Estimated to end Mid August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Cork Av - Salter St/Sly Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid July 2019
Estimated to end Late August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Corydon Av - Borebank St/Brock St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early July 2019
Estimated to end Fall 2019
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Corydon Av - Cordova St/Lanark St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early July 2019
Estimated to end Fall 2019
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Corydon Av - Daly St N / Hugo St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early June 2019
Estimated to end Early August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Corydon Av / Brock St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Corydon Av / Harrow St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Corydon Av/Conservatory Dr   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Corydon Av/Osborne St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Corydon Av/Pembina Hw   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Dalhousie Dr/Silverstone Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Darwin St- Riel Av/Riverbend Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Day St - McMeans Av E/Kildare Av W   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2020
Estimated to end To Be Determined
Approx. % completed 0
Consultant KGS Group Limited
Contractor Darco Enterprises Ltd.
Day St - McMeans Ave W / Kildare Av W   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant KGS Group Limited
De Bourmont Av - Maginot St/Elizabeth Rd   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Late July 2019
Estimated to end Mid August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
De La Seigneurie Bv - Pauline Boutal Cr/Island Shore Bv   View Map
Facility type Street
Type of work TBO
Estimated to start Late July 2019
Estimated to end Mid August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
De Vries Av - McIvor Av/Springfield Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Darco Enterprises Ltd.
Delorme Pl - Grandmont Bv/Delorme By   View Map
Facility type Street
Type of work TBO
Estimated to start Early July 2019
Estimated to end Late July 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Derek St - Parker Av/Windermere Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Fall 2019
Estimated to end Summer 2020
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Des Meurons St - Vivian Av/Regal Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Desharnais St - Adsum Dr/Margate Rd   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2019
Estimated to end Late August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Devonshire Dr/Plessis Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Donald St - Portage Av/Notre Dame Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid June 2019
Estimated to end Late September 2019
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Borland Construction Inc.
Additional information Click here
Dowker Av - Crowson By/Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor J.C. Paving Ltd.
Drake Bv - Elizabeth Rd/Autumnwood Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Dublin Av - Midland St/St James St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Winter 2019
Estimated to end To Be Determined
Approx. % completed 0
Consultant Stantec Consulting Ltd
Additional information Click here
Dublin Av / Border St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Dublin Avenue Bridge Over Omand's Creek   View Map
Facility type Bridge
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Planned
Consultant Stantec Consulting Ltd
Additional information Click here
Dugald Rd / Ravenhurst St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Dugald Rd at Railway   View Map
Facility type Bridge
Type of work Maintenance
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor ArmCon Ltd.
Dugald Rd/Lagimodiere Bv   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Dunbar Cr - Portsmouth Bv/Andover Av   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Dundurn Pl/Wolseley Av-Maryland St/Walnut St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Edison Av - De Graff Pl/Rothesay St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Darco Enterprises Ltd.
Ellice Av - Maryland St/Arlington St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late June 2019
Estimated to end Late September 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Ellice Av / Toronto St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Ellice Av/Agnes St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Ellice Av/Balmoral St/Colony St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Ellice Av/Maryland St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Emory Rd - Dalhousie Dr/Rice Rd   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Empress St / Jack Blick Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Empress St E - Portage Av/Westway   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Summer 2020
Approx. % completed 80
Consultant Morrison Hershfield Limited
Contractor Borland Construction Inc.
Additional information Click here
Empress St/Maroons Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Ethelbert St - Preston Av/Westminster Av   View Map
Facility type Street
Type of work TBO
Estimated to start Early June 2019
Estimated to end Late June 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Fairhaven Rd - Farmingdale Bv/Lindenwood Dr W   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Fawn Pl- Woodstock Ln/Whitetail Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Darco Enterprises Ltd.
