Site Accessibility Information Access Key 1 to Skip to Top Navigation Access Key 2 to Skip to the Three One One link Access Key 3 to Skip to City of Winnipeg Main Menu Access Key 4 to Skip to Left Navigation Menu Access Key 5 to Skip to Content area Access Key 6 to Skip to Right Sidebar content area Access Key 7 to Skip to Footer Links
City of Winnipeg
|  Link to the City of Winnipeg French websiteFrançais  |
COVID-19: City of Winnipeg response and latest updates on City facilities and services COVID-19 : Mesures prises par la Ville de Winnipeg et dernières nouvelles sur les installations et services municipaux
Public Works

Road Construction List

The roadway construction list provides project information in alphabetical order by street name. Project information is available by location in both map and list format. Please see the regional street lane closures page for information on current lane closures on major streets.

How to use the construction list

Click on the + beside the project name. A dropdown box will appear with these project details:

  1. type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
  2. type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
  3. estimated to start,
  4. estimated to end,
  5. approximate percentage completed:
    • Pre-Construction – Construction phase has not started.
    • 0% – Construction contract is in place, but crews have not mobilized to the site.
    • 5% – Crews have mobilized to the site and construction has just begun.
    • 10% 90% – An approximation of progress; construction is well underway.
    • 95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
    • COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
  6. consultant information, and
  7. contractor information.

You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.

Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.

A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z


City of Winnipeg - Public Works Capital Projects
(Last updated on December 3, 2020 @ 7:00 PM)
 
