Site Accessibility Information Access Key 1 to Skip to Top Navigation Access Key 2 to Skip to the Three One One link Access Key 3 to Skip to City of Winnipeg Main Menu Access Key 4 to Skip to Left Navigation Menu Access Key 5 to Skip to Content area Access Key 6 to Skip to Right Sidebar content area Access Key 7 to Skip to Footer Links
City of Winnipeg
|  Link to the City of Winnipeg French websiteFrançais  |

Public Works

Fee Schedule

For a Local Improvement

The following table outlines:

  • What types of local improvements are presently available;
  • The estimated cost per frontage foot;
  • The time period allowed to pay for the local improvements after construction.

RATES EFFECTIVE UNTIL January 1, 2018

LOCAL IMPROVEMENT

ESTIMATED COST PER FRONTAGE FOOT $

TERM YEARS

ESTIMATED RATE/LEVY PER FRONTAGE FOOT PER TERM YEAR

Asphalt Surface Roadways (Rural Areas Only With Ditches) 1

220.00

10

27.80

Boulevards – 12.5' to 20.5' wide 1

30.00 to 45.00

3

10.71 to 16.06

Concrete Sidewalk 5'x 4" (Depends if one or both sides of the street are subject to frontage levy) 1

40.00 to 80.00

5

8.86 to 17.72

Concrete Street Pavement 25'x 6" (including boulevards) 1

360.00

10

45.50

Concrete Street Pavement 25'x 6" (only) 1

320.00

10

40.44

Concrete Street Pavement 33'x 8" (including boulevards) 1

490.00

10

61.93

Concrete Street Pavement 33'x 8" (only) 1

455.00

10

57.50

Granular Surface Lanes 1

35.00

3

12.49

LDS (Laterals & Trunks)

95.00

20

7.79

LDS (Laterals)

40.00

20

3.28

LDS (Trunks)

55.00

20

4.51

Lane Lighting on Wood Poles 1

10.00

3

3.57

Lane Oiling (10' to 12') 1

15.00 to 18.00

1

15.00 to 18.00

Asphalt Lane Pavement – 10’ X 5” to 20’ x 5”1

50.00 to 100.00 2

10

6.32 to 12.64 2

Concrete Lane Pavement – 10'x 6" to 20'x 6" 1

150.00 to 250.00

20

12.29 to 20.49

Ornamental Lights – Lane 1

30.00

3

10.71

Ornamental Lights – Street 1

40.00

3

14.28

Road Oiling 20' - Type II 1

10.00

1

10.00

Wastewater Sewers 1

122.00

20

10.00

Watermains 1

97.00

10

12.26

(1) The rates for these improvements are estimated only. Actual assessments will be based on the average actual costs for similar improvements constructed in the same year. All other rates are fixed by by-law and represent the actual assessable rates.

(2) The estimated rates reflect the City subsidizing 50% of the estimated costs.

Example:

What is the estimated cost to construct a 14’ X 6” concrete lane pavement as a Local Improvement for a lot with 50’ of frontage?

50’ X $190/ft = $9,500.00 lump sum payment, or

50' X $15.67/ft = $783.50 per year for 20 years. 

What is the estimated subsidized cost to construct a 14' X 5" asphaltic concrete lane pavement as a Local Improvement for a lot with 50' of frontage?

50’ X $70/ft = $3,500.00 lump sum payment, or

50' X $8.85ft = $442.50 per year for 10 years. 

Click here for information on the Local Improvement (By-Law 98/72)