Fermor Av - 500m West of Lagimodiere Bv / CN Overpass   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early June 2019
Estimated to end Late October 2020
Approx. % completed 50
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Fermor Av at Seine River Crossing   View Map
Facility type Bridge
Type of work Culvert Installation
Estimated to start Summer 2018
Estimated to end Summer 2019
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor MD Steele
Additional information Click here
Fermor Av/Archibald St/Royal Salinger Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Fermor Avenue Bridge over the Seine River Rehabilitation and Roadworks from St. Anne's Road to Archibald Street   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2018
Estimated to end Fall 2019
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor MD Steele
Fife St - College Av/Burrows Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Fife St - Inkster Bv/College Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2019
Estimated to end Late September 2019
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Fife St - Inkster Bv/College Av   View Map
Facility type Sidewalk
Type of work New - Sidewalk Construction
Estimated to start Mid May 2019
Estimated to end Late September 2019
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Fife St/ Church Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Flynn St - Barrington Av/Moore Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Darco Enterprises Ltd.
Fort St/York Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Gagnon St- Oxbow Bend Rd/Augier Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Darco Enterprises Ltd.
Garden Grove Dr - Fairgrove By/Burrows Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Garry St - Broadway/Assiniboine   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Mid June 2019
Estimated to end Fall 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Garry St - Notre Dame Av/Portage Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid June 2019
Estimated to end Fall 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Garry St - Portage Av/Broadway   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid June 2019
Estimated to end Fall 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Garry St / Graham Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Garry St / Portage Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Garwood Av - Lilac St/Wentworth St   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2019
Estimated to end Mid August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Glen Oaks Cv - Norlorne Dr/Norlorne Dr   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2019
Estimated to end Mid September 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Gleneagles Rd - Willow Point Rd/Pebble Beach Rd   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2019
Estimated to end Late August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Governors Ct - Beecher Av/Templeton Av   View Map
Facility type Street
Type of work TBO
Estimated to start Late May 2019
Estimated to end Mid June 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Grant Av / Stafford St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Grant Av/Kenaston Bv   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Greene Av/Linden Av - Woodvale St/Kildonan Dr   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Summer 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Greenwood Av- Wyoming St/ #49 Greenwood Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Late July 2019
Estimated to end Late August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Haig Av- Egerton Rd/Des Meurons St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Fall 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Hamel Av - Des Meurons St/Aulneau St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Darco Enterprises Ltd.
Haresford Cr- Hawkins Cr/Novavista Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Fall 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Hargrave St - Notre Dame Av/McDermot Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 50
Consultant AECOM Canada Ltd
Hargrave St - William Av/Bannatyne Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 10
Consultant AECOM Canada Ltd
Harkness St/Stradbrook Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Hazelwood Av - Dells Cr/Dakota St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Darco Enterprises Ltd.
Henderson Hw/Larsen Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Henlow By - Dovercourt Dr/Fultz Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Henlow By - Scurfield Bv/Dovercourt Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Higgins Av - Henry Av/Princess St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2019
Estimated to end Mid August 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Highfield St/Coniston St - Chandos Av/Crawford Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Summer 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Highfield St/Coniston St - Claremont Av/Ferndale Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early May 2019
Estimated to end Late June 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Hudson St - Clarence Av/Chevrier Bv   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Fall 2019
Estimated to end Summer 2020
Approx. % completed 50
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Hutchings St - Inkster Bv/Sheppard St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Summer 2019
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Inkster Bv - Fife St/Milner St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early June 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor J.C. Paving Ltd.
Inkster Bv/70m West of Lansdowne Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Inkster Bv/Fife St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Inkster Bv/McPhillips St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Jacques Av - Skowron Cr/Silver Fields Ln   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Jamison Av - Roch St/Henderson Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Jefferson Av/65m West of Watson St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Jefferson Av/McPhillips St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Jubilee Av/Pembina Hw   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Kairistine Ln - Kinver Av/Dexter St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early September 2019
Estimated to end Summer 2020
Approx. % completed 40
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Keewatin St - Inkster Bv/Burrows Av   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant Stantec Consulting Ltd
Contractor Darco Enterprises Ltd.