 
View All on Map


Academy Rd/Kingsway - Campbell St/Borebank St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start May 26/2020
Estimated to end Early July 2020
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Wintec Building Services Inc.
Document
2020 Construction Notice_Borebank Street_Campbell Street_Alley Phase 2.pdf
Academy Rd/Kingsway - Elm St/Oak St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start June 8/2020
Estimated to end Late July 2020
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Wintec Building Services Inc.
Document
2020 Construction Notice_Oak Street_Elm Street_Alley Phase 1.pdf
Aikins St - Enniskillen Av / McAdam Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 27/2020
Estimated to end Summer 2021
Approx. % completed 70
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Albert St - Bannatyne Av/McDermot Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Complete
Consultant AECOM Canada Ltd
Albrin Park Path Renewal   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start June 11/2020
Estimated to end Early July 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Document
2020 Construction Notice_Albrin Park Pathway.pdf
Alexander Av - Princess St / Stanley St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 2/2020
Estimated to end Late August 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2020 Construction Notice_Alexander Avenue.pdf
Archibald St - Elizabeth Rd / Cottonwood Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 29/2020
Estimated to end Late September 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Bituminex Paving Ltd
Additional information Click here
Document
2020 Construction Notice_Archibald Street.pdf
Archibald St - Marion St / St Catherine St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2021
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor To Be Determined
Additional information Click here
Archibald St - Messier St / Kavanagh St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 2021
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor To Be Determined
Additional information Click here
Archibald St - Plinguet St / Doucet St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 2022
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor To Be Determined
Additional information Click here
Archibald St - Plinguet St / Messier St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2020
Estimated to end To Be Determined
Approx. % completed Planned
Archibald St - St Catherine St / Elizabeth Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor To Be Determined
Additional information Click here
Arlington St - St Matthews Av/Portage Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start May 25/2020
Estimated to end Mid June 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Document
2020 Construction Notice_Arlington Sidewalk.pdf
Arlington Street Overpass   View Map
Facility type Bridge
Type of work Maintenance
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Complete
Armstrong Av/Leila Av - Salter St/Weinberg Rd   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start June 8/2020
Estimated to end Late July/2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Document
2020 Construction Notice_Salter Street_Weinberg Road_Alley.pdf
Arthur St - Bannatyne Av/McDermot Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Complete
Consultant AECOM Canada Ltd
Ashland Av - Darling St / Churchill Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 27/2020
Estimated to end Mid October 2020
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Borland Construction Inc.
Document
2020 Construction Notice_Ashland Avenue.pdf
Ashland Av - Eccles St / Darling St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 6/2020
Estimated to end Mid October 2020
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Borland Construction Inc.
Document
2020 Construction Notice_Ashland Avenue.pdf
Ashland Av - Mabel St / Eccles St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 6/2020
Estimated to end Mid October 2020
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Borland Construction Inc.
Document
2020 Construction Notice_Ashland Avenue.pdf
Ashworth St S - Warde Av/Baisinger Dr   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2020
Estimated to end Fall 2020
Approx. % completed Planned
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Atlantic Av - Duke St / Mcphillips St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 27/2020
Estimated to end Mid October 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Balmoral St - Portage Av/St Mary Av   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Balmoral St - St Mary Av/Broadway   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2020
Estimated to end Fall 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Bannerman Av - Duke St / Mcphillips St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 27/2020
Estimated to end Mid October 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Bernadine Crescent Park Path Renewal   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start May 25/2020
Estimated to end Mid June 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Document
2020 Construction Notice_Bernadine Crescent.pdf
Bertrand St - Des Meurons St/De La Morenie St   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2020
Estimated to end Mid August 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Besant St - North Limit / Munroe Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 24/2020
Estimated to end Mid October 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2020 Construction Notice_Besant Street.pdf
Bishop Grandin Bv - Bishop Grandin Bv Bridge (Fort Garry Bridge) / Rapid Transit Corridor   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Complete
Consultant Dillon Consulting Limited
Bishop Grandin Bv - St Annes Rd / Lagimodiere Bv   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Complete
Consultant Dillon Consulting Limited
Blackwater By - Blackwater By / Charing Cross Cr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 22/2020
Estimated to end Mid August 2020
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Document
2020 Construction Notice_Blackwater Bay.pdf
Blackwater By - End / Charing Cross Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 22/2020
Estimated to end Mid August 2020
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Document
2020 Construction Notice_Blackwater Bay.pdf
Booth Dr - Bruce Av / Portage Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 22/2020
Estimated to end Late October 2020
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Boyd Av - Powers St/Salter St   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Braeside Pl - Point West Dr / End   View Map
Facility type Street
Type of work TBO
Estimated to start Spring 2021
Estimated to end Summer 2021
Approx. % completed 0
Consultant KGS Group Limited
Broadway - Osborne St / Main St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Summer 2023
Approx. % completed Planned
Consultant AECOM Canada Ltd
Brookside Bv - Inkster Bv / Mollard Rd   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Complete
Consultant Dillon Consulting Limited
Burrows Av - Main St/Powers St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 1/2020
Estimated to end Early August 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Document
2020 Construction Notice_Burrows Avenue.pdf
Burrows Av / Keewatin St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Caledon Rd - Mapleridge Av/Killarney Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Carlton St - Ellice Av / Portage Av   View Map
Facility type Street
Type of work TBO
Estimated to start August 17/2020
Estimated to end Early October 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Bituminex Paving Ltd
Additional information Click here
Document
2020 Construction Notice_Carlton Street.pdf
Carriage By - Heritage Bv/Heritage Bv   View Map
Facility type Street
Type of work TBO
Estimated to start August 31/2020
Estimated to end Late October 2020
Approx. % completed Complete
Consultant KGS Group Limited
Document
2020 Construction Notice_Carriage Bay.pdf
Casey St - Ashland Av/Balfour Av   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Caslon Pl - Councillor By / Councillor By   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 30/2020
Estimated to end Mid September 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Document
2020 Construction Notice_Caslon Place.pdf
Cathedral Av - Rail x-ing west of Sinclair St / Arlington St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 27/2020
Estimated to end Late October 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Cecil St - Logan Av/Alexander Av   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Chalfont Rd - Grant Av/Cathcart St   View Map
Facility type Street
Type of work TBO
Estimated to start September 7/2020
Estimated to end Late September 2020
Approx. % completed Complete
Consultant KGS Group Limited
Document
2020 Construction Notice_Chalfont Avenue.pdf
Chalmers Av - Watt St/Brazier St   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2020
Estimated to end Fall 2020
Approx. % completed Planned
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Chancellor Drive - Gaylene Pl / West Lake Cr   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start May 26/2020
Estimated to end Mid June 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Chief Peguis Greenway Extension   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Additional information Click here
Chief Peguis Greenway Extension   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start Summer 2018
Estimated to end Summer 2020
Approx. % completed 90
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Additional information Click here
Claremont Av / Ferndale Av - Walmer St / Kirkdale St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start August 25/2020
Estimated to end Mid October 2020
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Asphaltec Paving
Document
2020 Construction Notice_Ferndale Avenue_Claremont Avenue_Alley.pdf
Colchester By - Holland Bv / Holland Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 22/2020
Estimated to end Late October 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Colony St - Portage Av / St Mary Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Coniston St / Lyndale Dr - Gauvin St / Chandos Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start August 4/2020
Estimated to end Late September 2020
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2020 Construction Notice_Chandos_Gauvin_Completion Notice.pdf
Corydon Av - Borebank St/Brock St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 19/2020
