Site Accessibility Information Access Key 1 to Skip to Top Navigation Access Key 2 to Skip to the Three One One link Access Key 3 to Skip to City of Winnipeg Main Menu Access Key 4 to Skip to Left Navigation Menu Access Key 5 to Skip to Content area Access Key 6 to Skip to Right Sidebar content area Access Key 7 to Skip to Footer Links
City of Winnipeg
|  Link to the City of Winnipeg French websiteFrançais  |
Until Election Day
on October 24

Public Works

Disraeli Bridges Project

Project Timeline

The first stages of the Disraeli Bridges Project--public consultation, procurement of the private-sector service provider, finalization of design concepts--have been completed.

Following are the timelines for significant project milestones:

Remainder of 2010: Detailed design, material delivery and environmental permitting
January 2011: Start river bridge construction
March 2011: Start construction of overpass across CP Rail mainline
Late 2012: New vehicular bridge and overpass open to traffic; start demolition of old bridge, and begin construction of Active Transportation bridge
August 2013: Active Transportation bridge open and landscaping completed
   