Additional information Click here
Kenny St - Marion St/Kitson St   View Map
Facility type Street
Type of work TBO
Estimated to start Early June 2019
Estimated to end Late June 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Kildonan Settlers Bridge   View Map
Facility type Bridge
Type of work Maintenance
Estimated to start Winter 2019
Estimated to end To Be Determined
Approx. % completed 0
Consultant AECOM Canada Ltd
King St/Alexander Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Kings Park   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Knightsbridge Dr- Ashworth St/Meadowood Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Lagimodiere Bv - Dugald Rd/Regent Av W   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant Stantec Consulting Ltd
Contractor Bituminex Paving Ltd
Lagimodiere Bv / Almey Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Lagimodiere Bv and Sage Creek Bv Intersection   View Map
Facility type Street
Type of work Intersection Improvement
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant Stantec Consulting Ltd.
Contractor Bituminex Paving Ltd
Lagimodiere Bv/Fermor Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Larsen Av - Brazier St/Henderson Hw   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Darco Enterprises Ltd.
Lavalee Rd/St Annes Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Leila Av/ 157m East of McPhillips St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Leila Av/ 60m East of Simkin Dr   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Leila Av/Main St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Lodge Av - Davidson St/Moray St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed 75
Consultant WSP Canada Inc
Contractor Darco Enterprises Ltd.
Logan Av/Keewatin St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Logan Av/Princess St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Lombard Av / Westbrook St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To be determined
Estimated to end To be determined
Approx. % completed 0
Consultant HTFC Planning and Design
Lombard Av / Westbrook St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
London St - Prince Rupert Av/Munroe Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early July 2019
Estimated to end Early August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Loudoun Rd - Wilkes Av/Wyper Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2018
Estimated to end Late June 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Hugh Munro Construction
Maddin Cr - Manila Rd/Manila Rd   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2019
Estimated to end Mid August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Madeline St - Edward Av W/Harold Av W   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Late July 2019
Estimated to end Late August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Magnus Av - Shaughnessy St/Lawrence St   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Main St - Higgins Av / Lombard Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid August 2019
Estimated to end Summer 2020
Approx. % completed 80
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Main St - McAdam Av/ Kildonan Pk Golf Cs.   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late April 2019
Estimated to end Mid October 2019
Approx. % completed Complete
Consultant Stantec Consulting Ltd
Main St/ McKay Dr   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Main St/ Smithfield Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Main St/Hartford Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Main St/Kingsbury Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Main St/Partridge Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Main St/Seven Oaks Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Manthorne Av - Southwell Rd/Sunny Hills Rd   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Maralbo Av W/Parkville Dr - St Marys Rd/Dunkirk Dr   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early September 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Marion St/Dawson Rd N   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Marion St/Lagimodiere Bv   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Maureen St - Barron Dr/Assiniboine Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor J.C. Paving Ltd.
McGillivray Bv - Rapid Transit Corridor Overpass   View Map
Facility type Bridge
Type of work New - Rapid Transit Corridor
Estimated to start Spring 2017
Estimated to end Summer 2020
Approx. % completed 75
Consultant Plenary Roads
Contractor PCL
Additional information Click here
McGregor St - Selkirk Av/Mountain Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
McIvor Av - Reiny Dr/Henderson Hw   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Mid June 2019
Estimated to end Late June 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
McPhillips St - Jarvis Av/Logan Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Mid June 2019
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Borland Construction Inc.
McPhillips St - Logan Av/Jarvis Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Mid June 2019
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Borland Construction Inc.
McPhillips St / Kingsbury Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
McPhillips St/Burrows Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Melrose Av W/Pandora Av W-Bond St/Winona St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Memorial Bv - Portage Av/St Mary Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late May 2019
Estimated to end Mid October 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Memorial Bv - Portage Av/St Mary Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Late May 2019
Estimated to end Mid October 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Memorial Bv - York Av/St Mary Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late May 2019
Estimated to end Mid October 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Memorial Bv / 100m South of Portage Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Milan St - Oswald By/Hewitt Cr   View Map
Facility type Street
Type of work TBO
Estimated to start Late July 2019
Estimated to end Mid August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Molson St - Nottingham Av/Union Av E   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Darco Enterprises Ltd.