Estimated to end Late October 2020
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Additional information Click here
Corydon Av - Cambridge St / Thurso St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Stantec Consulting Ltd
Additional information Click here
Corydon Av - Cordova St/Lanark St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 19/2020
Estimated to end Late October 2020
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Additional information Click here
Corydon Av - Thurso St / Stafford St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 11/2020
Estimated to end Summer 2021
Approx. % completed 70
Consultant Stantec Consulting Ltd
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Document
2020 Construction Notice_Corydon Avenue.pdf
Corydon Av - Waterloo St / Cambridge St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 11/2020
Estimated to end Mid September 2020
Approx. % completed Complete
Consultant Stantec Consulting Ltd
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Document
2020 Construction Notice_Corydon Avenue.pdf
Corydon Av/Fleet Av - Oak St/Ash St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Spring 2021
Estimated to end Summer 2021
Approx. % completed Deferred
Consultant WSP Canada Inc
Contractor Wintec Building Services Inc.
Document
2020 Construction Deferral Notice_Ash St_Oak St_Alley.pdf
Councillor By - Manila Rd / Manila Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 6/2020
Estimated to end Late August 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Document
2020 Construction Notice_Councillor Bay.pdf
Crossgate Rd - St Martin Bv/Whitehall Bv   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2020
Estimated to end Fall 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Dakota St - Abbotsford Cr / College Jeanne-Suave   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Complete
Consultant Dillon Consulting Limited
Dakota St - Beliveau Rd / St Marys Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Summer 2023
Approx. % completed Planned
Dakota St - Bishop Grandin Bv / Beliveau Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Summer 2023
Approx. % completed Planned
Dakota St - Southglen Bv / Hyatt Pl   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Complete
Consultant Dillon Consulting Limited
Darwin St - Arden Av/St Michael Rd   View Map
Facility type Street
Type of work TBO
Estimated to start October 5/2020
Estimated to end Late October 2020
Approx. % completed Complete
Consultant KGS Group Limited
Document
2020 Construction Notice_Darwin Street.pdf
Day St - McMeans Av E / Kildare Av W   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 11/2020
Estimated to end Late June 2020
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Darco Enterprises Ltd.
Document
2020 Construction Notice_Day Street.pdf
Day St - McMeans Ave W / Kildare Av W   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start May 11/2020
Estimated to end Late June 2020
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Darco Enterprises Ltd.
Document
2020 Construction Notice_Day Street.pdf
Day St - Pandora St / Regent Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Dee St - Midmar Av/Logan Av   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2020
Estimated to end Mid August 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Denman Cr - Kirkbridge Dr/Brentlawn Bv   View Map
Facility type Street
Type of work TBO
Estimated to start September 21/2020
Estimated to end Late October 2020
Approx. % completed Complete
Consultant KGS Group Limited
Document
2020 Construction Notice_Denman Crescent.pdf
Derek St - Parker Av/Windermere Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Des Meurons St - Carriere Av / Morier Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 20/2020
Estimated to end Late October 2020
Approx. % completed 50
Consultant Dillon Consulting Limited
Contractor Wintec Building Services Inc.
Document
2020 Construction Notice_Des Meurons Street.pdf
Des Meurons St - Goulet St / Marion St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Summer 2023
Approx. % completed Planned
Des Meurons St - Marion St / Horace St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start August 31/2020
Estimated to end Early October 2020
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Asphaltec Paving
Document
2020 Construction Notice_Des Meurons East Alley.pdf
Donald - Broadway / Gertrude Av (not including Bridge)   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Consultant AECOM Canada Ltd
Donald - Broadway / Gertrude Av (not including Bridge)   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Donald - St Mary / Broadway   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2020
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Doncaster St - Blanche Av / Corydon Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start May 19/2020
Estimated to end Early June 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Document
2020 Construction Notice_Doncaster Street.pdf
Drake Bv - Autumnwood Rd / Cottonwood Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 13/2020
Estimated to end Late August 2020
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Document
2020 Construction Notice_Drake Boulevard.pdf
Dublin Av - Midland St/St James St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2020
Estimated to end Fall 2020
Approx. % completed Complete
Consultant Stantec Consulting Ltd
Contractor Bayview Construction Ltd
Additional information Click here
Dublin Avenue Bridge Over Omand's Creek   View Map
Facility type Bridge
Type of work Reconstruction
Estimated to start Mid May 2020
Estimated to end Fall 2020
Approx. % completed Complete
Consultant Stantec Consulting Ltd
Contractor Bayview Construction Ltd
Additional information Click here
Document
2020 Construction Notice_Dublin Avenue Bridge.pdf
Dudley Av - Guelph St / Wilton St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start May 19/2020
Estimated to end Early June 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Document
2020 Construction Notice_Dudley Avenue.pdf
Dufferin Av - Sinclair St/Arlington St   View Map
Facility type Street
Type of work TBO
Estimated to start Spring 2021
Estimated to end Summer 2021
Approx. % completed 0
Consultant KGS Group Limited
Duke St - Polson Av / Bannerman Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 27/2020
Estimated to end Mid October 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Dunkirk Dr - Fermor Av / Norberry Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Additional information Click here
Dunkirk Dr - Fermor Av / St Marys Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Additional information Click here
Dunkirk Dr - Norberry Dr / St Marys Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Additional information Click here
Durado By - Kildare Av E/Kildare Av E   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2020
Estimated to end Fall 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Durward St - Templeton Av/Tully Rd   View Map
Facility type Street
Type of work TBO
Estimated to start Spring 2021
Estimated to end Summer 2021
Approx. % completed 0
Consultant KGS Group Limited
Edmonton St - Ellice Av / Cumberland Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Summer 2023
Approx. % completed Planned
Ellice Av - Carlton St/Donald St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start August 31/2020
Estimated to end Late September 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Document
2020 Construction Notice_Ellice Avenue Sidewalk.pdf
Ellice Av/Portage Av - Furby St/Sherbrook St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start June 29/2020
Estimated to end Mid September 2020
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Asphaltec Paving
Ellice Av/St Matthews Av - Victor St/Toronto St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start July 6/2020
Estimated to end Late August 2020
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Asphaltec Paving
Document
2020 Construction Notice_Toronto Street_ Victor Avenue_Alley.pdf
Empress St E - Portage Av/Westway   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 4/2020
Estimated to end Late September 2020
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Borland Construction Inc.
Additional information Click here
Document
2020 Construction Notice_Empress Street.pdf
Erin St - Notre Dame Ave / Sargent Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Summer 2023
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Additional information Click here
Erin St - Sargent Av / Wolever Ave   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Additional information Click here
Evans St / Seine - Prosper St / St Catherine St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start August 27/2020
Estimated to end Mid October 2020
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2020 Construction Notice_Prosper_St Catherine_Completion Notice.pdf
Farwell By - Donnelly St / Donnelly St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 6/2020
Estimated to end Mid October 2020
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Borland Construction Inc.
Document
2020 Construction Notice_Farwell Bay.pdf
Fermor Av - 500m West of Lagimodiere Bv / CN Overpass   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 19/2020
Estimated to end Mid August 2020
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Additional information Click here
Document
2020 Construction Notice_Fermor Avenue.pdf
Fermor Av - St. Vital Pedestrian Underpass   View Map
Facility type Bridge
Type of work Pedestrian Corridor Improvements
Estimated to start Mid May 2020
Estimated to end Fall 2020
Approx. % completed Complete
Consultant WSP Canada Inc
Additional information Click here
Document
2020 Construction Notice_Fermor Avenue.pdf
Fernwood Av - St Annes Rd/St Andrew Rd   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2020
Estimated to end Fall 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Ferry Rd - St Matthews Av / Silver Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start September 14/2020
Estimated to end Late October 2020
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Document
2020 Construction Notice_Ferry Road.pdf
Fleury Pl - Fontaine Cr / Fontaine Cr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 13/2020
Estimated to end Late September 2020
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Document
2020 Construction Notice_Fleury Place.pdf
Forest Cove Dr - Garton Av/Jonathan Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 24/2020
Estimated to end Mid October 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Document
