Site Accessibility Information Access Key 1 to Skip to Top Navigation Access Key 2 to Skip to the Three One One link Access Key 3 to Skip to City of Winnipeg Main Menu Access Key 4 to Skip to Left Navigation Menu Access Key 5 to Skip to Content area Access Key 6 to Skip to Right Sidebar content area Access Key 7 to Skip to Footer Links
Public Works

Osborne Street Bridge Rehabilitation Project

This project is now complete.

Traffic Management Plan

A similar traffic management plan to that successfully implemented in Phase 1 is planned. From late March to late August 2012, there will be two southbound traffic lanes and one northbound lane, except for morning rush hour when one lane will be reversed, making two northbound lanes and one southbound lane.

Traffic Management Plan during Construction
Late April to late June 2012
(Late March to late April and Late June to late August similar)

 
Thumbnail image of Traffic Management Plan, May to August 2012. Select this image to see a full-size version.
Select image for larger version
Measures to aid traffic flow and safety include

Late March to late April and late June to late August:
  • No left turns onto Roslyn Road from Osborne Street in either direction.
  • Right turns for Osborne Street southbound traffic permitted at Mostyn.
  • Left turns for northbound Osborne Street traffic permitted at Broadway.
  • Left turns from northbound Osborne Street traffic onto Mostyn permitted for emergency vehicles only.
  • Transit stops remain at existing locations.
  • No diamond lane for southbound traffic on Osborne Street.
Late April to late June:
  • No left turns onto Roslyn Road from Osborne Street in either direction.
  • No traffic permitted on Mostyn except emergency vehicles.
  • No northbound left turn from Osborne Street onto Broadway.
  • Bus stops for northbound and southbound Osborne in front of the Great West Life Building will be removed.
  • No diamond lane for southbound traffic on Osborne.
  • Direct access maintained for Great West Life and Shell gas station.

Beginning in late August to mid-October, two lanes will be available for both northbound and southbound traffic and left turns for northbound traffic will be permitted at Broadway. Traffic restrictions will continue on Mostyn, the diamond lane for southbound traffic on Osborne will not be in effect and Transit stops will return to existing locations.

Traffic Management Plan during Construction
Late August to Late October 2012

Thumbnail image of Traffic Management Plan, August to October 2012. Select this image to see a full-size version.
Select image for larger version

Pedestrian and Cyclist Access

The east sidewalk over the bridge will stay open throughout construction. Pedestrian and cyclist access and crossings will be clearly signed as they are adjusted during construction.

Pedestrian and cyclist traffic crossing Osborne Street north of the bridge can use the signalized crossing at Broadway Avenue or the underbridge crossing on the north bank of the river, when it is available. In 2011, the underbridge crossing level was raised as high as possible to prevent closing during high water levels of the Assiniboine River. The crossing has a roof for protection from construction debris.

Street-level at Assiniboine Avenue and Mostyn Place is a construction zone, and is unsafe for pedestrians. The signalized crossing for pedestrians and cyclists will be operational once construction concludes and sidewalks are completed.

Below are PDF maps showing access for pedestrians and cyclists during construction:

Last update: January 8, 2020
Error processing SSI file

Was this information helpful?

How can we make this web page better?

Information collected will be used to improve our website. Do not use this form to submit a request for service or information because it will not be forwarded to departments for response. To submit a request for service or information, contact 311.

This form is not intended to collect personal information; however, any personal information you choose to include in your comments is collected by the City of Winnipeg under the authority of section 36(1)(b) of the Freedom of Information and Protection of Privacy Act for the purpose of improving our website and will not be used or disclosed for any other purposes, except as authorized by law. Contact the Corporate Access and Privacy Officer by mail (City Clerk’s Department, Susan A. Thompson Building, 510 Main Street, Winnipeg MB, R3B 1B9) or by telephone (311) if you have any questions about the collection of this information.

Ces renseignements sont-ils utiles?

Comment pourrait-on améliorer cette page Web?

Les renseignements recueillis serviront à l’amélioration de notre site Web. Prière de ne pas se servir de ce formulaire pour soumettre une demande de service ou de renseignements, car la demande ne sera pas transmise au service en question. Pour soumettre une demande de service ou de renseignements, veuillez communiquer avec le 311.

Le présent formulaire ne vise pas à recueillir des renseignements personnels. Cependant, les renseignements personnels que vous choisissez d’inclure dans vos commentaires sont recueillis par la Ville de Winnipeg en conformité avec l’alinéa 36(1)b) de la Loi sur l’accès à l’information et la protection de la vie privée dans le but d’améliorer son site Web et ne seront ni utilisés ni divulgués pour d’autres raisons, sauf dans les cas où cela est autorisé par la loi. Communiquez avec l’agent de l’accès à l’information et de la protection de la vie privée de la Ville par courrier au Bureau du greffier, immeuble Susan-A.-Thompson, 510, rue Main, Winnipeg (Manitoba) R3B 1B9, ou par téléphone au 311 si vous avez des questions sur la collecte de ces renseignements.

-->