Moray St - Saulteaux Cr/Moray St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Morpeth Bv - North End/Taylor Av   View Map
Facility type Sidewalk
Type of work New - Sidewalk Construction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant AECOM Canada Ltd
Mountain Av - Arlington St/Airlies St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Mulvey Av - Arbuthnot St/Lilac St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor J.C. Paving Ltd.
Munroe Av/Watt St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Mutchmor Cs- Tu Pelo Av/Tu Pelo Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Darco Enterprises Ltd.
Nairn Av - Grey St/Panet Rd   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Nelson River Construction Inc.
Nairn Av - Panet Rd/Grey St   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Nelson River Construction Inc.
Ness Av - Olive St/Moray St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Mid May 2019
Estimated to end Late June 2019
Approx. % completed Complete
Consultant Stantec Consulting Ltd
Contractor Bituminex Paving Ltd
Ness Av - Sturgeon Rd/Pebblewood Ln   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor J.C. Paving Ltd.
Neville St - Margate Rd/Mapleton Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late July 2019
Estimated to end Mid August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Newcroft Rd / Shamrock Dr   View Map
Facility type Sidewalk
Type of work New - Sidewalk Construction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Nora St- Logan Av/Alexander Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late August 2019
Estimated to end Mid October 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Norcross Cr - Shorehill Dr/Shorehill Dr   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2019
Estimated to end Mid August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Northwest Hydro Corridor Pathway - Leila Av / Church Av   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Norwood & Main Street Bridge   View Map
Facility type Bridge
Type of work Maintenance
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant Morrison Hershfield Limited
Notre Dame Av - Portage Av/Princess St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid June 2019
Estimated to end Late September 2019
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Additional information Click here
Notre Dame Av/King Edward St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Notre Dame Av/McPhillips St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Notre Dame Av/Weston St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Nurgitz By - Swailes Av/Swailes Av   View Map
Facility type Street
Type of work TBO
Estimated to start Late May 2019
Estimated to end Mid June 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Palms Bv - Garden Grove Dr/Burrows Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2020
Estimated to end To Be Determined
Approx. % completed 0
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Partridge Av/McGregor St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Partridge Av/Royal Av-Powers St/Andrews St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Pately Cr - Paddington Rd/Burland Av   View Map
Facility type Street
Type of work TBO
Estimated to start Mid July 2019
Estimated to end Early August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Pembina Hw - Grant Av/Jessie Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Additional information Click here
Pembina Hw - Grant Av/Osborne St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Additional information Click here
Pembina Hw - Jessie Av/Osborne St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed 80
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Additional information Click here
Pembina Hw - Minerva Av/St. Norbert Bridge   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Nelson River Construction Inc.
Pembina Hw - Rapid Transit Corridor Underpass   View Map
Facility type Bridge
Type of work New - Rapid Transit Corridor
Estimated to start Spring 2017
Estimated to end Summer 2020
Approx. % completed 75
Consultant Plenary Roads
Contractor PCL
Additional information Click here
Pembina Hw/Southpark Dr   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Peony Av - Verbena St/Viola St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Pioneer Av/Westbrook St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Portage Av / Portage Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Portage Av / Ronald St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Portage Av/Linwood St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Portage Av/Mount Royal Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Preston Av/Westminster Av-Ethelbert St/Home St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Princess St - Willaim Av/Donald St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2019
Estimated to end Spring 2019
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Princess St - William Av/Notre Dame Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2019
Estimated to end Spring 2019
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Additional information Click here
Provencher Bridge   View Map
Facility type Bridge
Type of work Maintenance
Estimated to start Fall 2019
Estimated to end Winter 2019
Approx. % completed 0
Consultant Dillon Consulting Limited
Contractor ArmCon Ltd.
Provencher Bv - Des Meurons St/Archibald St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid May 2019
Estimated to end Late June 2019
Approx. % completed Complete
Consultant Stantec Consulting Ltd.
Contractor Bituminex Paving Ltd
Provencher Bv at Seine River   View Map
Facility type Bridge
Type of work Maintenance
Estimated to start Fall 2019
Estimated to end Winter 2019
Approx. % completed 0
Consultant Dillon Consulting Limited
Contractor ArmCon Ltd.