2020 Construction Notice_Forest Cove Drive.pdf
Fort - Graham Av / Broadway   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 11/2020
Estimated to end Late September 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Bituminex Paving Ltd
Additional information Click here
Document
2020 Construction Notice_Fort Street.pdf
Furness By - Burland Av/Healy Cr   View Map
Facility type Street
Type of work TBO
Estimated to start October 5/2020
Estimated to end Late October 2020
Approx. % completed Complete
Consultant KGS Group Limited
Document
2020 Construction Notice_Furness Bay.pdf
Gallagher Av W - Keewatin St/Dee St   View Map
Facility type Street
Type of work TBO
Estimated to start Spring 2021
Estimated to end Summer 2021
Approx. % completed 0
Consultant KGS Group Limited
Gertrude Av - Nassau St N / Osbourne St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 6/2020
Estimated to end Mid September 2020
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Borland Construction Inc.
Document
2020 Construction Notice_Gertrude Avenue.pdf
Goulet St - Braemar Av / Youville St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Summer 2023
Approx. % completed Planned
Government Av - Besant St / Louelda St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 20/2020
Estimated to end Mid September 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2020 Construction Notice_Government Avenue.pdf
Graham Av - Hargrave St / Carlton St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Grant Av - Montrose St / Lanark St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Summer 2023
Approx. % completed Planned
Grant Av - Montrose St / Queenston St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Summer 2023
Approx. % completed Planned
Grant Av / Stafford St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Grey St - Concordia Av/Simpson Av   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Grey St - Nottingham Av / Union Av E   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 20/2020
Estimated to end Late August 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2020 Construction Notice_Grey Street.pdf
Grosvenor Av/Corydon Av - Montrose St/Ash St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start June 9/2020
Estimated to end Mid October 2020
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Wintec Building Services Inc.
Document
2020 Construction Notice_Ash Street_Montrose Street_Alley Phase 2.pdf
Grosvenor Av/Corydon Av - Oxford St/Waverley St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Spring 2021
Estimated to end Summer 2021
Approx. % completed Deferred
Consultant WSP Canada Inc
Contractor Wintec Building Services Inc.
Document
2020 Construction Deferral Notice_ Waverley St_Oxford St_Alley.pdf
Hargrave St - Ellice Av / Portage Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2020
Estimated to end Late July 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Bituminex Paving Ltd
Additional information Click here
Document
2020 Construction Notice_Hargrave Street.pdf
Hargrave St - Notre Dame Av/McDermot Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 6/2020
Estimated to end Late August 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Hargrave St - William Av/Bannatyne Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 27/2020
Estimated to end Mid October 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Hargrave St - York Av / Broadway   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Summer 2023
Approx. % completed Planned
Consultant AECOM Canada Ltd
Additional information Click here
Harkness St/Stradbrook Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Harvlong Av - Lake Ridge Rd/Topaz Rd   View Map
Facility type Street
Type of work TBO
Estimated to start August 31/2020
Estimated to end Mid September 2020
Approx. % completed Complete
Consultant KGS Group Limited
Document
2020 Construction Notice_Harvlong Avenue.pdf
Hatcher Rd - Bournais Dr / Rougeau Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 25/2020
Estimated to end Mid July 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises
Document
2020 Construction Notice_Hatcher Road.pdf
Henderson Hw - McLeod Av / Leighton Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Highfield St / Coniston St - Tache Av / Monck Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start August 5/2020
Estimated to end Late September 2020
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2020 Construction Notice_Monck_Tache_Completion Notice.pdf
Hobbs Cr - London St/Antrim Rd   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2020
Estimated to end Late October 2020
Approx. % completed 70
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Hudson St - Clarence Av/Chevrier Bv   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Huntingdale Rd - Fairhaven Rd/Fairhaven Rd   View Map
Facility type Street
Type of work TBO
Estimated to start September 7/2020
Estimated to end Late September 2020
Approx. % completed Complete
Consultant KGS Group Limited
Document
2020 Construction Notice_Huntingdale Road.pdf
Inglewood St - Silver Av / Ness Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 19/2020
Estimated to end Late June 2020
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor J.C. Paving Ltd.
Document
2020 Construction Notice_Inglewood Street.pdf
Inkster Bv - McKenzie St / Arlington St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2021
Estimated to end Summer 2021
Approx. % completed Planned
Inkster Bv/70m West of Lansdowne Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Jamison Av - Roch St/Henderson Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2020
Estimated to end Mid June 2020
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Document
2020 Construction Notice_Jamison Avenue.pdf
Jefferson Av/65m West of Watson St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Jefferson Av/McPhillips St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
John Brebeuf Pl - Lanark St / Beaverbrook St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start June 8/2020
Estimated to end Late June 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Document
2020 Construction Notice_John Brebeuf Place.pdf
John Forsyth Rd - Baisinger Dr/Dakota St   View Map
Facility type Street
Type of work TBO
Estimated to start Spring 2021
Estimated to end Summer 2021
Approx. % completed 0
Consultant KGS Group Limited
John Taylor Pl - Tu Pelo Av / Werrell Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start September 18/2020
Estimated to end Mid October 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2020 Construction Notice_John Taylor Place.pdf
Johnson Av W - Levis St / Henderson Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 12/2020
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Additional information Click here
Jubilee Av - Osborne St / Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Additional information Click here
Kairistine Ln - Kinver Av/Dexter St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 19/2020
Estimated to end Mid June 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Document
2020 Construction Notice_Kairistine Lane.pdf
Keewatin St - Adsum Dr / Inkster Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Keewatin St - Selkirk Av / Logan Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2021
Estimated to end Summer 2021
Approx. % completed Planned
Kenaston Bv - Taylor Av / Sterling Lyon Pw   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Complete
Consultant Dillon Consulting Limited
Kildonan Settlers Bridge   View Map
Facility type Bridge
Type of work Maintenance
Estimated to start Winter 2019
Estimated to end Summer 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Killarney St - Fermor Av/Glen Av   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2020
Estimated to end Fall 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
King Edward St - Hyde Av / Logan Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2021
Estimated to end Summer 2021
Approx. % completed Planned
King Edward St - Hyde Av / Logan Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2021
Estimated to end Summer 2021
Approx. % completed Planned
King Edward St - Jefferson Av/Coatstone Dr   View Map
Facility type Sidewalk
Type of work New - Sidewalk Construction
Estimated to start Mid May 2020
Estimated to end Fall 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Kirkfield St - Portage Av / McBey Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 1/2020
Estimated to end Late October 2020
Approx. % completed 90
Consultant WSP Canada Inc
Contractor J.C. Paving Ltd.
Document
2020 Construction Notice_Kirkfield Street.pdf
Lafortune By - Brixford Cr/Brixford Cr   View Map
Facility type Street
Type of work TBO
Estimated to start October 12/2020
Estimated to end Late October 2020
Approx. % completed Complete
Consultant KGS Group Limited
Document
2020 Construction Notice_Lafortune Bay.pdf
Lagimodiere Bv (800m East Of) / Fermor Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Lagimodiere Bv - Fermor Av / Cottonwood Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Summer 2023
Approx. % completed Planned
Lagimodiere Bv - Regent Av W / Almey Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Mid May 2020
Estimated to end Late October 2020
Approx. % completed 30
Lagimodiere Bv - Springfield Rd / 200m S of Headmaster Rw   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2021
Estimated to end Summer 2021
Approx. % completed Planned
Lagimodiere Bv - Springfield Rd / 200m S of Headmaster Rw   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2021
Estimated to end Summer 2021
Approx. % completed Planned
Lagimodiere Bv SB - Reenders Dr / Regent Av W   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2021
Estimated to end Summer 2021
Approx. % completed Planned
Lagimodiere Bv/Fermor Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Lakeglen Dr - Lake Lindero Rd/Lake Lindero Rd   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2020
Estimated to end Fall 2020
Approx. % completed Planned
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Lakeside Dr - Augusta Dr / Forest Lake Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 6/2020
Estimated to end Mid October 2020
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Borland Construction Inc.
Document
2020 Construction Notice_Lakeside Drive.pdf
Lakeside Dr - Forest Lake Dr / Chancellor Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 6/2020
Estimated to end Mid October 2020
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Borland Construction Inc.
Document
2020 Construction Notice_Lakeside Drive.pdf
Lanark St - Corydon Av/John Brebeuf Pl   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 15/2020
