Project Timeline
The first stages of the Disraeli Bridges Project – public consultation, procurement of the private-sector service provider, finalization of design concepts – have been completed.
Following are the timelines for significant project milestones:
| Remainder of 2010: | Detailed design, material delivery and environmental permitting |
| January 2011: | Start river bridge construction |
| March 2011: | Start construction of overpass across CP Rail mainline |
| Late 2012: | New vehicular bridge and overpass open to traffic; start demolition of old bridge, and begin construction of Active Transportation bridge |
| August 2013: | Active Transportation bridge open and landscaping completed |