Pulberry St - Parkville Dr/St Michael Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Darco Enterprises Ltd.
Raleigh St - Donwood Dr/Springfield Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2020
Estimated to end To Be Determined
Approx. % completed 0
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Raleigh St - Munroe Av/Chalmers Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Rapid Transit Corridor - Phase 2   View Map
Facility type Rapid Transit Corridor
Type of work New - Rapid Transit Corridor
Estimated to start Summer 2016
Estimated to end Summer 2020
Approx. % completed 75
Consultant Plenary Roads
Contractor PCL
Additional information Click here
Regent Av W/Lagimodiere Bv   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Roanoke St - Whittier Av E/Harvard Av E   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2019
Estimated to end Mid August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Roberts Cr - Agnes Arnold Pl/Jefferson Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Roblin Bv - Assiniboine Park Dr/Shaftesbury Bv   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2019
Estimated to end Mid October 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Roblin Bv/247m E of Chalfont Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Roch St - Sydney Av/Trent Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Late July 2019
Estimated to end Mid August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Rupert Av - Main St/King St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant AECOM Canada Ltd
Salter St / Mountain Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Salter St / Selkirk Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Sanford Fleming Rd - Devonshire Dr/Plessis Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Darco Enterprises Ltd.
Sara Av/Westminster Av-Langside St/Furby St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Sargent Av/Dominion St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Sargent/Ellice Av-Arlington St/Alverstone St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Mid June 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Saskatchewan Av   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start Late July 2019
Estimated to end Late August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Saskatchewan Av - 2450 Saskatchewan Av/Moray St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late May 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Saskatchewan Av - Moray St/Sturgeon Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late May 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Scurfield Park Path   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start Mid July 2019
Estimated to end Mid August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Selkirk Av/Main St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Selkirk Av/McPhillips St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Semple Av - McGregor St/End   View Map
Facility type Street
Type of work TBO
Estimated to start Late May 2019
Estimated to end Mid June 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Semple Av/Kilbride Av-Main St/Aikins St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Shenfield Rd - Roblin Bv / End   View Map
Facility type Street
Type of work TBO
Estimated to start Early July 2019
Estimated to end Late July 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Sherbrook St - McDermot Av/Cumberland Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant Stantec Consulting Ltd.
Contractor Darco Enterprises Ltd.
Sherbrook St / Westminster Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Sherwin Rd - Notre Dame Av / Saskatchewan Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Slaw Rebchuk Bridge   View Map
Facility type Bridge
Type of work Maintenance
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor M.D. Steele Construction Ltd.
Speers Rd - Cottonwood Rd/Crestwood Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
St James St - 190m North of Ellice Av/Sargent Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late July 2019
Estimated to end Summer 2020
Approx. % completed 50
Consultant Morrison Hershfield Limited
St James St/Sargent Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
St Mary Av - Vaughan St/Memorial Bv   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Spring 2018
Estimated to end Summer 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
St Mary Av/Garry St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
St Mary Av/Osborne St N/Memorial Bv   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
St Matthews Av/Valour Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Stafford St - Corydon Av / McMillan Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early June 2019
Estimated to end Late June 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Stafford St - Yale Av / Corydon Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early June 2019
Estimated to end Summer 2020
Approx. % completed 75
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Stardust Av - McPhillips St/Watson St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late August 2019
Estimated to end Mid October 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Sterling Lyon Pw - Victor Lewis Dr/Kenaston Bv   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Nelson River Construction Inc.
Sterling Lyon Pw - Wilkes Av/Kenaston Bv   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Nelson River Construction Inc.
Stradford St - Risbey Cr/Hamilton Av   View Map
Facility type Street
Type of work TBO
Estimated to start Early July 2019
Estimated to end Late July 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Strathcona St - Ellice Av/St Matthews Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Darco Enterprises Ltd.
Sturgeon Creek Path   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start Late July 2019
Estimated to end Late August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Sun Valley Dr - Kingsdale Rd/Sunny Hills Rd   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early July 2019
Estimated to end Late July 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Sunny Hills Rd - Sun Valley Dr/Sunny Hills Rd   View Map
Facility type Street
Type of work TBO
Estimated to start Mid July 2019
Estimated to end Early August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Swindon Wy - Portsmouth Bv/Park Bv E   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Darco Enterprises Ltd.