Estimated to end Late August 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Laurel By - Hillhouse Rd / Diplomat Dr   View Map
Facility type Street
Type of work TBO
Estimated to start Spring 2021
Estimated to end Summer 2021
Approx. % completed 0
Consultant KGS Group Limited
Lavalee Rd/St Annes Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Lawndale Av / Birchdale Av - Kirkdale St / Highfield St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Asphaltec Paving
Document
2020 Construction Notice_Birchdale Avenue_Lawndale Avenue_Alley.pdf
Leila Av - McPhillips St / McGregor St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Leila Av/ 60m East of Simkin Dr   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Leila Ave - McPhillips St / McGregor St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Leila Ave - McPhillips St / McGregor St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Lilac St - Mulvey Av/Fleet Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 15/2020
Estimated to end Late July 2020
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor J.C. Paving Ltd.
Document
2020 Construction Notice_Lilac Street.pdf
Lindenwood Dr W - Forestgate Av/Lindmere Dr   View Map
Facility type Street
Type of work TBO
Estimated to start September 7/2020
Estimated to end Late October 2020
Approx. % completed 50
Consultant KGS Group Limited
Document
2020 Construction Notice_Lindenwood Drive West.pdf
Logan Av - Disraeli Fwy / Main St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Summer 2023
Approx. % completed Planned
Logan Av - Keewatin St / Dee St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start June 4/2020
Estimated to end Late June 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Document
2020 Construction Notice_Logan Street Sidewalk.pdf
Lombard Av / Westbrook St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Complete
Consultant HTFC Planning and Design
Lorette Av - Harrow St / Guelph St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start May 19/2020
Estimated to end Early June 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Document
2020 Construction Notice_Lorette Avenue.pdf
Lyndale Dr - Norwood Bridge / Walmer St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 29/2020
Estimated to end Late August 2020
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Wintec Building Services Inc.
Document
2020 Construction Notice_Lyndale Drive.pdf
Main St - Higgins Av / Lombard Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 7/2020
Estimated to end Mid August 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Maple Leaf Construction Ltd.
Document
2020 Construction Notice_Main Street.pdf
Malden Cs - Mannerley Wy/Mannerley Wy   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 10/2020
Estimated to end Late September 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Document
2020 Construction Notice_Malden Close.pdf
Manitoba Av - Sheppard St / Chudley St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 19/2020
Estimated to end Late June 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2020 Construction Notice_Manitoba Avenue.pdf
Maple St N - Hallet St/Sutherland Av   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2020
Estimated to end Mid August 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Marlow Ct - Mapleglen Dr/Mapleglen Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 1/2020
Estimated to end Mid July 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Document
2020 Construction Notice_Marlow Court.pdf
Maryland St - Broadway / Fawcett Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 1/2020
Estimated to end Early September 2020
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Nelson River Construction
Additional information Click here
Document
2020 Construction Notice_Maryland Street.pdf
Maryland St - Fawcett Av / Maryland Bridge   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 1/2020
Estimated to end Late August 2020
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Nelson River Construction
Additional information Click here
Document
2020 Construction Notice_Maryland Street.pdf
Maurepas Cr - Edgeland Bv/Edgeland Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 15/2020
Estimated to end Fall 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Maybank Dr - Marshall Cr / Donnelly St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 13/2020
Estimated to end Mid September 2020
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Borland Construction Inc.
Document
2020 Construction Notice_Maybank Drive.pdf
McDowell Dr - 47 McDowell Dr/Westlund Wy   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 24/2020
Estimated to end Mid September 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Document
2020 Construction Notice_McDowell Drive.pdf
McGregor St - Church Av / Mountain Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Summer 2023
Approx. % completed Planned
McGregor St - Seven Oaks Av / McAdam Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Summer 2023
Approx. % completed Planned
McPhillips St - Machray Av / Mountain Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Summer 2023
Approx. % completed Planned
Meredith By - Templeton Av / Templeton Av   View Map
Facility type Street
Type of work TBO
Estimated to start Spring 2021
Estimated to end Summer 2021
Approx. % completed 0
Consultant KGS Group Limited
Millbrook Ln - Northcliffe Dr/Fairview Dr   View Map
Facility type Street
Type of work TBO
Estimated to start September 7/2020
Estimated to end Late September 2020
Approx. % completed Complete
Consultant KGS Group Limited
Document
2020 Construction Notice_Milllbrook Lane.pdf
Minto St - Armoury Av / St Mathews Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 22/2020
Estimated to end Mid October 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Molgat Av - St Marys Rd/End   View Map
Facility type Street
Type of work TBO
Estimated to start September 28/2020
Estimated to end Late October 2020
Approx. % completed Complete
Consultant KGS Group Limited
Document
2020 Construction Notice_Molgat Avenue.pdf
Moray St - Ness Av / Portage Av   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Complete
Consultant Dillon Consulting Limited
Morley Av - Eccles St / Fisher St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start June 8/2020
Estimated to end Early July/2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Document
2020 Construction Notice_Morley Avenue.pdf
Morrison St - Buttercup Av / Arrowwood Dr N   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 18/2020
Estimated to end Mid August 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Document
2020 Construction Notice_Morrison Street.pdf
Mountain Av - Arlington St/Airlies St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Mountain Ave - Arlington St / McPhillips St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Mountbatten Av - Bower Bv/Shaftesbury Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 15/2020
Estimated to end Mid August 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Munroe Av - Raleigh St / Henderson Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 12/2020
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Additional information Click here
Munroe Av - Raleigh St / Henderson Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 12/2020
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Additional information Click here
Myles Robinson Wy - Desjardins Dr/Island Lakes Dr   View Map
Facility type Street
Type of work TBO
Estimated to start Spring 2021
Estimated to end Summer 2021
Approx. % completed 0
Consultant KGS Group Limited
Nairn Av - Stadacona St / Watt St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2021
Estimated to end Summer 2021
Approx. % completed Planned
Nairn Overpass   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Complete
Newcroft Rd / Shamrock Dr   View Map
Facility type Sidewalk
Type of work New - Sidewalk Construction
Estimated to start September 2/2020
Estimated to end Late September 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Document
2020 Construction Notice_Shamrock Drive_Newcroft Road_Sidewalk.pdf
Northwest Hydro Corridor Pathway - Leila Av / Church Av   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Norwood & Main Street Bridge   View Map
Facility type Bridge
Type of work Maintenance
Estimated to start June 15/2020
Estimated to end August 28/2020
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Norwood & Main Street Bridge   View Map
Facility type Bridge
Type of work Maintenance
Estimated to start June 15/2020
Estimated to end August 28/2020
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Notre Dame Av/McPhillips St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Oakhurst Cr - Monty Hall Dr/Monty Hall Dr   View Map
Facility type Street
Type of work TBO
Estimated to start Spring 2021
Estimated to end Summer 2021
Approx. % completed 0
Consultant KGS Group Limited
Oakleaf Dr - Avalon Rd/Riel Av   View Map
Facility type Street
Type of work TBO
Estimated to start Spring 2021
Estimated to end Summer 2021
Approx. % completed 0
Consultant KGS Group Limited
Oakridge By - Metz St / Metz St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 11/2020
Estimated to end Early October 2020
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Document
2020 Construction Notice_Oakridge Bay.pdf
Olive St - Braintree Cr / Ness Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 1/2020
Estimated to end Late July 2020
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor J.C. Paving Ltd.
Document
2020 Construction Notice_Olive Street.pdf
Palliser Av - Mount Royal Rd/Mount Royal Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 19/2020
Estimated to end Late June 2020
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor J.C. Paving Ltd.
Document
2020 Construction Notice_Palliser Avenue.pdf
Palms Bv - Garden Grove Dr/Burrows Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 19/2020
Estimated to end Mid June 2019
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Document
2020 Construction Notice_Palms Boulevard.pdf
Pandora Ave E - Day St / Wayoata St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Park Lane Av - East End / King Edward St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 19/2020
Estimated to end Late June 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2020 Construction Notice_Park Lane Avenue.pdf
Park Lane Av - Hekla Av / Park Lane Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Park Terrace Dr - Beaverhill Bv/Beaverhill Bv   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2020
