Disraeli Bridges Project

Project Timeline

The first stages of the Disraeli Bridges Project – public consultation, procurement of the private-sector service provider, finalization of design concepts – have been completed.

Following are the timelines for significant project milestones:

Remainder of 2010: Detailed design, material delivery and environmental permitting
January 2011: Start river bridge construction
March 2011: Start construction of overpass across CP Rail mainline
Late 2012: New vehicular bridge and overpass open to traffic; start demolition of old bridge, and begin construction of Active Transportation bridge
August 2013: Active Transportation bridge open and landscaping completed
   