Talbot Av - Foster St/Grey St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Darco Enterprises Ltd.
Taylor Av/Waverley St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Thatcher Dr - University Cr/Pembina Hw   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Fall 2019
Estimated to end Summer 2020
Approx. % completed 10
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Thom Av E - Wabasha St/Day St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Late May 2019
Estimated to end Mid June 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Thom Av W - Day St/Winona St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Late May 2019
Estimated to end Mid June 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Traill Av - Mount Royal Rd/Portage Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Darco Enterprises Ltd.
Traverse Av - Dollard Bv/Marion St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end Summer 2020
Approx. % completed 50
Consultant Dillon Consulting Limited
Contractor Darco Enterprises Ltd.
Traynor By - St Michael Rd/St Michael Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Darco Enterprises Ltd.
Troy Av - McPhillips St/Fife St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
University Cr/Dafoe Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
University Cr/Pembina Hw   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Villeneuve Bv - Ducharme Av/Des Trappistes St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Fall 2019
Estimated to end Summer 2020
Approx. % completed 50
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Wall St/Portage Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Walmer St/Kirkdale St - Lawndale Av/Birchdale Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Summer 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Wardlaw Av/Osborne St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Waverley St - Grandmont Bv/City Limit   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late July 2019
Estimated to end Fall 2020
Approx. % completed 40
Consultant Dillon Consulting Limited
Contractor Tri - Core Projects Ltd.
Waverley St / Lindenwood Pl / Seel Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Waverley St/Hurst Wy/Wilkes Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Waverley Underpass Project - Taylor Av / Waverley St / Wilkes Av / Grant Av   View Map
Facility type Street
Type of work Slope Restoration
Estimated to start Spring 2017
Estimated to end Fall 2019
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Waverley Underpass Project - Taylor Av / Waverley St / Wilkes Av / Grant Av   View Map
Facility type Bridge
Type of work New - Bridge
Estimated to start Spring 2017
Estimated to end Fall 2019
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Wellington Av/Sargent Av-Banning St/Lipton St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Wellington Av/Sargent Av-Toronto St/Beverley St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Wellington Cr   View Map
Facility type Sidewalk
Type of work New - Sidewalk Construction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
West Alexander Pedestrian and Cycling Corridor   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant Stantec Consulting Ltd.
Contractor Darco Enterprises Ltd.
Additional information Click here
West Alexander Pedestrian and Cycling Corridor   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start Summer 2017
Estimated to end Spring 2019
Approx. % completed Complete
Consultant Stantec Consulting Ltd.
Contractor Darco Enterprises Ltd.
Additional information Click here
Westminster Av/Wolseley Av-Evanson St/Wolseley Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Mid June 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Whitegates Cr - Barron Dr/Maureen St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor J.C. Paving Ltd.
Whitetail Dr- Chalfont Rd/Eldridge Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Darco Enterprises Ltd.
Whitley Dr- Ashworth St/Hawkins Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Winston Rd - Portage Av/Assiniboine Av   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2019
Estimated to end Late August 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Wittenberg Rd - Scurfield Bv/Fleetwood Rd   View Map
Facility type Street
Type of work TBO
Estimated to start Early July 2019
Estimated to end Late July 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Woodhaven Park Path   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed 50
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Woodstock Ln- North End/Eldridge Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Darco Enterprises Ltd.
Yarwood Av/Wellington Av-Ingersoll St/Sherburn St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
York Av - Memorial Bv / Osborne St N   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late May 2019
Estimated to end Mid October 2019
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
York Av/Garry St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
York Av/Memorial Bv   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Summer 2019
Estimated to end Fall 2019
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Youville St - Bertrand St/Goulet St   View Map
Facility type Street
Type of work TBO
Estimated to start Early June 2019
Estimated to end Late June 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd

Disclaimer and Indemnity:

The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.

The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.

By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.