Estimated to end Fall 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Pembina Hw - De Leglise Av / Ducharme Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2021
Estimated to end Summer 2021
Approx. % completed Planned
Additional information Click here
Pembina Hw - Ducharme Av / De Leglise Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2021
Estimated to end Summer 2021
Approx. % completed Planned
Additional information Click here
Pembina Hw - McGillivray Bv / Chevrier Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Additional information Click here
Pembina Hw - McGillivray Bv / Chevrier Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Additional information Click here
Pincarrow Pt - Scurfield Bv/Eglinton Cr   View Map
Facility type Street
Type of work TBO
Estimated to start Spring 2021
Estimated to end Summer 2021
Approx. % completed 0
Consultant KGS Group Limited
Pioneer Av - Westbrook St / Main St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Point Rd - Waterford Av / Riverwood Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start June 8/2020
Estimated to end Late June 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Document
2020 Construction Notice_Point Road.pdf
Portage Av - David St / St Charles St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Portage Av - David St / St Charles St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Portage Av - Main St / Memorial Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Portage Av - Main St / Memorial Bv   View Map
Facility type Street
Type of work TBO
Estimated to start July 6/2020
Estimated to end Early September 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Bituminex Paving Ltd
Additional information Click here
Document
2020 Construction Notice_Portage Avenue.pdf
Portage Av - Main St / Memorial Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Portage Av - Woodlawn St / Century St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Portage Av -St James St / Moorgate St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2021
Estimated to end Summer 2021
Approx. % completed Planned
Portage Av/Wolseley Av - Clifton St/Telfer St S   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start August 3/2020
Estimated to end Mid September 2020
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Asphaltec Paving
Document
2020 Construction Notice_Clifton Street_Telfer Street_Alley.pdf
Portage Ave WB - David St / St Charles St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2021
Estimated to end Summer 2021
Approx. % completed Planned
Powers St - Leila Av / Partridge Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start September 14/2020
Estimated to end Late October 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Document
2020 Construction Notice_Powers Street.pdf
Provencher Bv at Seine River   View Map
Facility type Bridge
Type of work Maintenance
Estimated to start Winter 2019
Estimated to end Summer 2020
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor ArmCon Ltd.
Radcliffe Rd - Oberlin Rd / Dalhousie Dr   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start July 22/2020
Estimated to end Mid August 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Document
2020 Construction Notice_Radcliffe Road.pdf
Raleigh St - Munroe Av/Chalmers Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 19/2020
Estimated to end Late July 2020
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Document
2020 Construction Notice_Raleigh Street.pdf
Rapid Transit Corridor - Phase 2   View Map
Facility type Rapid Transit Corridor
Type of work New - Rapid Transit Corridor
Estimated to start Summer 2016
Estimated to end Summer 2020
Approx. % completed 75
Consultant Plenary Roads
Contractor PCL
Additional information Click here
Redwood Av - Salter St / Main St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Regent Av W - Plessis Rd / Rougeau Av   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start Summer 2021
Estimated to end Summer 2021
Approx. % completed Planned
Regent Av W - Plessis Rd / Rougeau Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2021
Estimated to end Summer 2021
Approx. % completed Planned
Regent Av W/Lagimodiere Bv   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Renfrew St - 575 Renfrew St / John Brebeuf Pl   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start June 8/2020
Estimated to end Late June 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Document
2020 Construction Notice_Renfrew Street.pdf
River Av - Osborne St / Wellington Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Roblin Blvd - Berkley St / Dieppe Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Stantec Consulting Ltd
Additional information Click here
Roblin Blvd - Berkley St / Dieppe Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Stantec Consulting Ltd
Additional information Click here
Roblin Blvd - Dieppe St / PTH101   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 8/2020
Estimated to end Late October 2020
Approx. % completed 80
Consultant Stantec Consulting Ltd
Contractor Bituminex Paving Ltd
Additional information Click here
Document
2020 Construction Notice_Roblin Boulevard.pdf
Roblin Blvd - Dieppe St / PTH101   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 8/2020
Estimated to end Late October 2020
Approx. % completed 80
Consultant Stantec Consulting Ltd
Contractor Bituminex Paving Ltd
Additional information Click here
Document
2020 Construction Notice_Roblin Boulevard.pdf
Roblin Blvd - Dieppe St / PTH101   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 8/2020
Estimated to end Late October 2020
Approx. % completed 80
Consultant Stantec Consulting Ltd
Contractor Bituminex Paving Ltd
Additional information Click here
Document
2020 Construction Notice_Roblin Boulevard.pdf
Roblin Blvd - Grant Av / Fairmont Rd   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start June 10/2020
Estimated to end Late June 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Document
2020 Construction Notice_Roblin Sidewalk.pdf
Rosewarne Av - Kingston Rw / St Marys Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 27/2020
Estimated to end Mid September 2020
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Document
2020 Construction Notice_Rosewarne Avenue.pdf
Ross Av - Paulin St / Ellen St   View Map
Facility type Street
Type of work TBO
Estimated to start Spring 2021
Estimated to end Summer 2021
Approx. % completed 0
Consultant KGS Group Limited
Rougeau Av - Bournais Dr / Hatcher Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 25/2020
Estimated to end Mid July 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises
Document
2020 Construction Notice_Rougeau Avenue.pdf
Rupert Av - Main St/King St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 18/2020
Estimated to end Mid June 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Document
2020 Construction Notice_Rupert Street.pdf
Sabine Cr - Topaz Rd/Lumsden Av   View Map
Facility type Street
Type of work TBO
Estimated to start August 31/2020
Estimated to end Mid September 2020
Approx. % completed Complete
Consultant KGS Group Limited
Document
2020 Construction Notice_Sabine Crescent.pdf
Salter St - Cathedral Av / Slaw Rebchuk Bridge   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Additional information Click here
Salter St - Jefferson Av / Inkster Bv   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Summer 2023
Approx. % completed Planned
Sargent Av - Arlington St / Erin St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 4/2020
Estimated to end Fall 2020
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor J.C. Paving Ltd.
Additional information Click here
Document
2020 Construction Notice_Sargent Avenue.pdf
Sargent Av - Ashburn St/Strathcona St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start May 19/2020
Estimated to end Early June 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Document
2020 Construction Notice_Sargent Avenue Sidewalk.pdf
Sargent Av - Edmonton St / Furby St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Summer 2023
Approx. % completed Planned
Sargent Av - McMicken St/Langside St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start May 19/2020
Estimated to end Early June 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Document
2020 Construction Notice_Sargent Avenue Sidewalk.pdf
Sargent Av/Ellice Av - Ingersoll St/Sherburn St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start September 28/2020
Estimated to end Summer 2021
Approx. % completed 5
Consultant KGS Group Limited
Contractor Asphaltec Paving
Document
2020 Construction Notice_Sherburn Street_Ingersoll Street_Alley.pdf
Sargent Ave - Empress St / St James St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2021
Estimated to end Summer 2021
Approx. % completed Planned
Scurfield Park   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start Spring 2021
Estimated to end Summer 2021
Approx. % completed 0
Consultant City Of Winnipeg - Engineering Division
Selkirk Av - Main St / Salter St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Summer 2023
Approx. % completed Planned
Selkirk Av - Sheppard St/Buller St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 31/2020
Estimated to end Mid October 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Document
2020 Construction Notice_Selkirk Avenue.pdf
Selkirk Ave - Arlington St / McPhillips St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2021
Estimated to end Summer 2021
Approx. % completed Planned
Additional information Click here
Document
2020 Construction Notice - Selkirk Ave 1.pdf
Sharp Bv - Ness Av / Bruce Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 22/2020
Estimated to end Mid October 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Smith - Notre Dame / York Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Consultant AECOM Canada Ltd
Smith St - Notre Dame / Graham Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Consultant AECOM Canada Ltd
Southlawn Stroll - Bairdmore Bv/Bairdmore Bv   View Map
Facility type Street
Type of work TBO
Estimated to start September 21/2020
Estimated to end Late October 2020
Approx. % completed Complete
Consultant KGS Group Limited
Document
2020 Construction Notice_Southlawn Stroll.pdf
Southview Cr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 30/2020
Estimated to end Early August 2020
Approx. % completed Complete
Consultant WSP Canada Inc.
Document
2020 Construction Notice_Southview Crescent.pdf
Speers Rd - Elizabeth Rd / Betournay St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 29/2020
Estimated to end Mid August 2020
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Wintec Building Services Inc.
Document
2020 Construction Notice_Speers Road.pdf
Spring Meadow Cr - Plessis Rd/Plessis Rd   View Map
Facility type Street
Type of work TBO
Estimated to start September 7/2020
Estimated to end Late September 2020
Approx. % completed Complete
Consultant KGS Group Limited
Document
2020 Construction Notice_Spring Meadow Crescent.pdf
Springfield Rd - Gateway Rd / Brian St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 25/2020
Estimated to end Late July 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises
Document
2020 Construction Notice_Springfield Road.pdf
St Annes Rd - St Marys Rd / Fermor Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Summer 2023
Approx. % completed Planned
St David Rd - Havelock Av/Berrydale Av   View Map
Facility type Street
Type of work TBO
Estimated to start September 21/2020
Estimated to end Late October 2020
Approx. % completed Complete
Consultant KGS Group Limited
Document
2020 Construction Notice_St. David Road.pdf
St James St - 190m North of Ellice Av/Sargent Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 19/2020
Estimated to end June 25/2020
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Document
2020 Construction Notice_St. James Street.pdf
St James St - Dublin Av/Saskatchewan Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid May 2020
Estimated to end Fall 2020
Approx. % completed Complete
Consultant Stantec Consulting Ltd
Contractor Bayview Construction Ltd
Additional information Click here
St James St - Notre Dame Av / Omand's Creek   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2020
Estimated to end Fall 2020
Approx. % completed Complete
Consultant Stantec Consulting Ltd
Contractor Bayview Construction Ltd
Additional information Click here
St James St/Sargent Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited / Harris Holdings Ltd.
St Mary Av - Kennedy St/Memorial Bv   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start October 5/2020
Estimated to end Late October 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Document
2020 Construction Notice_St Mary Avenue Sidewalk.pdf
St Mary Av - Memorial Bv / Portage Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
St Mary Av - Memorial Bv / Portage Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
St Matthews Av - Ferry Rd/Berry St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid October 2020
Estimated to end Late October 2020
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Document
2020 Construction Notice_EB St. Matthews.pdf
St Matthews Av/Wolever Av - Garfield St N/Dominion St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start July 27/2020
Estimated to end Late September 2020
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Asphaltec Paving
Document
2020 Construction Notice_Dominion Street_Garfield Street_Alley.pdf
St. Vital Bridge over Red River   View Map
Facility type Bridge
Type of work Maintenance
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Complete
Consultant Tetra Tech Canada Inc
St. Vital Park   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 29/2020
Estimated to end Late September 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Stafford St - Corydon Ave/Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Consultant Stantec Consulting Ltd
Additional information Click here
Stafford St - Yale Av / Corydon Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Stewart St - Portage Av / Allard Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 22/2020
Estimated to end Early September 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Stockton Pl - Colchester By / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 22/2020
Estimated to end Late October 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Stradbrook Ave - Wellington Cr / Osborne St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Strood Av - Rothesay St/Henderson Hw   View Map
Facility type Street
Type of work TBO
Estimated to start September 8/2020
Estimated to end Late September 2020
Approx. % completed Complete
Consultant KGS Group Limited
Document
2020 Construction Notice_Strood Avenue.pdf
Stuart Av - Pentland St/Henderson Hw   View Map
Facility type Street
Type of work TBO
Estimated to start September 8/2020
Estimated to end Late September 2020
Approx. % completed Complete
Consultant KGS Group Limited
Document
2020 Construction Notice_Stuart Avenue.pdf
Sturgeon Rd - Ness Av / Hallonquist Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Sturgeon Rd - Ness Av / Hallonquist Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Tache Av - Darveau St/La Verendrye St   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2020
Estimated to end Late October 2020
Approx. % completed Complete
Consultant KGS Group Limited
Document
2020 Construction Notice_Tache Ave.pdf
Tanner St - Margaret Av / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 27/2020
Estimated to end Late October 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Taylor Ave - Harrow St/Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Consultant Stantec Consulting Ltd
Additional information Click here
Taylor Ave - Wilton St / Harrow St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Stantec Consulting Ltd
Additional information Click here
Taylor Ave - Wilton St / Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2020
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Stantec Consulting Ltd
Taylor Ave - Wilton St / Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Stantec Consulting Ltd
Additional information Click here
Taylor Ave - Wilton St / Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Stantec Consulting Ltd
Additional information Click here
Thatcher Dr - University Cr/Pembina Hw   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Thornhill By - Rochester Av/Rochester Av   View Map
Facility type Street
Type of work TBO
Estimated to start Spring 2021
Estimated to end Summer 2021
Approx. % completed 5
Consultant KGS Group Limited
Document
2020 Construction Notice_Thornhill Bay.pdf
Traverse Av - Dollard Bv/Marion St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Darco Enterprises Ltd.
Trowbridge By - Malmsbury Av/Knotsberry By   View Map
Facility type Street
Type of work TBO
Estimated to start Spring 2021
Estimated to end Summer 2021
Approx. % completed 0
Consultant KGS Group Limited
Document
2020 Construction Notice_Trowbridge Bay.pdf
Tyndall Park Path Renewal   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start June 1/2020
Estimated to end Mid July 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Document
2020 Construction Notice_Tyndall Park Pathway.pdf
Ulster St - Dalhousie Dr/Mapleridge Av   View Map
Facility type Street
Type of work TBO
Estimated to start Spring 2021
Estimated to end Summer 2021
Approx. % completed 0
Consultant KGS Group Limited
University Cr - Chancellor Matheson Rd / Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
University Cr - Pembina Hw / Sifton Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
University Cr - Sifton Rd / Chancellor Matheson Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Villeneuve Bv - Ducharme Av/Des Trappistes St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Wall St - Sargent Av / Notre Dame Ave   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Additional information Click here
Wall St - St Matthews Av / Sargent Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2021
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Additional information Click here
Walmer St/ Kirkdale St - Ferndale Av / Lawndale Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start June 8/2020
Estimated to end Mid July 2020
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2020 Construction Notice_Lawndale Avenue_Ferndale Avenue_Alley.pdf
Watt St - Chalmers Av / Munroe Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 11/2020
Estimated to end Fall 2020
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Additional information Click here
Document
2020 Construction Notice_Watt Street.pdf
Watt St - Chalmers Av / Munroe Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 11/2020
Estimated to end Fall 2020
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Additional information Click here
Document
2020 Construction Notice_Watt Street.pdf
Waverley St - Scurfield Bv/Chevrier Bv   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start September 14,2020
Estimated to end Late October 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Document
2020 Construction Notice_Waverley Street Multi-Use Pathway.pdf
Waverley St - Grandmont Bv/City Limit   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2020
Estimated to end Fall 2020
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Tri - Core Projects Ltd.
Wellington Av - Arlington St/Banning St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 15/2020
Estimated to end Mid August 2020
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor J.C. Paving Ltd.
Document
2020 Construction Notice_Wellington Avenue.pdf
Wellington Cr - Renfrew St/Lindsay St   View Map
Facility type Sidewalk
Type of work New - Sidewalk Construction
Estimated to start August 18/2020
Estimated to end Mid September 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Wellington Cr - River Av / Stradbrook Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
William Av - Arlington St / McPhillips St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Additional information Click here
William Stephenson Wy - Main St / Westbrook St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Summer 2022
Approx. % completed Planned
Wolever Av - Minto St / Wall St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 22/2020
Estimated to end Late September 2020
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Woodfield By - Cathcart St/Cathcart St   View Map
Facility type Street
Type of work TBO
Estimated to start September 18/2020
Estimated to end Late October 2020
Approx. % completed Complete
Consultant KGS Group Limited
Document
2020 Construction Notice_Woodfield Bay.pdf
Woodhaven Park Path   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start Mid May 2020
Estimated to end Summer 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Woodview By - Cathcart St/Woodview By   View Map
Facility type Street
Type of work TBO
Estimated to start September 7/2020
Estimated to end Late September 2020
Approx. % completed Complete
Consultant KGS Group Limited
Wynyard By - Southwell Rd/Manthorne Av   View Map
Facility type Street
Type of work TBO
Estimated to start Spring 2021
Estimated to end Summer 2021
Approx. % completed 0
Consultant KGS Group Limited
Yale Av E - Roanoke St/Kanata St   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2020
Estimated to end Fall 2020
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services

Disclaimer and Indemnity:

The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.

The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.

By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.


Was this information helpful?

How can we make this web page better?

Information collected will be used to improve our website. Do not use this form to submit a request for service or information because it will not be forwarded to departments for response. To submit a request for service or information, contact 311.

This form is not intended to collect personal information; however, any personal information you choose to include in your comments is collected by the City of Winnipeg under the authority of section 36(1)(b) of the Freedom of Information and Protection of Privacy Act for the purpose of improving our website and will not be used or disclosed for any other purposes, except as authorized by law. Contact the Corporate Access and Privacy Officer by mail (City Clerk’s Department, Susan A. Thompson Building, 510 Main Street, Winnipeg MB, R3B 1B9) or by telephone (311) if you have any questions about the collection of this information.

Ces renseignements sont-ils utiles?

Comment pourrait-on améliorer cette page Web?

Les renseignements recueillis serviront à l’amélioration de notre site Web. Prière de ne pas se servir de ce formulaire pour soumettre une demande de service ou de renseignements, car la demande ne sera pas transmise au service en question. Pour soumettre une demande de service ou de renseignements, veuillez communiquer avec le 311.

Le présent formulaire ne vise pas à recueillir des renseignements personnels. Cependant, les renseignements personnels que vous choisissez d’inclure dans vos commentaires sont recueillis par la Ville de Winnipeg en conformité avec l’alinéa 36(1)b) de la Loi sur l’accès à l’information et la protection de la vie privée dans le but d’améliorer son site Web et ne seront ni utilisés ni divulgués pour d’autres raisons, sauf dans les cas où cela est autorisé par la loi. Communiquez avec l’agent de l’accès à l’information et de la protection de la vie privée de la Ville par courrier au Bureau du greffier, immeuble Susan-A.-Thompson, 510, rue Main, Winnipeg (Manitoba) R3B 1B9, ou par téléphone au 311 si vous avez des questions sur la collecte de ces renseignements.